Drawing the Line: In Tennessee, the Economic Loss Doctrine Does Not Apply to Contracts for Services
December 11, 2023 —
Gus Sara - The Subrogation StrategistIn Commercial Painting Co. v. Weitz Co. LLC, No. W2019-02089-SC-R11-CV, 2023 Tenn. LEXIS 39 (Weitz), the Supreme Court of Tennessee (Supreme Court) considered whether the economic loss doctrine barred the plaintiff’s claims for fraud, negligent misrepresentation and punitive damages arising out of a contract with the defendant for construction services. The court held that the economic loss doctrine only applies to product liability cases and does not apply to claims arising from contracts for services. This case establishes that, in Tennessee, the economic loss doctrine does not bar tort claims in disputes arising from service contracts.
In Weitz, defendant, Weitz Co. LLC (Weitz), was the general contractor for a construction project and hired plaintiff Commercial Painting Co. (Commercial) as a drywall subcontractor. Weitz refused to pay Commercial for several of its payment applications, claiming that the applications were submitted untimely and contained improper change order requests. Commercial filed a lawsuit against Weitz seeking over $1.9 million in damages, alleging breach of contract, unjust enrichment, enforcement of a mechanic’s lien, and interest and attorney’s fees under the Prompt Pay Act of 1991. Weitz filed a counterclaim for $500,000 for costs allegedly incurred due to Commercial’s delay and defective workmanship. In response, Commercial amended its complaint to add claims for fraud, intentional and negligent misrepresentation, rescission of the contract and $10 million in punitive damages. Commercial alleged that Weitz received an extension of the construction schedule but fraudulently withheld this information from Commercial and continued to impose unrealistic deadlines.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Real Property Alert: Recording Notice of Default as Trustee Before Being Formally Made the Trustee Does Not Make Foreclosure Sale Void
February 18, 2015 —
Krsto Mijanovic and Annette F. Mijanovic – Haight Brown & Bonesteel LLPIn Ram, et al. v. OneWest Bank, FSB, et al. (filed 2/6/15, No. A139055), the California Court of Appeal held that a nonjudicial foreclosure sale is not void merely because the notice of default was recorded by an entity who had not yet been substituted as trustee. The court also held that because the sale was voidable, rather than void, the plaintiffs were required to allege an ability and willingness to tender their debt in addition to alleging that they were prejudiced by the irregularity in the foreclosure process.
Plaintiffs were borrowers who purchased a home subject to a deed of trust. After they defaulted on their loan, nonjudicial foreclosure proceedings were initiated, and the beneficiary of the deed of trust, OneWest Bank, FSB ("OneWest"), purchased the property at the foreclosure sale. Plaintiffs sued OneWest and other entities for wrongful foreclosure, alleging that the sale was void because the entity identified as the trustee on the notice of default, Aztec Foreclosure Corporation ("Aztec"), had not been formally substituted as trustee until after the notice of default was recorded. The trial court sustained OneWest's demurrer and plaintiff appealed.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP and
Annette F. Mijanovic, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Mijanovic may be contacted at amijanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Preparing For and Avoiding Residential Construction Disputes: For Homeowners and Contractors
September 18, 2023 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Construction Law Musings, we welcome a great friend. Scott Wolfe Jr. (@scottwolfejr)is a construction attorney in Louisiana, Washington and Oregon, and is the founding member of the construction practice Wolfe Law Group. He authors the Construction Law Monitor. He is also the founder of the mechanic lien and preliminary notice filing service, Zlien, and the author of its Construction Lien Blog.
Residential construction disputes come in all shapes and sizes, but very typically have one thing in common: they can get very nasty.
This is understandable, especially in today’s economy. The homeowner is spending hard-earned money on something very personal to them, their home. They want it done right. The contractor is working on really tight margins, and with a diligent client.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Nine Firm Members Recognized as Super Lawyers or Rising Stars
June 29, 2017 —
Ceslie Blass - Ahlers & Cressman PLLCWhile we avoid using this blog as a platform for self-promotion, we recently received share-worthy distinctions, which both flatter and humble us. We invite you, our loyal readers, to celebrate in our success, which in great measure is due to you.
John P. Ahlers, one of the firm's founding partners, was ranked third overall across all practicing industries in Washington 2017 Super Lawyers and founding partner Paul R. Cressman, Jr. was ranked in the Top 100. The following other firm members were also recognized as Super Lawyers: Founding partner Scott R. Sleight, Bruce A. Cohen (Partner), Brett M. Hill (Partner), and Lawrence Glosser (Partner). In addition, Ryan W. Sternoff (Partner), James R. Lynch (Partner), Tymon Berger (Associate), and Lindsay (Taft) Watkins (Associate) were selected as Super Lawyers Rising Stars. Over half of the firm's lawyers received Super Lawyers distinction.
Read the court decisionRead the full story...Reprinted courtesy of
Ceslie Blass, Ahlers & Cressman PLLC
Four Common Construction Contracts
August 26, 2015 —
Garret Murai – California Construction Law BlogLike Baskin Robins, construction contracts come in a variety of different flavors although, thankfully, significantly fewer than 31. Here are four of the more common types of construction contracts between project owners and contractors:
Fixed Price
Fixed price construction contracts, also commonly referred to as “lump sum” or “stipulated sum” contracts, are the most common types of construction contracts. As its name suggests, under a fixed price contract a contractor agrees to construct a project for a “fixed” or agreed upon price.
1.
Benefits: Fixed price construction contracts provide price predictability for project owners because absent changes in the scope of work, unforeseen conditions, or other circumstances which might cause the “fixed” price of the contract to go up or down, the contractor is required to complete the work for the agreed upon price.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Wendel Rosen Construction Attorneys Recognized by Super Lawyers and Best Lawyers
August 30, 2017 —
Wendel Rosen Black & Dean LLP - California Construction Law BlogTwo members of Wendel Rosen’s
Construction Practice Group were recognized recently.
Garret Murai was selected for inclusion in the 2017 list of Northern California Super Lawyers and
Matthew Graham was selected for inclusion in
The Best Lawyers in America© 2018 edition. Garret Is co-chair of the firm’s Construction Practice Group and Matt is a 30+ year veteran of construction law.
Read the court decisionRead the full story...Reprinted courtesy of
NYC Condo Skyscraper's Builder Wins a Round -- With a Catch
November 15, 2017 —
Oshrat Carmiel - BloombergThe battle over whether an 800-foot condo tower planned for Manhattan’s East Side can be built to its full height took a step forward Wednesday -- with city officials saying both yes, and no.
A years-long neighborhood lobbying effort to cap the height of new towers near the East 50s riverfront won an endorsement Wednesday from the planning commission, which agreed to rezone the area in a way that would make skyscraping condo towers impossible to build. But commissioners also voted to allow Sutton 58, the under-construction project that inspired the rezoning push, to be grandfathered in under the new law, and proceed as is.
Read the court decisionRead the full story...Reprinted courtesy of
Oshrat Carmiel, Bloomberg
Construction Litigation Roundup: “Apparently, It’s Not Always Who You Know”
December 16, 2023 —
Daniel Lund III - LexologyA respondent party in a pair of international arbitrations on the losing end of roughly $285,000,000 in adverse awards attacked the awards based upon arbitrator bias.
“If there is one bedrock rule in the law of arbitration, it is that a federal court can vacate an arbitral award only in exceptional circumstances. … The presumption against vacatur applies with even greater force when a federal court reviews an award rendered during an international arbitration.”
Applying the Federal Arbitration Act (according to the court, the international arbitrations were “seated” in the United States and fell under the New York Convention, such that the FAA is required to be the basis for vacatur efforts), the court examined assertions that certain alleged non-disclosures by the panel “concealed information related to the arbitrators’ possible biases and thereby ‘deprived [respondent] of [its] fundamental right to a fair and consensual dispute resolution process.’” The aggrieved party urged that one arbitrator’s undisclosed nomination of another arbitrator to serve as president of another arbitral panel – “a position that sometimes pays hundreds of thousands of dollars” – possibly influenced the second arbitrator to side with the first. Assertions were also levied that the arbitrators’ undisclosed work with the attorneys for the claimant in other arbitrations “allowed them to become familiar with each other, creating a potential conflict of interest.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com