New York Assembly Reconsiders ‘Bad Faith’ Bill
May 17, 2021 —
Copernicus T. Gaza, Adam Krauss, Robert S. Nobel, Craig Rokuson & Eric D. Suben - Traub LiebermanThe New York State Assembly is considering A07285, which creates a private right of action for bad faith “if the insurer unreasonably refuses to pay or unreasonably delays payment without substantial justification.” The bill was first introduced in 2013 but was reintroduced on May 3, 2021 and has received some recent attention. According to the bill, an insurer acts unreasonably when it (among other things):
- Fails to provide the claimant with accurate information regarding policy provisions relating to the coverage at issue; or
- Fails to effectuate in good faith a prompt, fair, and equitable settlement of a claim or portion of a claim and where the insurer failed to reasonably accord at least equal or more favorable consideration to its insured's interests as it did to its own interests, and thereby exposed the insured to a judgment in excess of the policy limits or caused other damage to a claimant; or
- Fails to provide a timely written denial of a claimant's claim, or portion thereof, with a full and complete explanation of such denial, including references to specific policy provisions wherever possible; or
Reprinted courtesy of
Copernicus T. Gaza, Traub Lieberman,
Adam Krauss, Traub Lieberman,
Robert S. Nobel, Traub Lieberman,
Craig Rokuson, Traub Lieberman and
Eric D. Suben, Traub Lieberman
Mr. Gaza may be contacted at cgaza@tlsslaw.com
Mr. Krauss may be contacted at akrauss@tlsslaw.com
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Mr Suben may be contacted at esuben@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court to Examine Arbitration Provisions in Several Upcoming Cases
December 09, 2011 —
CDJ STAFFGlen C. Hansen, writing on Abbott & Kinderman’s Land Use Law Blog looks at several cases pending before the California Supreme Court which ask if a developer can insist on arbitration of construction defect claims, based on provision in the CC&Rs. Currently, there is a split of opinions in the California appeals courts on the issue.
Four of the cases are in California’s Fourth Appellate District. In the earliest case, Villa Milano Homeowners Association v. Il Davorge, from 2000, the court concluded that the arbitration clause was sufficient to require that construction defect claims undergo arbitration. However, the Fourth Appellate District Court concluded in three later cases that the arbitration clauses did not allow the developer to compel arbitration. In two cases, argued in 2008 and 2010, the court concluded that to do otherwise would deprive the homeowners of their right to a jury trial. In the most recent case, Villa Vicenza Homeowners Association v. Nobel Court Development, the court decided that the CC&Rs did not create contractual rights for the developer.
The Second Appellate District Court came to a similar decision in Promenade at Playa Vista Homeowners Association v. Western Pacific Housing, Inc. In their decision, the court noted that CC&Rs could be enforced by homeowners and homeowners associations, but not developers.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
If I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
December 29, 2020 —
William L. Porter - Porter Law GroupIf I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
In general, the answer to the above questions is “Yes”, but only if you meet the following requirements:
- You must only release the mechanics lien itself, but not the “right” to a mechanics lien: There is an important distinction to be made between releasing a mechanics lien and releasing the right to a mechanics lien. Whether you do one or the other will depend on the specific language used in your release. In the case of Santa Clara Land Title Co. v. Nowack and Associates, Inc. (1991) 226 Cal. App.3d, 1558 a “release of mechanics lien” document was recorded TO THE County Recorder’s office which included a statement that the mechanics lien was “fully satisfied, released and discharged”. Based on this language, the court concluded that the mechanics lien claimant had waived its “right” to a further mechanics lien on the same property for the work in question. The court concluded that since the release stated that the claim was “fully satisfied” the right to mechanics lien on the project had forever been waived. The Nowak case can be distinguished from the case of Koudmani v. Ogle Enterprises, Inc., (1996) 47 Cal.App.4th 1650, where the release of mechanics lien only stated that the mechanics lien was “otherwise released and discharged” and not that it was “satisfied”. Based on the distinction drawn from the two cases, a simple mechanics lien release that only releases the mechanics lien itself, but not the “right” to a mechanics lien should be used. At the following link you will find a proper form to achieve this purpose: https://www.porterlaw.com/wp-content/uploads/2019/06/03PRI-Mechanics-Lien-Release.pdf
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Construction Defect Claim Not Timely Filed
January 27, 2020 —
Ryan M. Charlson - Florida Construction Law NewsIf construction defect claims are not timely filed, Florida Statutes provide design and construction companies with a formidable defense. As a case in point, a Miami-Dade Circuit Court Judge issued an Order granting summary judgment based on Fla. Stat. § 95.11(3)(c), Florida’s Statute of Limitations governing actions founded on alleged construction defects.
In Covenant Baptist Church, Inc. v. Vasallo Construction, Inc. and Lemartec Engineering & Construction Corporation, Plaintiff alleged multiple construction defects against two Defendants. The alleged defects were focused on water intrusion through the roofing systems and were known to the Plaintiff on August 13, 2006. However, four years and eleven months later, Plaintiff filed suit acknowledging that the building had “been plagued with water intrusion issues for a number of years,” and that Plaintiff’s complaints “regarding the water intrusion [had] been met largely with ‘band-aid’ type ineffective repairs.”
Lemartec Engineering & Construction Corporation (“Lemartec”), filed a Motion for Summary Judgment as to multiple counts and rested its Motion squarely on the shoulders of Florida’s four-year statute of limitations. Importantly, the statute begins to run “where there has been notice of an invasion of legal rights or a person has been put on notice of his right to a cause of action” Snyder v. Wernecke, 813 So.2d 213,216 (Fla 4th DCA 2002) (citing City of Miami v. Brooks, 70 So.2d 306 (Fla. 1954)). Plaintiff attempted to bypass the four-year nature of the statute by trying to classify the defects in question as latent.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & KissaneMr. Charlson may be contacted at
Ryan.Charlson@csklegal.com
NEHRP Recommendations Likely To Improve Seismic Design
November 09, 2020 —
Nadine M. Post - Engineering News-RecordCode-based earthquake engineering is on the verge of getting simpler, thanks to the National Earthquake Hazards Reduction Program’s recommendation to replace the traditional seismic hazard maps with an improved seismic hazards database. The recommendation is one of the most significant changes put forth in the 2020 update of the NEHRP seismic design provisions, which are the foundation for the prescriptive seismic design code for buildings and other structures.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Scaffolding Purchase Suggests No New Building for Board of Equalization
July 30, 2014 —
Beverley BevenFlorez-CDJ STAFFEmployees at California’s Board of Equalization spoke out against the Brown administration after the state purchased new scaffolding for the defect-riddled building, rather than finding a new facility, reported the Sacramento Bee. The existing scaffolding was leased for $10,000 per month, but the lease expired, prompting the purchase of new scaffolding for about $100,000.
The board’s Chairman Jerome Horton stated “that while the change may make financial sense in the short term, it sends a signal that the Department of General Services intends to keep Equalization’s 2,200 or so employees in the troubled building,” according to the Sacramento Bee.
Building problems include “toxic mold, defective elevators, leaking windows, corroded wastewater pipes, floods, and exterior glass panels that spontaneously break or pop off.” So far, $2.3 million has been paid “in connection with building-related employee injury claims” along with $60 million in repairs. However, an additional $115 million is estimated to completely fix the defects.
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Exists for Landlord as Additional Insured
September 03, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Court of Appeals determined the landlord was entitled to coverage as an additional insured under the tenant's policy. Selective Ins. Co. v. Erie Ins. Exch., 2014 Ind. App. LEXIS 365 (Ind. Ct. App. July 30, 2014).
Rangeline, LLC owned a warehouse. Rangeline negotiated a lease with Hammons Storage to store insulation manufactured by Knauf Insulation. Pursuant to requirements in the lease, Hammons secured liability coverage with Erie Insurance naming Rangeline as an additional insured.
After Hammons moved insulation into the warehouse for storage, the pipes of the sprinkler system burst, causing damage to the insulation. The cause of the loss was determined to be water from the system freezing, which led to the cast iron fittings cracking, causing the failure of the sprinkler heads.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
America’s Infrastructure Gets a D+
March 16, 2017 —
Garret Murai – California Construction Law BlogThe American Society of Civil Engineers (ASCE) has issued their 2017 Infrastructure Report Card, which assigns a letter grade to the nation’s infrastructure.
Our country’s grade in 2017? A disappointing D+.
Although, if you’re a glass half full kind of person (bless your soul) at least our grade didn’t fall since the last report card was issued in 2013, when our grade was a D+ as well.
In short, we suck. Although, apparently, we don’t suck evenly across the board.
ASCE has divided its cumulative GPA into grades for specific courses, if you will. Our transit systems received a grade of D-; our airports, dams, drinking water and waste water plants, inland waterways, levees and roads received a grade of D; our power plants, hazardous waste plants, public parks and schools received a grade of D+; our bridges, ports and solid waste plants a grade of C+, and our rail systems received a grade of B.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at