Construction Defect Notice in the Mailbox? Respond Appropriately
August 04, 2011 —
Douglas Reiser, Builders Council BlogRecently, I have seen a rash of ignored construction defect notices. What is a construction defect notice? It’s a statutorily required notice, sent from a homeowner to a contractor, listing a number of defects found at their property. If you get one, don’t ignore it.
The Revised Code of Washington includes a number of provisions intended for residential construction disputes. Among them is the “Notice to Customer” requirement in RCW 18.27.114, which can preempt a contractor’s lien rights, and the “Notice of Construction Defects” found in RCW 64.50.020.
The Notice of Construction Defects is a standard notice mandated by RCW 64.50, a chapter in the Revised Code of Washington, intended to provide a pre-litigation resolution process for contractors and consumers. The chapter applies only to those losses “caused by a defect in the construction of a residence or in the substantial remodel of a residence.”(See “Action” RCW 64.50.010).
Unfortunately, many contractors will simply ignore these notices or tell the homeowner to make a warranty claim. But, the notice actually provides a contractor with a forty-five (45) day window to alleviate the dispute.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Unpunished Racist Taunts: A Pennsylvania Harassment Case With No True 'Winner'
December 04, 2023 —
Richard Korman - Engineering News-RecordThe taunts started in the first days of Andre Pryce’s new job, camouflaged as joking. During the nine months of 2019 spent working as a drill rig hand, mostly in the woods in western Pennsylvania, for a contractor that also performs much construction-related drilling, he said coworkers filled his ears with racist insults.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Contract And IP Implications Of Design Professionals Monetizing Non-Fungible Tokens Comprising Digital Construction Designs
December 26, 2022 —
Colin C. Holley - ConsensusDocsThere is an emerging market that appears poised to increasingly provide opportunities to monetize architectural and other construction designs through the sale of non-fungible tokens (NFTs). Last year, artist Krista Kim reportedly made the first sale of a digital home design via an NFT marketplace, for over $500,000. With some NFTs selling for millions of dollars, monetizing digital designs is undoubtedly an enticing prospect for architects, engineers, and other design professionals. It is thus critical to understand the application of intellectual property rights to NFTs and to address those rights in contracts involving design professionals.
What is an NFT?
To understand the market for NFTs it is necessary to first understand blockchain technology. A blockchain is a decentralized system of recording information via a digital ledger of transactions duplicated and distributed across many computers. The manner in which each block of the ledger chain is created—using a cryptographic mathematical algorithm tied into the previous block, a timestamp, and transaction data—prevents it from being changed retroactively without a change to all subsequent blocks and consensus of the decentralized network.
An NFT is a ‘token’ secured to a blockchain. It can represent ownership of any item that is non-fungible, i.e., any item that has unique qualities that add value and make the item non-interchangeable. NFTs can take unlimited forms, including, for example, tokens representing unique artwork, music, fashion items, in-game items, essays, collectibles, memorabilia, furniture, and real estate.
Read the court decisionRead the full story...Reprinted courtesy of
Colin C. Holley, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Mr. Holley may be contacted at
cholley@watttieder.com
The ‘Sole Option’ Arbitration Provision in Construction Contracts
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFOn his Best Practices Construction Law blog, Matthew Devries discussed how the “at its sole option…has the right to demand arbitration” can “be a good provision if you are the party who has that option.”
For instance, Devries cites the case Archer Western Contractors, LLC v Holder Construction Company, where “the Georgia Court of Appeals recently affirmed the trial court’s decision to grant a contractor’s motion to compel arbitration with a ‘sole option’ provision.”
Devries stated that “it is important to review carefully the disputes clause in your construction contract to fully understand who has the right to demand arbitration and what rules will apply.”
Read the court decisionRead the full story...Reprinted courtesy of
A Teaming Agreement is Still a Contract (or, Be Careful with Agreements to Agree)
November 18, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed teaming agreements in this past here at Construction Law Musings. These agreements are most typically where one of two entities meets a contracting requirement but may not have the capacity to fulfill a contract on its own so brings in another entity to assist. However, these agreements are contracts and are treated as such here in Virginia with all of the law of contracts behind them.
One illustrative case occurred here in Virginia and was decided by the Virginia Supreme Court. That case is CGI Fed. Inc. v. FCi Fed. Inc. While this is not strictly a “construction” case, it helps lay out some of the pitfalls of teaming agreements in general.
In this case, the parties entered into a fairly typical small business (FCI) Big Business (CGI) teaming arrangement for the processing of visas for the State Department. The parties negotiated the workshare percentage (read payment percentage) should FCI get the work and the teaming agreement set out a framework for the negotiation of a subcontract between FCI, the proposed general contractor, and CGI, the proposed subcontractor. After a while working together, FCI submitted a proposal to the State Department and as part of the negotiations of this proposal, the work percentage for CGI was lowered in exchange for some management positions for CGI relative to the work by amendment to the original teaming agreement. However, one day later FCI submitted a proposal to the State Department that not only didn’t include the management positions, but further lowered CGI’s workshare.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Draft Federal Legislation Reinforces Advice to Promptly Notify Insurers of COVID-19 Losses
April 20, 2020 —
James Hultz - Newmeyer DillionInsurers across the country are nearly universally denying claims for business interruption stemming from the COVID-19 pandemic. Those denials have in turn been met with swift litigation and potential legislative action. The first business interruption coverage lawsuit related to COVID-19 was filed in New Orleans on March 16. There are now no less than 13 such cases nationwide and many more are likely to follow. Further, legislatures in at least seven states are considering legislation that would, to varying degrees, mandate business interruption coverage for COVID-19 losses, notwithstanding any seemingly contrary policy provisions.
From the early stages of the pandemic, we have consistently advised our clients to promptly notify their insurers of all COVID-19 related losses, even where coverage appeared uncertain. The deluge of coverage litigation and contemplated legislation could drastically alter how insurers handle COVID-19 claims. But policyholders who have failed to satisfy policy notice requirements could miss out on the benefits of those changes. Therefore, policyholders would be ill-advised to sit on the sidelines and wait it out.
Now, draft Federal legislation appears to add further impetus to instructions to “tender early.” The contemplated “Pandemic Risk Insurance Act of 2020” would reportedly devote billions of dollars of federal funds through a Department of Treasury administered reinsurance program designed to offset losses sustained by insurers who actually pay business interruption losses. The legislation is still taking shape but would reportedly create “a Federal program that provides for a transparent system of shared public and private compensation for business interruption losses resulting from a pandemic or outbreak of communicable disease.” President Trump is also reportedly pressuring insurers to provide business interruption coverage. The massive influx of federal funds and pressure from the White House could encourage insurers to reconsider denials of COVID-19 business interruption claims.
Read the court decisionRead the full story...Reprinted courtesy of
James Hultz, Newmeyer DillionMr. Hultz may be contacted at
james.hultz@ndlf.com
Seabold Construction Ties Demise to Dispute with Real Estate Developer
April 29, 2024 —
Richard Korman - Engineering News-RecordWhen Harry W. Seabold, co-founder and CEO of Seabold Construction, died unexpectedly in January 2023 at age 69, the Beaverton, Ore.-based general contractor, which had been in business since 1984, kept chugging along for a year on two adjacent North Portland apartment projects.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Few Homes Available to Reno Buyers, Plenty of Commercial Properties
January 22, 2013 —
CDJ STAFFSaying that "new home inventory does not exist," Mark Krueger of ArchCrest Commercial Partners tells the Reno Gazette Journal that this had lead to a problem, in that there are no homes for prospective buyers in the Reno and Sparks area. Adding to the problem is that investors are buying up resale homes with the intent of selling them at a profit later, which adds to the scarcity of available homes.
While the residential market is suffering from not enough homes to satisfy buyers, there are ample commercial properties. As a result, there are no plans for any additional retail, office, or industrial projects in the Reno area for 2013. Vacancy rates are expected to fall only slightly to 12.3% for industrial properties and 17.7% for retail properties.
Read the court decisionRead the full story...Reprinted courtesy of