Three-Year Delay Not “Prompt Notice,” But Insurer Not “Appreciably Prejudiced” Either, New Jersey Court Holds
November 04, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Harleysville Preferred Insurance Company v. East Coast Painting & Maintenance, LLC, 2019 U.S. Dist. LEXIS 135295 (D.N.J. Aug. 12, 2019) (East Coast Painting), the U.S. District Court for the District of New Jersey held that an insurer, which received notice of a bodily injury accident three years after it happened, was not “appreciably prejudiced” by such late notice, even as the court acknowledged notice three years later did not satisfy the policy’s “prompt notice” condition. The court also held that the policy’s “Operational Exclusion,” which excluded coverage for bodily injury arising out of the operation of “cherry pickers and similar devices,” did not apply because the accident arose out of the use of a “scissor lift,” which is not a device similar to a cherry picker.
East Coast Painting arose out of a Queens, New York bridge-painting project, during which an employee of the insured, East Coast Painting and Maintenance LLC was injured while “standing on a scissor lift mounted to the back of a truck,” owned and operated by East Coast. The employee sued various project-related entities which, in turn, joined East Coast as a defendant. East Coast sought coverage under its business auto policy, and the insurer agreed to defend the insured under a reservation of rights. The insurer subsequently sought a declaration that it did not owe coverage based on, among other things, the policy’s “Operational Exclusion,” and the insured’s failure to satisfy the policy’s “prompt notice” condition. The insurer moved for summary judgment on both of those bases, but the court in East Coast Painting denied the motion.
As for the insurer’s “prompt notice” defense, the court in East Coast Painting concluded that, the insured’s notice to the insurer was not prompt because it did not receive notice until three years after the accident. But, the court added, the inquiry does not end there. “[T]his Court must determine whether [the insurer] was appreciably prejudiced by that delay.” Reviewing the facts, the court held that the insurer was not “appreciably prejudiced,” even though during the three-year delay the lift truck was “not properly maintained” or “in the same condition it was at the time of the Accident.” The court observed that the insurer had “ample other evidence with which it can defend itself,” such as experts who inspected the lift truck and opined about the cause of the accident.” [Emphasis added.] Further, “there are multiple contemporaneous accident reports,” “a list of the East Coast employees on site at the time,” “photographs of the lift truck and its location when [the employee] was injured,” and “depositions of [the employee] and others regarding the events at issue.” Thus, the court held, the insurer was not prejudiced and summary judgment was inappropriate.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Additional Insured Is Covered Under On-Going Operations Endorsement Despite Subcontractor's Completion of Work
December 20, 2017 —
Tred Eyerly - Insurance Law HawaiiAlthough the homeowners did not own their homes when the subcontractors completed their work, the general contractor was still covered as an additional insured for the homeowners' suits based on the ongoing operations endorsement in the subcontractors' policies. McMillin Mgmt. Servs. v. Fin. Pac. Ins. Co., 2017 Cal. App. LEXIS 1000 (Cal. Ct. App. Nov. 14, 2017).
McMillin was the developer and general contractor for the project. Among the subcontractors were Martinez Construction Concrete Contractor, Inc. and Rozema Corporation. Martinez performed concrete flatwork between 2003 and November 2005. Rozema performed lath and stucco work between March 2003 and October 2005.
Lexington issued CGL policies to Martinez and Rozema. McMillin was an additional insured under both policies, "but only with respect to liability arising out of your [i.e., Martinez's or Rozema's] ongoing operations performed for [McMillin]." An exclusion provided that the insurance did not apply to property damage occurring after the insured subcontractor had completed operations on behalf of the additional insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law HawaiiMr Eyerly may be contacted at
te@hawaiilawyer.com
The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle
December 20, 2017 —
Dave Suggs - CDJ STAFFSeattle Washington is experiencing a shortage of in-city condos. Of the 27,000 units of new housing being built in downtown Seattle, 94 percent will be rentals. As housing prices are rising in the US’s fastest-growing large city, the median home price is $660,000. Dean Jones of the Seattle Magazine reports on why consumers consider condos, but home developers don’t in his article “The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle.”
Reason 1, condominiums don’t always offer high returns and can be riskier for the home developer. Reason 2, the Washington State Condo Act “overprotects” buyers of condos with over-the-top warranties that makes everyone in the industry afraid to work with condos. Reason 3, the cost of condo building is increased because of the risk of defect litigation. Reason 4, condo presale buyers are not required to deposit a percentage to invest in a new development and before closing could decide to walk away. Reason 5, there is a lot of interest in apartment buildings from investment groups.
Reason 6, investors whose goal is to own “trophy” assets in rising markets can’t wait the years it takes developers to plan and construct a new multistory community. Reason 7, since rent prices have risen 50 percent on average in the last 7 years, it’s profitable to be a landlord. Reason 8, the millennials who live and work in this tech oriented region prefer to rent because of living through the rise and fall of the housing market. Reason 9, the costs is rising each year to deliver new projects. Reason 10, high-rise zoning was adopted 2 years before the recession, so just as condo development was gearing up, apartment building took over.
Read the court decisionRead the full story...Reprinted courtesy of
Policyholder Fails to Build Adequate Record to Support Bad Faith Claim
May 19, 2011 —
Tred R. EyerlyThe importance of careful preparation and documentation was the take away lesson in a Texas bad faith case, C.K. Lee v. Catlin Specialty Ins. Co., 2011 U.S. Dist. LEXIS 19145 (S.D. Tex. Feb. 28, 2011).
C.K. Lee owned a commercial shopping center in Houston. Catlin issued a commercial property policy to Lee. On September 12, 2008, Hurricane Ike hit and caused substantial property damage throughout the Texas Gulf Coast area. On September 24, 2008, Lee submitted a claim for damage to the roof of his shopping center to Catlin.
Catlin hired Engle Martin to represent its interests in adjusting the claim. Engle Martin eventually adjusted over 200 Ike-related claims for Catlin.
In November 2008, Engle Martin and Emergency Services Inc., retained by Lee, inspected Lee’s property. Engle Martin observed evidence of roof repairs that had apparently been made both before and after Hurricane Ike. Engle Martin decided it was necessary to use an infrared scan of the roof to help identify which damages, if any, were attributable to wind and which, if any, were attributable to sub par, prior repairs or natural deterioration.
Engle Martin retained Project, Time & Cost (PT&C) to conduct the infrared inspection. PT&C’s inspection determined there was no wind-related damage to the roof and no breaches or openings created by wind. Instead, the roof had exceeded its life expectancy and was in need of replacement due to normal wear and weathering. Consequently, Catlin decided that the damage to Lee’s roof was not caused by winds from Hurricane Ike.
Meanwhile, Lee’s contractor, Emergency Services, prepared a report estimating that the total cost of repairing the roof would be $871,187. Engle Martin’s estimate for repair of the roof was $22,864.
Lee filed suit for breach of contract, breach of the duty of good faith and fair dealing, and violations of the Texas Insurance Code. Catlin moved for summary judgment on all claims but breach of contract, arguing that because there was a bona fide dispute concerning the cause of the damages and whether they were covered under the policy, there was no evidence of bad faith or violations of the Texas Insurance Code.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Lead Paint: The EPA’s Renovation, Repair and Painting Rule
September 09, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome Joshua Glazov for the first time. Josh has been a construction lawyer since 1995. He practices at Much Shelist in Chicago and focuses on negotiating and preparing design and construction contracts for owners, contractors, and lenders, as well as preparing for, and confronting, construction related insolvency when a project participant goes bankrupt or a lender goes into FDIC receivership. Josh publishes on these topics at his blogs: Construction Law Today and the Bank Failure Blog.
Last month the EPA finally issued their Renovation, Repair and Painting Rule (PDF), the one that sets up new requirements for work on projects that may involve lead paint. The requirements are many complex. You’ll need to become familiar with this rule if you do any renovation , repair, or painting work, especially of your work is on buildings built before lead paint was banned in 1978.
- You’ll need to become a certified by the EPA as a Certified Renovation Firm
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Top 10 Construction Contract Provisions – Changes and Claims
November 03, 2016 —
James R. Lynch – Ahlers & Cressman PLLCThis is the seventh post in our “Top 10 Construction Contract Provisions” series. Prior posts discussed
Price and Payment,
Liquidated Damages,
Consequential Damages – Part I and
Part II,
Indemnity,
Scope of Work, and
Flow-Down Provisions.
Today’s topic, Changes and Claims, is a contender for the top spot on our list, for both day-to-day impact on the job and importance in disputes. In fact, these provisions[i] are so variable and are involved in so many reported construction law decisions, that this post will not attempt to survey all their various forms, uses, or potential legal ramifications, but instead focuses on bottom line “best practices”—questions to consider as a general contractor, subcontractor, or owner when drafting, negotiating, or managing the Changes and Claims provisions of a contract. There is no “ideal” here, and the changes and claims procedures should be suited to the project, owner, contractor(s), likely issues, and other project-specific considerations. Key considerations include the following:
1. How prescriptive is the Change Order process? At one end of the spectrum, a Change Order provision may include requirements for written direction and request by the owner and formal response by the contractor, with pricing and specific supporting data or documentation, in addition to strict timelines for response, execution, and performance, precise methods to determine the resulting contract adjustment, limits on the type or extent of adjustment, or terms defining the effect of a signed Change Order, e.g. to what extent related claims or impacts might be extinguished. At the other end of the spectrum, the Change Order provision might simply recognize that the owner may direct changes, and the parties intend to document the directions and resulting compensation in a Change Order, with no further elaboration. There is no universal ideal on this spectrum. A highly defined and prescriptive process may be appropriate for a complex, high value, multi-stakeholder project on which significant changes are likely. The same process would be an inefficient waste of resources on a small and simple project where significant changes are unlikely and the parties would be unlikely to comply with more formal procedures.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
Duty to Defend Broadly Applies to Entire Action; Insured Need Not Apportion Defense Costs, Says Maryland Appeals Court
January 27, 2020 —
Michael S. Levine & Kevin V. Small - Hunton Insurance Recovery BlogIn a recent decision, the Maryland Court of Special Appeals reiterated that the duty to defend broadly requires a liability insurer to defend an entire lawsuit against its insured, even where only some of the allegations are potentially covered. The court further held that the insured has no obligation to apportion defense costs among multiple implicated policies. The decision, Selective Way Insurance Company v. Nationwide Property and Casualty Insurance Company, et al., can be found here.
The coverage litigation arose out of a construction defect case against a general contractor. The general contractor tendered the action to its insurer, Nationwide, which, in turn, filed a declaratory judgment action against the various insurers of construction project subcontractors that had named the general contractor as an additional insured. Ultimately, the court granted a summary judgment motion declaring that all of the subcontractors’ insurers had a duty to defend the general contractor “because the allegations in the underlying lawsuit raised claims that potentially arose from the [s]ubcontractors’ work at the [construction site].” All of the subcontractors’ insurers settled with Nationwide except for one, Selective Way; and the parties proceeded to a jury trial on various issues. The jury found for Nationwide on all issues. Selective Way appealed.
Selective Way argued on appeal that even if some of the allegations were covered under its policy, it had no obligation to defend the general contractor because its insureds, the subcontractors, could not have been responsible for all of the losses given the nature of their work. Further, Selective Way contended that if it was responsible for defending the general contractor, it was not responsible for the entire defense, and the general contractor was responsible for apportioning the costs among the various subcontractors. The panel disagreed on both points.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Kevin V. Small, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of