Construction Law Alert: Unlicensed Contractors On Federal Projects Entitled To Payment Under The Miller Act
May 07, 2014 —
Steven M. Cvitanovic and Jessica M. Lassere Ryland - Haight Brown & Bonesteel, LLPAs a matter of first impression, the Ninth Circuit Court of Appeals in Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co., 12-56539, 2014 WL 1674108 (9th Cir. Apr. 29, 2014), allowed an unlicensed subcontractor to recover from a prime contractor for unpaid services relating to a federal construction project under a federal Miller Act claim. California law otherwise prevents unlicensed contractors from recovering for unpaid work on non-federal projects as a penal measure intended to encourage contractors to maintain a valid license at all times.
Technica LLC (“Technica”) worked as a sub-subcontractor on a large federal fence replacement project (the “Project”). Over the course of a year, Technica supplied nearly a million dollars worth of labor, materials, and services for the Project. However, Technica received only $287,861.81 in partial payments for its work. Technica proceeded to file suit in district court against the prime contractor Candelaria Corporation (“Candelaria”) and its payment surety Carolina Casualty Insurance Company (“CCIC”) under the Miller Act to recover amounts owed to it on the subcontract against the payment bond.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel, LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel, LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Lassere Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Jonathan Harwood Obtains Summary Judgment Determining Insurer Has No Duty to Defend or Indemnify
February 27, 2023 —
Jonathan R. Harwood - Traub LiebermanTraub Lieberman Partner Jonathan Harwood obtained summary judgment in favor of the Plaintiff determining that it had no duty to defend or indemnify an insured in a personal injury action, in a case brought in the Eastern District of New York.
The Plaintiff, an insurance provider (“the Insurer”), issued a General Commercial Policy (the “Policy”) to the Defendant, a commercial property owner (the “Property Owner”). In the underlying action, a former employee (the “Employee”) of a concrete vendor sued the Property Owner, and others, in New York Supreme Court, Queens County, for an injury that occurred on the street in front of the Property Owner’s premises during the course of repairs of sewer pipes that serviced the Property Owner’s premises.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Harwood, Traub LiebermanMr. Harwood may be contacted at
jharwood@tlsslaw.com
A Compilation of Quirky Insurance Claims
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 showcased five “nutty claims stories” based upon recollections by several insurance professionals.
Number four, subtitled, “The Case of the Soaked Survivalists,” described a claim by an elderly couple who “made a $350,000 water-damage claim after heavy rains and an inadequate sump pump ruined what they described as thousands of ‘valuable items’ in their storage area.” However, a claims adjuster discovered during the investigation that the area in question was actually a bomb shelter built during the Cold War era, and the so-called valuable items were actually “soap, toothpaste, canned goods, and more.” The insurer ended up settling for about $200,000.
Read the court decisionRead the full story...Reprinted courtesy of
University of Tennessee’s New Humanities Building Construction Set to Begin
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFConstruction preparation of the Tennessee Volunteer’s $30.5 million new humanities building has begun, according to The Tennessean. The 80,000 square-foot facility will become the largest building on the university’s campus, and will feature 23 classrooms, 18 labs, 11 collaborative study areas, 56 offices, 20 adjunct faculty workrooms as well as an outdoor theater and courtyard.
“This is a significant milestone in the history of the college,” President Jerry Faulkner told The Tennessean. “This building has been on our wish list for about 12 years in terms of wanting to have this facility available, so for the first time our humanities division is going to have a home of its own.”
Read the court decisionRead the full story...Reprinted courtesy of
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 —
CDJ STAFFWriting in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Eye on Housing Examines Costs of Green Features
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing reported that it costs more to build a green home, however, builder’s experience with green techniques reduces costs.
According to McGraw Hill Construction survey data (as quoted by Eye on Housing), “the incremental cost for builders to construct green homes was 8% in 2013. For remodelers, green projects raised costs by 9% on average.” Furthermore, “McGraw Hill’s analysis found that the cost to build green varied to some degree by the amount of green construction undertaken.”
Read the court decisionRead the full story...Reprinted courtesy of
Federal Judge Rips Shady Procurement Practices at DRPA
October 07, 2016 —
Wally Zimolong – Supplemental ConditionsIn an opinion overturning a $17,000,000 bridge painting contract for the Commodore Barry Bridge, a United States Federal Judge called the procurement practices of the Delaware River Port Authority “a black box . . . obscure and unexplained, and lacking any indicia of transparency or the hallmarks of a deliberative process.”
The case involved lead paint remediation and repainting of the Pennsylvania span of the Commodore Barry. Seven contractors submitted bids. Alpha Painting was the apparent low bidder. Corcon was the second low bidder. Corcon was also the contractor that was perform the painting work on the New Jersey span of the bridge. Like most agencies engaged in public bidding, the DRPA requires contracts to be awarded to the lowest responsible and responsive bidder.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com