Flow-Down Clauses Can Drown Your Project
August 26, 2015 —
Craig Martin – Construction Contractor AdvisorFlow-Down or pass-through clauses obligate downstream contractors to certain provisions contained in the up up-stream contractor contracts, such as the contract between the general contractor and the owner. These clauses are contained in every major form subcontract and they can expand the scope of your potential liability. This blog will look at typical language of a flow-down clause, what it means and how you can deal with them.
Typical Flow-Down Clause
A simple flow down clause might provide:
“The Subcontractor agrees to be bound to the Contractor by the terms of the prime contract and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the Owner, except to the extent that the provisions contained therein are by the terms or by law applicable only to the Contractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
California Contractor Spills Coffee on Himself by Failing to Stay Mechanics Lien Action While Pursuing Arbitration
August 14, 2018 —
Garret Murai - California Construction Law BlogIt bugs the Mrs. that I have a habit of reading the directions. “Just plug the darn thing in!” said the Mrs. when we got a new coffee maker to replace our old one which we’ve had since I think before we were married (Life Lesson No. 347: Get a coffee maker you really, really like because they last forever). “But . . . the directions?,” I said.
By the time I had finished reading the instruction manual I could smell the coffee brewing in the kitchen. Granted, the Mrs. is more practical than I am in many ways (e.g., “You know, you didn’t need to buy 10 cans of corn to get the 10 for $10 discount. I guess you’re going to be eating a lot of corn”). But still. What might have happened if there was a serious coffee mishap?
And worrier as I may be mishaps can happen if you don’t read the directions. James Zenovic didn’t read the directions, and here’s his story . . .
Von Becelaere Ventures, LLC v. Zenovic
In Von Becelaere Ventures, LLC v. Zenovic, Case No. D072620 (June 6, 2018), James Zeonovic doing business as James Zeonovic Construction entered into a construction contract to build a single-family house for Von Becelaere Ventures, LLC in Laguna Beach, California. The construction contract included an arbitration provision that stated:
If any dispute arises concerning this Contract or the interpretation thereof, of concerning construction of the Improvements, or the Limited Warranty, customer service, defects, damages, or obligations therewith (a “Construction Dispute”), such Construction Dispute will be settled by binding arbitration. Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Las Vegas’ McCarran Tower Construction Issues Delays Opening
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that an improperly applied chemical coating might delay the opening of McCarran International Airport’s Federal Aviation Administration tower by a year and cost millions of dollars to repair.
The chemical coating was intended “to prevent the spread of toxic fungus,” but was “improperly applied and is ineffective,” workers on the site told the Las Vegas Review-Journal.
“Officials said the” $99 million, 352-foot “tower was expected to be operational by 2015, but the FAA now says it won’t be able to use the facility until late 2016 or early 2017.”
Read the court decisionRead the full story...Reprinted courtesy of
Best Lawyers Honors 43 Lewis Brisbois Attorneys, Recognizes Three Partners as 'Lawyers of The Year'
September 14, 2020 —
Lewis BrisboisBest Lawyers has selected 43 Lewis Brisbois attorneys across 25 offices for inclusion in its list of 2021 Best Lawyers in America. It has also recognized three Lewis Brisbois partners as "Lawyers of the Year": Los Angeles Partner Jon P. Kardassakis (Mass Tort Litigation / Class Actions - Defendants); Roanoke Partner Paul C. Kuhnel (Medical Malpractice Law - Defendants); and Northwest Indiana Managing Partner Renee J. Mortimer (Personal Injury Litigation - Defendants).
Please join us in congratulating these three partners and the following attorneys on their Best Lawyers recognition.
Reprinted courtesy of
Lewis Brisbois
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
What Counts as Adequate Opportunity to Cure?
June 13, 2022 —
Christopher G. Hill - Construction Law Musingsqimono @ PixabayHere at Musings, we like to discuss (likely more than readers would like) the fact that in Virginia, the contract is king and its terms will be looked at carefully by the courts. One of those provisions that will be looked at carefully is the so-called “cure period.” The “cure period” is the time that a subcontractor has to fix any non-compliant construction after receiving notice of any deviation from the contract documents that must be fixed.
In United States ex rel Allan Myers VA, Inc. v. Ocean Construction Services, Inc. the federal court for the Eastern District of Virginia examined what it means to grant a proper opportunity to cure. The Ocean Construction Services case arises from a contractual dispute between Allan Myers VA Inc. and Ocean Construction Services Inc., or OCS, involving renovation work performed in sections of Arlington National Cemetery. Presently before the court is Myers’ motion for partial summary judgment, arguing that the undisputed facts demonstrate that it was not provided with a three-day cure period, a contractual prerequisite to OCS terminating the subcontract for default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
4 Ways to Mitigate Construction Disputes
March 20, 2023 —
Bill Shaughnessy - ConsensusDocsResolving construction disputes in litigation (court or arbitration) can be expensive and may drag on for years. Most disputes could have been avoided, or at least mitigated, had the parties (both owners and contractors) identified contract risks during negotiations and been more proactive in communicating the risks during execution of the work. This article highlights four practical risk management approaches that help all parties focus on their mutual interest in close coordination and clear communication at the beginning of the project as well as throughout performance:
- Identifying and allocating risks;
- Accurate scheduling;
- Clear project documentation and communication; and
- Real-time dispute resolution.
The intent of these techniques is not to shift legal obligations or risks. Rather, the intent is to keep project personnel and project management for all the participants focused on communicating and working together, including responsibly confronting real problems to avoid or mitigate their impact. Allocating risks, scheduling, project documentation and communication, and real-time dispute resolution are independently relevant on a bilateral basis between the owner, designer, and the various contractors. These approaches and their diligent execution by the parties during construction contribute far more to a successful project than anything lawyers and claims consultants can contribute in after-the-fact legal proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker LLP (ConsensusDocs)Mr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Hawaii Construction Defect Law Increased Confusion
August 27, 2013 —
CDJ STAFFHawaii’s Act 83 put into the law that in determining if a construction defect was due to an occurrence, the courts needed to ignore any case law that arose after the insurance policy was taken out. The hope, according to Bibeka Shrestha, writing at Law360, was to provide certainty to builders. The effect, however, “further muddled the litigation landscape.”
Carl Shapiro said of the Hawaii legislature that “instead of solving the problem, they’ve created an even bigger miss.” Tred Eyerly, an insurance attorney says that the state “needs a decision from the Hawaii Supreme Court.”
One result is that now the state court and the federal courts have different views on how to look at prior cases. The state courts are holding that “the uncertainly should be resolved in favor of the policyholder,” while the federal courts “pointed to earlier case law that nixed coverage for these types of claims.
The legislature seems unlikely to resolve this confusion on its own. One legislative liaison said that “nobody knew how to pass a law saying ‘you will grant coverage.’” Brian Yamane also told Law360 that “there has been no attempt by anybody to introducte legislation to amend the law.”
Read the court decisionRead the full story...Reprinted courtesy of
Cable-Free Elevators Will Soar to New Heights, and Move Sideways
January 14, 2015 —
Belinda Lanks – BloombergI live in one of the few buildings in New York that still has a manual elevator. When I ask the operator on the morning shift how he's doing, his well-oiled response is "up and down." For the last 160 years, elevators have travelled a predictably vertical path. That will soon change when the German manufacturer ThyssenKrupp introduces the first fleet of cable-free cars that can also move sideways.
The system, dubbed MULTI, will allow multiple cabs to motor along a single, looping shaft. The cars move by magnetic levitation (the same technology behind some high-speed trains), rather than being pulled by the heavy steel ropes that limit how high skyscrapers can stretch. With MULTI, architects will be able to build spindly towers on small plots formerly deemed untenable for high-rises.
Read the court decisionRead the full story...Reprinted courtesy of
Belinda Lanks, BloombergMs. Lanks may be contacted at
blanks@bloomberg.net