Maximizing Contractual Indemnity Rights: Insuring the Indemnitor's Obligation
December 02, 2015 —
William Kennedy – White and Williams LLPContracting parties can circumvent the limitations of common law tort doctrines by drafting contracts with language that details the allocation or shifting of the risk of tort loss. Properly composed, “broad form” contractual indemnity provisions can permit an Indemnitee to shift the full range of tort exposure – damages and defense fees and costs – if they have the kind of specificity set forth in Part Two of this series, "Maximizing Contractual Indemnity Rights: Components of an Effective Provision." In most business transactions, however, both the Indemnitee and the Indemnitor want the indemnity obligation to be insured.
Part Three: Insuring the Indemnitor's Obligation
“Insured Contract Coverage”
Although CGL policies do not typically cover an Insured’s breaches of contract, per se, most insurance policies do cover a policyholder’s “incidental contracts” or “insured contracts” under which the policyholder has an obligation to indemnify an Indemnitee. The business contract (as opposed to the insurance policy) should require the Indemnitor to take all steps necessary to have the Indemnitee identified as either a Covered Person, Insured, or Additional Insured on the Indemnitor’s applicable insurance policies. There are subtle, but potentially significant legal rights and responsibilities that hinge on whether an entity is a Covered Person, Insured, Additional Insured, or some other classification. Purported Indemnitees may need to consult insurance coverage counsel to ensure that they are seeking the appropriate status from the Indemnitor’s CGL insurer.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
To Catch a Thief
March 06, 2023 —
Christopher Durso - Construction ExecutiveTony Rader calls it “peeling back the onion”—the slow, methodical process of uncovering the full extent of an embezzlement scam that eventually totaled more than $1 million. What National Roofing Partners (NRP) first discovered was bad enough. The Coppell, Texas–headquartered company, which oversees a nationwide network of nearly 250 commercial roofing contractors, learned in 2018 that a South Texas firm called Statewide Texas Roofing was billing clients for work on behalf of NRP and pocketing all the money. It turned out to be a scheme masterminded by NRP’s then-president, who created Statewide, staffed the company with his kids and used phony work orders to steal hundreds of thousands of dollars in client fees from NRP. He’d been president for six years and with the company since it was created in 2007. It was a huge betrayal—and still just the tip of the iceberg.
“Initially, we thought it was only half a million [dollars] or so,” says Tony Rader, NRP’s chief operating officer. “But I’ll never forget, [Chief Executive Officer] Steve [Little] and I were talking over a bourbon one night, and that’s when I told him, ‘I’ve seen this once before, and this is like an onion. You’ve only peeled off the outer layers. We’re going to be finding stuff for a year, and it’s just going to get bigger and bigger and bigger.’ He said, ‘You think?’ And I said, ‘Oh, I’m pretty sure.’” Rader was all too correct. Working with a third-party forensic accountant, NRP found that not only were its then-chief financial officer and several other employees involved in the scheme, but the president had also abused his corporate credit card, racking up personal charges going back to 2013—on luxury vacations, expensive dinners, clothes, jewelry, even his daughter’s destination wedding in Jamaica. The final tally on his scams: $1.4 million.
Reprinted courtesy of
Christopher Durso, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Henkels & McCoy Pays $1M in Federal Overtime-Pay Case
July 19, 2021 —
Tom Ichniowski - Engineering News-RecordIn a consent judgment in a federal labor case, major specialty contractor Henkels & McCoy Inc. has paid about $1.1 million in back pay and damages for allegedly not paying required overtime wages to 362 current and former workers in five states, the U.S. Dept. of Labor says.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Effectively Managing Project Closeout: It Ends Where It Begins
August 06, 2019 —
William E. Underwood - ConsensusDocsProject closeout is sometimes one of the last things on a contractor’s mind at the beginning of a project, but project closeout can have a huge impact on a contractor’s overall profitability and success. Effectively managing the closeout process is critical, and it all begins with the negotiation and execution of the project contract. This contract can, and should, provide a complete roadmap for project closeout, as addressing these issues on the front end can set up the parties for successful project completion. It is then equally important to re-review the terms of the contract as project closeout approaches to ensure that everyone, including the owner, adheres to all contractual requirements.
This article examines several pertinent issues related to project closeout that should be addressed during the contracting stage, including defining substantial and final completion, inspection and acceptance, punch lists, and warranties.
Defining Substantial and Final Completion
Having clear definitions for both substantial and final completion in your construction contract is an important and necessary early step in achieving successful project closeout.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
United States Supreme Court Backtracks on Recent Trajectory Away from Assertions of General Jurisdiction in Mallory v. Norfolk Southern
August 01, 2023 —
Charles S. Anderson - Lewis BrisboisWashington, D.C. (June 28, 2023) – On June 27, 2023, the U.S. Supreme Court issued a sharply divided opinion that appears to backtrack on the Court’s steady trajectory away from assertions of general jurisdiction in recent years, e.g. Goodyear Dunlop Tires Operations, S.A. v. Brown, 564 U.S. 915, 919 (2011), Daimler AG v. Bauman, 134 S. Ct. 746 (2014), BNSF Railway Co. v. Tyrrell, 2017, 137 S. Ct. 1549 (2017). Relying on a case from 1917, Pennsylvania Fire Ins. Co. of Philadelphia v. Gold Issue Mining & Milling Co., 243 U. S. 93 (1917), Justice Gorsuch, writing on behalf of the plurality, (Justices Gorsuch, Thomas, Sotomayor, and Jackson) (Justice Alito concurring) found that Norfolk Southern “consented” to jurisdiction in Mallory via 42 Pa. Cons. Stat. §5301(a)(2)(i),(b) by registering to do business in Pennsylvania. This statute, 42 Pa. Cons. Stat. §5301, specifically permits jurisdiction over a corporation “incorporat[ed] under or qualifi[ed]as a foreign corporation under the laws of this Commonwealth … for any cause of action that may asserted against him, whether or not arising from acts enumerated in this section.”
In Pennsylvania Fire, the U.S. Supreme Court addressed the Due Process Clause of the U.S. Constitution in connection with a Missouri law that required an out-of-state insurance company desiring to transact any business in the state to file paperwork agreeing to (1) appoint a state official to serve as the company’s agent for service of process and (2) accept service on that official as valid in any suit. After more than a decade of complying with the law, Pennsylvania Fire was served with process and argued that the Missouri law violated due process. The Court unanimously found that there was “no doubt” that Pennsylvania Fire could be sued in Missouri because it had agreed to accept service of process in Missouri on any suit as a condition of doing business there.
Read the court decisionRead the full story...Reprinted courtesy of
Charles S. Anderson, Lewis BrisboisMr. Anderson may be contacted at
Charles.Anderson@lewisbrisbois.com
The Pandemic of Litigation Sure to Follow the Coronavirus
March 30, 2020 —
Aaron Lovaas - Newmeyer DillionAs the Coronavirus crisis persists, America’s richly diverse private business sector finds itself increasingly subject to unprecedented governmental orders and restrictions that were unheard of only a few weeks ago. While the various “shutdown,” “shelter in place,” and “non-essential business” orders all aim to protect the public health, there is no doubt that the wave of litigation to follow is already swelling.
Business interruption, civil authority, and cyber insurance coverages have already been widely discussed as issues certain to be litigated over the coming months and beyond. Additionally, breach of contract litigation is likely to spike as parties attempt to recoup their losses from canceled events, unfulfilled purchase commitments and other unmet obligations.
Moreover, regional and national businesses are now in the difficult position of managing their respective affairs to comply with a patchwork of executive orders that are inconsistent from state to state. And, as the pandemic wears on, many are questioning the authority under which some of these executive orders and emergency regulations are being issued in the first place. Indeed, constitutional challenges are almost certain to follow as the business community reframes the characterization of their losses into notions of unconstitutional takings of private property and governmental impairment of private contract rights.
Read the court decisionRead the full story...Reprinted courtesy of
Aaron Lovaas, Newmeyer DillionMr. Lovaas may be contacted at
aaron.lovaas@ndlf.com
EPA Will Soon Issue the Latest Revision to the Risk Management Program (RMP) Chemical Release Rules
February 10, 2020 —
Anthony B. Cavender - Gravel2GavelOn November 21, 2019, EPA released a pre-publication copy of its Reconsideration of the revised Risk Management Program (RMP) Rules. In an accompanying statement, the agency noted that it has taken steps to “modify and improve” the existing rule to remove burdensome, costly and unnecessary requirements while maintaining appropriate protection (against accidental chemical releases) and ensuring responders have access to all of the necessary safety information. This action was taken in response to EPA’s January 13, 2017 revisions that significantly expanded the chemical release prevention provisions the existing RMP rules in the wake of the disastrous chemical plant explosion in West, Texas. The Reconsideration will take effect upon its publication in the Federal Register.
Background
As recounted by the D. C. Circuit in its August 2018 decision in the case of Air Alliance Houston, et al. v. EPA, in 1990, the Congress amended the Clean Air Act to force the regulation of hazardous air pollutants (see 42 USC Section 7412). An initial list of these hazardous air pollutants was also published, at Section 7412 (b). Section 112(r) (codified at 42 USC Section 7412 (r)), authorized EPA to develop a regulatory program to prevent or minimize the consequences of a release of a listed chemical from a covered stationary source. EPA was directed to propose and promulgate release prevention, detection, and correction requirements applicable to stationary sources (such as plants) that store or manage these regulated substances in amounts determined to be above regulated threshold quantities. EPA promulgated these rules in 1996 (see 61 FR 31668). The rules, located at 40 CFR Part 68, contain several separate subparts devoted to hazard assessments, prevention programs, emergency response, accidental release prevention, the development and registration of a Risk Management Plan, and making certain information regarding the release publicly available. EPA notes that over 12.000 RMP plans have been filed with the agency.
In January 2017, in response to the catastrophe in West, EPA issued substantial amendments to these rules, covering accident prevention (expanding post-accident investigations, more rigorous safety audits, and enhanced safety training), revised emergency response requirements, and enhanced public information disclosure requirements. (See 82 FR 4594 (January 13, 2017).) However, the new administration at EPA, following the submission of several petitions for reconsideration of these revised rules, issued a “Delay Rule” on June 14, 2017, which would have extended the effective date of the January 2107 rules until February 19, 2019. On August 17, 2018, the Delay Rule was rejected and vacated by the D.C. Circuit in the aforementioned Air Alliance case (see 906 F. 3d 1049 (DC Circuit 2018)), which had the effect of making the hotly contested January 2017 RMP revisions immediately effective.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at