Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Despite Misapplying California Law, Federal Court Acknowledges Virus May Cause Physical Alteration to Property
October 26, 2020 —
Scott P. DeVries, Michael S. Levine & Michael L. Huggins - Hunton Insurance Recovery BlogOn August 28, Judge Stephen V. Wilson of the Central District of California, entered the latest ruling in the ongoing saga of the COVID-19 business interruption coverage dispute between celebrity plaintiff’s attorney Mark Geragos and Insurer Travelers.
The case, 10E, LLC v. The Travelers Indemnity Co. of Connecticut, was filed in state court. Travelers removed to federal court, where Geragos sought remand and Travelers moved to dismiss. Judge Wilson denied remand and granted the Motion to Dismiss, finding plaintiff did not satisfactorily allege the actual presence of COVID-19 on insured property or physical damage to its property. This holding is inconsistent with long standing principles of California insurance law and appears to improperly enhance the minimal pleading threshold under Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (To survive a motion to dismiss, a complaint need only allege a claim “that is plausible on its face.”).
After rejecting Geragos’ attempt to have the case remanded based on a finding that Geragos had fraudulently joined a defendant to avoid removal, the Judge proceeded to the Motion to Dismiss which raised three issues: (1) the effect of the Virus Exclusion in the Travelers’ Policy, (2) whether plaintiff failed to allege that the governmental orders prohibited access to its property, and (3) whether plaintiff could “‘plausibly allege that it suffered ‘direct physical loss or damage to property’ as required for civil authority coverage.’” Rather than address the effect of the exclusion, which would be the narrowest issue (this exclusion is not present in all policies), the Court proceeded directly to the third issue, which has the broadest potential application.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Michael L. Huggins, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Huggins may be contacted at mhuggins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
California Court of Appeal Vacates $30M Non-Economic Damages Award Due to Failure to Properly Apportion Liability and Attorney Misconduct During Closing Argument
February 08, 2021 —
Krsto Mijanovic, Peter A. Dubrawski, Arezoo Jamshidi & Catherine M. Asuncion - Haight Brown & Bonesteel LLPOn January 20, 2021, the California Court of Appeal, Second District, Division Six (Ventura), in Plascencia v. Deese (B299142), vacated a $30 million non-economic damages award in a highway fatality case because: (1) the award did not properly apportion non-economic damages among everyone at fault in violation of Proposition 51; and (2) the amount of the award appeared to have been influenced by plaintiffs’ counsel’s misconduct and prejudicial remarks during closing argument.
In Plascencia, the plaintiffs sued several defendants for the wrongful death of their daughter arising from a highway fatality accident. All the defendants settled or were dismissed before trial except the trucking defendants. The highway fatality was caused when one defendant driver made an illegal U-turn on a highway as she left another defendant’s fruit stand. The plaintiffs’ daughter swerved to avoid the U-turn driver, lost control of her car, and crashed into the back of the trucking defendants’ diesel tractor-trailer. The truck driver had parked the truck on the side of the highway near the fruit stand, which the trucking defendants’ expert conceded fell below the standard of care.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel LLP,
Peter A. Dubrawski, Haight Brown & Bonesteel LLP,
Arezoo Jamshidi, Haight Brown & Bonesteel LLP and
Catherine M. Asuncion, Haight Brown & Bonesteel LLP
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Mr. Dubrawski may be contacted at pdubrawski@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Ms. Asuncion may be contacted at casuncion@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Remodels Replace Construction in Redding
September 09, 2011 —
CDJ STAFFThe Record Searchlight reports that while new construction is down in Redding, California, residential and commercial remodel permits are up 17 percent. By August 2010, there had been 63 housing and commercial business starts in Redding, while this year has seen only 15.
One such remodel, that of Parkview Market, will cost about $201,000. Safeway is planning on two $80,000 remodels of its grocery stores in Redding. In all, the 150 building permits for remodels are worth a total of $2.8 million.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Brookfield Wins Disputed Bid to Manage Manhattan Marina
January 28, 2015 —
Martin Z Braun – Bloomberg(Bloomberg) -- Brookfield Property Partners won a bid to run a marina in New York’s Battery Park City neighborhood over the objections of residents backing a local businessman who operated the facility and a popular sailing club and school.
The state’s Battery Park City Authority voted Thursday to approve a 10-year agreement with Brookfield, which owns an adjacent 8 million-square-foot office and retail complex. Brookfield is bringing in billionaire real estate investor Andrew Farkas’s Island Global Yachting to manage the North Cove Marina.
Read the court decisionRead the full story...Reprinted courtesy of
Martin Z Braun, BloombergMr. Braun may be contacted at
mbraun6@bloomberg.net
Claim for Vandalism Loss Survives Motion to Dismiss
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court ruled that the insured's claim for vandalism of his house by a renter and for bad faith survived the insurer's motion to dismiss. Wehrenberg v. Metro. Prop. & Cas. Ins. Co., 2015 U.S. Dist. LEXIS 103758 (W.D. Pa. Aug. 7, 2015).
The insured's home was insured by a homeowner's policy issued by Metropolitan. The insured rented his home to Alphonso Hyman in October 2011. In lieu of rent, Hyman was to pay the mortgage company the equivalent of his rent each month.
In early 2012, Hyman stopped making the monthly rent/mortgage payments. The insured went to the home and found the locks had been changed. Looking in the windows, he saw the interior had been gutted. When the insured reached Hyman, Hyman said he was a contractor and was fixing the structural problems and would put the house back together. He also promised to make up late payments to the mortgage company. The insured did not report what he found to Metropolitan.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Do Engineers Owe a Duty to Third Parties?
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorA Texas Court of Appeals, in USA Walnut Creek, DST v. Terracon Consultants, Inc., recently ruled that an engineer owed a duty to the buyer of an apartment complex, even though the engineer had no contractual relationship with the buyer. This is an expansion of the duty professionals owe on construction projects and could signal a change in the law.
In the case, Walnut Creek purchased a three year old apartment complex. A few years after taking possession, Walnut Creek noticed problems with the apartments, including cracking foundations, walls, breaking windows, and out of square door frames. Walnut Creek sued the developer and general contractor, alleging construction defects. The developer claimed that the engineer, Terracon, was at fault and Walnut Creek added Terracon to the lawsuit, asserting that Terracon was negligent in performing engineering services during construction. Terracon asked the court to dismiss the claim, arguing that it did not owe a duty to Walnut Creek. Walnut Creek in turn argued that engineers do owe a duty to subsequent owners. The trial court dismissed the case against the engineer and Walnut Creek appealed.
The appellate court reversed the trial court, finding that the engineer did owe a duty to subsequent purchasers. The court seemed persuaded by the allegations that the engineer actually created the construction defects which were the basis for the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com