The Privilege Is All Mine: California Appellate Court Finds Law Firm Holds Attorney Work Product Privilege Applicable to Documents Created by Formerly Employed Attorney
June 29, 2017 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Tucker Ellis LLP v. Superior Court (A148956 – Filed 6/21/2017), the First Appellate District held that (1) the holder of the attorney work product privilege is the employer law firm rather than the former employee attorney who created the privileged documents while a firm employee, and (2) as a result, the firm did not owe a duty to obtain the former attorney’s permission before disclosing the subject documents to third parties.
In Tucker Ellis LLP, the attorney, while still employed by Tucker Ellis, exchanged a series of e-mails with a consultant retained by the firm to assist in asbestos litigation for a client. The firm also entered into an agreement with the consultant to summarize scientific studies on the causes of mesothelioma in a published review article. After the attorney departed the firm, Tucker Ellis was served with a subpoena in connection with a matter pending in Kentucky for the production of communications with the consultant regarding the article. In response, Tucker Ellis, in relevant part, produced the work product e-mails authored by the former attorney. The e-mails eventually ended up on the Internet and reached over 50 asbestos plaintiffs’ attorneys, resulting in the attorney’s termination from his new firm. After Tucker Ellis ignored the attorney’s “claw-back” letter, he filed suit against the firm for negligence, among other causes of action. The trial court granted the former attorney’s motion for summary adjudication on the issue of duty, reasoning that the firm owed the attorney a legal duty to prevent the disclosure of the work product. Tucker Ellis filed a petition for a writ of mandate with the Court of Appeal challenging the trial court’s decision on the duty issue.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Anti-Concurrent Causation Endorsements in CGL Insurance Policies: A Word of Caution
August 29, 2022 —
David M. McLain – Colorado Construction LitigationWhile I have not performed exhaustive research into the origin of anti-concurrent causation (“ACC”) endorsements on insurance policies, or how or when they migrated from first-party property policies to commercial general liability (“CGL”) policies, they have done so. The result for Colorado’s construction professionals may rear its ugly head as an unwelcome and surprise outright declination of coverage for construction defect claims.
ACC endorsements state that if there are two causes of damage: one of which is covered by a policy and one of which is not, the carrier can invoke the ACC endorsement to disclaim coverage for all of the damage. An exemplar ACC endorsement is ISO Form CG 21 67, entitled “Fungi or Bacteria Exclusion.”
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Medical Center Builder Sues Contracting Agent, Citing Costly Delays
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Pennsylvania firm Bedwell Co. “has sued the Camden County Improvement Authority, saying it is owed $4.6 million for construction of [the Cooper Medical School of Rowan University]” in Camden, New Jersey, according to the Courier-Post. The Bedwell Co. alleges that its expenses exceeded fifty million, “but that it has been paid only $46 million.”
The lawsuit states, as quoted by the Courier-Post, “From its inception, the project was plagued by delays due to defects in the design document and other circumstances that were beyond Bedwell’s control.” Furthermore, there were “an abnormally large quantity of design changes, schedule disputes, schedule disruptions and work-activity interference.”
“Representatives of the CCIA and HDR could not be reached for comment Wednesday,” according to the Courier-Post. “Bedwell declined to comment on the allegations in the suit.”
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Senate Bill 435 is Now in Effect
February 24, 2020 —
Bremer Whyte Brown & O'Meara LLPATTENTION: Nevada liability departments and auto insurance carriers! Nevada Senate Bill No. 435 was recently signed into law and there are two key points to be aware of: Disclosure of Policy Limits Demand and Voiding Releases. These both deal with pre-litigation situations.
1) Nevada law now requires a motor vehicle insurer to disclose the limits of the policy if the claimant provides a HIPAA authorization which allows the carrier to “receive all medical reports, records and bills related to the claim from the providers of health care.” This is a change from the previous Nevada statute which required the disclosure of policy limits only after litigation was commenced.
However, it appears from the language of the statute that there are limits to this new mandate. Section 4 of the new law is written in such a way to allow the argument that the new law applies only to accidents that occurred after 10/1/19, and that the insurance company has to request the HIPAA waiver from the claimant in order for the disclosure requirement to apply.
The plaintiff’s bar is already attempting to address this language in the legislature. As written, subsection (4) is governed by subsection (1) which states that the insurance company “may require the claimant … to provide … a written authorization.” The following subparts all appear to be triggered only by the act of the insurance company requesting a HIPAA waiver. The plaintiff’s bar is pushing for clarifying language that would make it clear that once the claimant sent a HIPAA waiver, irrespective of whether the document was requested by the insurance company or not, the insurance company is required to disclose policy limits. This is not how the law reads on its face, and the change would make a significant difference from a practical perspective.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Construction Resumes after Defects
June 28, 2013 —
CDJ STAFFWhen inspectors found defective bolts in the construction of the Media Arts Center at L. A. Mission College, the contractor walked off the job. The project had been underway for about eighteen months. After problems were found with welds and bolts, the contractor informed the school that it could not complete the job. The California Division of the State Architect then required inspection of every weld and joint, leading to a dispute as to who was going to pay for it.
At this point, only the first story has been inspected. Although the other two stories must be inspected, the new contractor is about to begin work on the building. James O’Reilly, the executive director for facilities, planning and development, said that “the main focus is on fixing the defective issues and getting construction completed so we can serve the Mission campus.” Still at question is how much SMC Construction received before they walked off the job.
Read the court decisionRead the full story...Reprinted courtesy of
New York’s Lawsky Proposes Changes to Reduce Home Foreclosures
May 20, 2015 —
Jesse Westbrook – BloombergNew York’s banking regulator proposed changes to the foreclosure process to try to help borrowers in the state keep their homes.
One reason New York has a high rate of foreclosures is that mandatory settlement meetings between borrowers and mortgage servicers typically don’t take place for months after a bank initiates a foreclosure, Benjamin Lawsky, superintendent of New York’s Department of Financial Services said in prepared remarks Tuesday.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Westbrook, Bloomberg
E-Commerce Logistics Test Limits of Tilt-Up Construction
January 28, 2019 —
Jeff Rubenstone - Engineering News-RecordWhile “fulfillment centers” and other e-commerce logistic facilities drive a hot market for the manufacturing sector, traditional construction methods such as tilt-up concrete panels are being pushed to ever-greater heights. At a recent project in Tulsa, Okla., contractor Clayco oversaw installation of tilt-up composite panels that reached 81 ft in height, using an unusual brace and a lot of careful pre-planning.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Rubenstone, ENRMr. Rubenstone may be contacted at
rubenstonej@enr.com
Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses
October 24, 2022 —
Amanda L. Marutzky - ConsensusDocsSince October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.
The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.
Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda L. Marutzky, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Ms. Marutzky may be contacted at