Payment Bond Claim Notice Requires More than Mailing
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Biden’s Buy American Policy & What it Means for Contractors
February 22, 2021 —
Meredith Thielbahr & Nicole Lentini - Gordon & Rees Construction Law BlogJanuary 25, 2021, President Biden signed an Executive Order (EO) “Ensuring the Future is Made in All America by All of America’s Workers”, which seeks to bolster U.S. manufacturing through the federal procurement process. Note that, just six day earlier, on January 18, the Federal Acquisition Regulation (FAR) Counsel issued a final rule implementing former President Trump’s July 2019 EO, titled “Maximizing Use of American-Made Goods, Products, and Materials” (EO No. 13881) on the then-current Buy American standards. For context, Trump’s proposed revisions – adopted and implemented by the FAR Council earlier this year – imposed three (3) significant changes worth noting: (1) increasing the percentage of domestic content (other than iron or steel) from 50% to 55% that an end product must contain in order to qualify as a “domestic end product”; (2) implementing an even higher increase in the domestic content requirement for iron and steel products to at least 95% U.S. “predominately” iron or steel product; and (3) increasing the price evaluation preference for domestic offerors from 6% to 20% (for other than small business) and 30% (for small businesses). The FAR’s rule became effective January 21, 2021, and applies to solicitations issued on or after February 22, 2021, and resulting contracts let. Biden’s EO rescinds Trump’s EO No. 13881 “to the extent inconsistent with [Biden’s] EO.” However, when dissected, it is clear Biden’s Buy American plan does little to modify thresholds inconsistent with the Trump Administration; rather, the White House’s latest EO implements changes in the form of BA administration. Nonetheless, Biden’s EO does expressly note that it supersedes and replaces Trump’s EO on the same issues.
Reprinted courtesy of
Meredith Thielbahr, Gordon & Rees and
Nicole Lentini, Gordon & Rees
Ms. Thielbahr may be contacted at mthielbahr@grsm.com
Ms. Lentini may be contacted at nlentini@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
No Duty to Defend Construction Defect Claims
May 16, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined the insurer had no duty to defend construction defect claims asserted against the insured. Pa. Nat'l Mut. Cas. Ins. Co. v. River City Roofing, 2022 U.S. Dist. LEXIS 38226 (E.D. Va. March 3, 2022).
Branch Builds, Inc, was the general contractor for Shock Valley View Genesis, LLC ("Genesis") in charge of constructing apartments. River City Roofing was a subcontractor for all roofing, aluminum and composition siding at the project. River City contracted and warranted its materials and work, agreed to indemnify Branch, and agreed to make Branch an additional insured under its CGL policy.
After completion of the project, Genesis reported defects in the construction. The roof, aluminum and composition siding allowed water intrusion and property damage to the apartments. Branch repaired and compensated Genesis for all damage done to the apartments. Branch then sued River City and another subcontractor and demanded judgment of $3,000,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Forecast Sunny for Solar Contractors in California
June 06, 2018 —
Amy Pierce - Gravel2Gavel Construction & Real Estate Law BlogOn May 9, the California Energy Commission announced that it has “adopted building standards that require solar photovoltaic systems starting in 2020.” The 2019 Building Energy Efficiency Standards are expected to “reduce greenhouse gas emissions by an amount equivalent to taking 115,000 fossil fuel cars off the road.” California will be the first in the nation to require solar. The new standards take effect on January 1, 2020.
Read the court decisionRead the full story...Reprinted courtesy of
Amy L. Pierce, Pillsbury Winthrop Shaw Pittman LLPMs. Pierce may be contacted at
amy.pierce@pillsburylaw.com
Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Fourth Circuit Finds Insurer Reservation of Rights Letters Inadequate to Preserve Coverage Defenses Under South Carolina Law
January 17, 2023 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Stoneledge at Lake Keowee Owners Ass'n v. Cincinnati Ins. Co., 2022 U.S. App. LEXIS 34292 (D.S.C. Dec. 13, 2022), the Fourth Circuit Court of Appeals addressed the adequacy of reservation of rights letters issued by Builders Mutual Insurance Company (“Builders Mutual”) and Cincinnati Insurance Company (“Cincinnati”) to their insureds, Marick Home Builders, LLC (“Marick”) and Rick Thoennes (“Thoennes”), Marick’s managing member, for an underlying construction defect lawsuit. In short, the Fourth Circuit found that the reservation letters were inadequate to preserve the insurers’ coverage defenses because they did not sufficiently explain the basis of the carriers’ position.
Stoneledge, a homeowners association, managed a community of 80 townhomes on South Carolina’s Lake Keowee. In 2009, Stoneledge brought suit against Marick and Thoennes, among other defendants, alleging construction defects in the townhomes that resulted in water intrusion and other physical damage. Marick and Thoennes held commercial general-liability policies through Cincinnati and Builders Mutual covering, in relevant part, “property damage” as defined by the policies. Builders Mutual issued policies covering the period from January 2004 to October 2007, and Cincinnati issued policies covering the period from April 2008 to April 2012. After Marick notified the insurers of the underlying action, Builders Mutual sent Marick two reservation of rights letters, one in May 2009 and one in July 2009. Cincinnati sent Marick one reservation of rights letter in March 2010.
In March 2014, Stoneledge brought a declaratory-judgment action against Cincinnati seeking coverage for a judgment entered in the underlying action. The insurers removed the case to federal court, and in September 2016, Stoneledge amended its complaint, adding Builders Mutual as a defendant and seeking coverage for additional damages pursuant to a settlement agreement entered into by Stoneledge, Marick, Thoennes. The district court granted Stoneledge's motion for summary judgment, primarily on the ground that the insurers failed to reserve the right to contest coverage. The insurers appealed to the Fourth Circuit, which affirmed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
The Great Skyscraper Comeback Skips North America
February 05, 2015 —
Patrick Clark – BloombergTall buildings are back. Developers around the globe completed a record 97 buildings of at least 200 meters (656 feet) in height in 2014, according to a new report from the Council on Tall Buildings and Urban Habitat, as size-obsessed builders got back on a growth track after a two-year skyscraper dip.
It’s not hard to explain the pattern. A typical skyscraper takes two to four years to finish, says report co-author Daniel Safarik. Work back from the year of completion, and the global financial crisis looks like an easy explanation for the drop-off in tall buildings. If you thought it was hard to get a home loan in 2009, imagine asking bankers to finance a gravity-and-wind-defying symbol of luxury, industry, and capitalist will. Especially, as Bloomberg Businessweek’s Bryant Urstadt pointed out, since supertall buildings are notorious for being hard to fill with tenants. (It’s worth noting that “tall” isn’t a technical term, though “supertall,” which is used to describe buildings more than 300 meters tall, is. And construction schedules vary. The Ryugyong Hotel in Pyongyang, North Korea, planned for 330 meters, has been under construction for 28 years, according to a CTBUH report last year.)
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Insurance Attorney Gary Barrera Joins Wendel Rosen’s Construction Practice Group
July 26, 2017 —
Garret Murai - California Construction Law BlogWendel Rosen’s Construction Practice Group welcomes a new member to our band of merry men (and women), Gary Barrera.
Gary, an insurance attorney, has extensive experience with construction defect, property damage, professional liability and environmental claims. He has represented real estate developers and contractors in all aspects of construction defect litigation and has resolved insurance coverage disputes arising out of construction claims on behalf of policyholders. Prior to attending law school, Gary worked as a claims representative and examiner for several insurance carriers and third-party administrators.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at