Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Balancing Cybersecurity Threats in Smart Cities: Is the Potential Convenience of “Smart” Intersections Worth the Risk?
September 02, 2024 —
James P. Bobotek & Brian E. Finch - Gravel2Gavel Construction & Real Estate Law BlogThe term “smart cities” has become popular parlance for municipalities’ attempts to enhance delivery of urban services and infrastructure through information and communications technology. While they may conjure images of neon-lit high rises or streetscapes populated by sleek, hovering vehicles, a bit like the 1960s-era The Jetsons cartoon envisioned our high-tech future, the reality of smart cities has begun to emerge in more subtle, less glamourous forms. Cities tend to focus on wastewater monitoring, traffic control and energy distribution technologies in their efforts to become incrementally “smarter.”
Smart cities lean heavily on automation, internet connectivity and the Internet of Things (IoT)—including smartphones, connected cars and a host of web-based appliances and utilities—to boost the delivery and quality of essential urban services and infrastructure like transit, sanitation, water, energy, emergency response and more. Successful smart cities need infrastructure that supports such connectivity, and they pull data from hundreds, or even thousands, of sensors that can be used to analyze and shepherd the direction of resources.
Reprinted courtesy of
James P. Bobotek, Pillsbury and
Brian E. Finch, Pillsbury
Mr. Bobotek may be contacted at james.bobotek@pillsburylaw.com
Mr. Finch may be contacted at brian.finch@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Atlanta Office Wins Defense Verdict For Property Manager On Claims By Vendor, Cross-Claims By Property Owner
January 08, 2024 —
Lewis Brisbois NewsroomAtlanta, Ga. (December 18, 2023) – Atlanta Partner
Adi Allushi and Associate
Cecilia Walker recently secured a defense verdict for a national property management corporation on claims brought by a vendor and cross-claims lodged by the property owner. Lewis Brisbois’ client is a national corporation, over a century old, that managed over 140 properties with 40,000 units.
In 2019, the client entered the Georgia market managing three apartment complexes owned by a hedge fund in New York. The owner terminated without cause the client within six months, and several vendors – including the plaintiff, who was a remedial services provider – were not paid during the last few months and the transition period. The plaintiff sued the owner for the unpaid services, as well as an incorrect entity it believed to be the client. The owner cross-claimed against the client for fraudulent misrepresentations. Based on the misnomer statute, the court granted default judgment against the client.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Guidance for Construction Leaders: How Is the Americans With Disabilities Act Applied During the Pandemic?
September 28, 2020 —
Molly Gwin - Construction ExecutiveWith the spread of the COVID-19 pandemic, numerous cities and states have mandated infection control practices, including social distancing, mask requirements and sanitization of work areas and tools. As a result, many construction leaders now have questions as to how government guidance related to COVID-19 interacts with the Americans with Disabilities Act (ADA). For example, can a project manager enforce a mask mandate when a construction worker presents a doctor’s excuse noting breathing difficulties? Or, what if the employer is aware that an individual presents a higher risk for severe illness because of an underlying health condition, but that employee does not request an accommodation?
Thankfully, the United States Equal Employment Opportunity Commission (EEOC) recently published guidance relating to these requests that construction leaders can reference. While our goal is to summarize that guidance and provide practical advice for the construction sector, this article does not substitute for situation specific legal counsel.
SCENARIO 1: AN EMPLOYEE REFUSES TO WEAR A MASK AND PRODUCES A DOCTOR’S NOTE CITING BREATHING DIFFICULTIES. MUST THE EMPLOYER ACCOMMODATE SUCH A REQUEST?
Potentially. Since the request to not wear a mask is considered an accommodation under the ADA, the employer can still require a doctor’s note when considering the accommodation.
Reprinted courtesy of
Molly Gwin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Gwin may be contacted at
mgwin@isaacwiles.com
Is a Text a Writing?
June 10, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCIs a text message a writing? Project communication is constantly evolving, and text messages are an increasingly common way teams share pictures, video, and provide project updates. When texting is part of the communication flow on a project, contractors and owners might text approvals for extra work, notices of changed conditions, or other information that could be a basis for a change order.
In a text exchange about a compensable event, the notice, reply, and approval are all saved on the phone. But contracts often contain specific requirements for a contractor or subcontractor to request changes and authorization to proceed may be specifically required in writing.
For example, the Associated General Contractors of Washington – 2018 Standard Subcontract says the “Subcontractor shall make no claims for extras unless the same shall be agreed upon
in writing by Contractor prior to performance of any such extra work.” (emphasis added).
The AGC subcontract doesn’t define “writing,” so the subcontractor and contractor might wonder if a text message exchange about a potentially compensable event was an “agreement in writing.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Denver’s Mayor Addresses Housing and Modifying Construction Defect Law
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFDuring his State of the City Address, Mayor Michael Hancock discussed housing, specifically calling “on the state legislature to modify a construction defects law,” according to KWGN news.
“…it is my sincere hope that the 2015 State Legislature will recognize the chilling effect the construction defects law has on the for sale condo market,” Hancock stated, as reported in The Denver Post. “I encourage lawmakers to modify the law so that we can experience the full potential of housing in metro Denver.”
Hancock also claimed that though the population has increased, the “housing stock has not kept pace,” according to KWGN. “This gap is exacerbated by rising home prices, which are good news for homeowners and our local economy, but a challenge for many residents and families.”
Read the full story, KWGN...
Read the full story, Denver Post... Read the court decisionRead the full story...Reprinted courtesy of
Insurance Policies and Indemnity Provisions Are Not the Same
October 19, 2020 —
Garret Murai - California Construction Law BlogJust because you own a pair of Air Jordans doesn’t make you Michael Jordan. In the next case, Carter v. Pulte Home Corporation, Case No. A154757 (July 23, 2020), the 1st District Court of Appeal denied an insurance carrier’s equitable subrogation claim explaining that an insurer’s obligations under its insurance policy are not the same as an idemnitee’s obligations under an indemnity provision. Or, as aptly put by the Court of Appeal, while a “subrogated insurer is said to ‘stand in the shoes’ of its insured, because it has no greater rights than the insured. Here . . . [the insurer] is seeking to stand in a different, more advantageous set of shoes.”
Carter v. Pulte Home Corporation
Pulte Home Corporation was sued for construction defects by 38 homeowners in two housing developments. Various subcontractors had worked on the projects, but under their subcontracts, each subcontractor agreed to indemnify Pulte from and against “all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (‘Claims’) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte . . . ”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Traub Lieberman Partner Lisa M. Rolle Wins Summary Judgment in Favor of Third-Party Defendant
May 06, 2024 —
Traub LiebermanTraub Lieberman Partner Lisa M. Rolle won summary judgment in favor of Third-Party Defendant, a general contracting company (the “Contracting Company”), in a personal injury action brought in Suffolk County. In the underlying matter, the Plaintiff—an employee of the Contracting Company—alleged that they sustained injuries from an incident which occurred when they were struck by a skid-steer loader owned by the Co-Defendant masonry company (the “Masonry Company”) and operated by the president and owner of the Co-Defendant/Third-Party Plaintiff construction company (the “Construction Company”). The Plaintiff brought claims against the Defendant companies for common law negligence and violations of Labor Law § § 200, 240, and 241, as well as Industrial code (12 NYCRR) subpart 23-2.
Reprinted courtesy of
Lisa Rolle, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of