Firm Sued for Stopping Construction in Indiana Wants Case Tried in Germany
October 16, 2013 —
CDJ STAFFGetrag Transmission, a German firm, is being sued by a Detroit-based construction firm that Getrag had hired to build a factory in Indiana. When a court gave the go-ahead to Walbridge Construction for the suit, Getrag appealed, stating that the case should be held in German so that Getrag officials do not have the expense of traveling to Indiana.
Getrag was building the plant, which would have cost $350 million, as part of a partnership with Chrysler. Chrysler dropped from the project after filing for bankruptcy. Shortly afterward, Getrag also filed for bankruptcy.
Walbridge is seeking $118.5 million due to expenses incurred with subcontractors. Chrysler has announced its intention of finishing the plant, which they estimate will cost about $162 million. Once complete, the plant will employ about 850 workers.
Read the court decisionRead the full story...Reprinted courtesy of
Updates to AIA Contract Applications
January 07, 2025 —
Anand Gupta - Construction Law Zone BlogThe construction industry often relies on contract forms drafted by the American Institute of Architects (AIA). These AIA forms include agreements between owners, designers, consultants, contractors, subcontractors, and construction managers. Some prefer to use the forms in the stock form, but others prefer to modify the language to their benefit. These modifications can be made in Microsoft Word and uploaded into AIA’s current web-based system, ACD5, to create redlines against the standard AIA forms (Checked-Drafts) and final clean versions without the “DRAFT” watermarks. Law firms and clients keep repositories of these modified templates for future projects.
A common issue with modifying documents offline in Microsoft Word and passing the documents back-and-forth between different email and document management systems is that the metadata of the forms becomes corrupted. AIA technical support then must reset the metadata, which takes hours or days. This delay can pose challenges to clients when they are up against a deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Anand Gupta, Robinson+ColeMr. Gupta may be contacted at
agupta@rc.com
4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of
Mortgage Whistleblower Stands Alone as U.S. Won’t Join Lawsuit
April 28, 2014 —
Jef Feeley and David McLaughlin – BloombergTwo years after Lynn Szymoniak helped the U.S. recover $95 million from Bank of America Corp. and other lenders for mortgage-fraud tied to the housing bubble, the whistle-blower said the government is ignoring a chance to collect more money for identical claims against other banks.
Szymoniak got $18 million when the U.S. Justice Department intervened in her foreclosure-fraud lawsuit. The government negotiated a settlement with five lenders including Bank of America and JPMorgan Chase & Co. (JPM)
The other banks accused of the same behavior, including Deutsche Bank AG (DBK) and HSBC Holdings Plc (HSBA), are still fighting Szymoniak’s suit, saying she isn’t a true whistle-blower. And the U.S., while continuing its crackdown on banks that packaged risky loans for sale as securities, hasn’t joined with her this time, leaving her to fight the banks alone. U.S. District Judge Joseph Anderson in Columbia, South Carolina, today is set to consider their bid to throw the case out.
Mr. Feeley may be contacted at jfeeley@bloomberg.net; Mr. McLaughlin may be contacted at dmclaughlin9@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Jef Feeley and David McLaughlin, Bloomberg
Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
Know and Meet Your Notice Requirements or Lose Your Payment Bond Claims
May 17, 2021 —
Chris Broughton, Jones Walker LLP - ConsensusDocsTime is of the essence in the construction industry, and failing to provide timely notice of your payment bond claim can end your chance of recovery. Payment bonds guarantee payment for the subcontractors and suppliers who provide labor or materials on covered construction projects. Federal and state statutes governing payment bonds on public projects and the specific terms of non-statutory, private payment bonds have strict notice and timing requirements. Claimants who fail to provide timely notice can forfeit their chance of recovery. This article provides a brief overview of the notice requirements for payment bond claims – who has to give notice, what notice is required, and when you have to give notice.
Payment bond protection is a frequent feature in construction. Payment bonds are required on most federal construction projects of over $100,000 under the federal Miller Act. Similar state statutes, typically referred to as “Little Miller Acts,” also require payment bonds on most state and local construction projects. Owners on private projects may require their general contractor to provide a payment bond to protect the property from liens. Finally, general contractors may also require subcontractors to provide payment bonds on public or private projects.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
Insured's Claim for Replacement Cost Denied
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Illinois Appellate Court affirmed the trial court's ruling that the insured was only entitled to the actual cost value of his loss, not the replacement cost. Lytle v. Country Mutual Ins. Co., 2015 Ill. App. LEXIS 756 (Sept. 30, 2015).
The insured's home was built around 1903. On June 21, 2011, the insured discovered damage to his home because of a severe storm. He made a claim with his insurer, Country Mutual.
The policy contained a depreciation holdback provision. The provision said the insurer would not pay more than the actual cash value until the actual repair or replacement was complete. If the insured elected to accept actual cash value, he would have one year from the date of the loss to repair or replace the damaged property and request the difference between the actual cash value and the replacement cost.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
How to Build a Water-Smart City
August 23, 2021 —
Chris Malloy - BloombergCities across time have stretched to secure water. The Romans built aqueducts, the Mayans constructed underground storage chambers, and Hohokam farmers dug more than 500 miles of canals in what is now the U.S. Southwest.
Today’s cities use portfolios of technologies to conserve supply — everything from 60-story dams and chemicals to centrifugal pumps and special toilets. And yet, the cities of tomorrow will have to do more.
A recent United Nations report on drought says climate change is increasing the frequency, severity and duration of droughts, which contribute to food insecurity, poverty and inequality. The report also asserts that “drought has been the single longest-term physical trigger of political change in 5,000 years of recorded human history.” It calls for urgent action and a transformation in governance to manage modern drought risk more effectively.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Malloy, Bloomberg