Ten-Year Statute Of Repose To Sue For Latent Construction Defects
November 12, 2019 —
David Adelstein - Florida Construction Legal UpdatesIf you are dealing with latent construction defects, it is imperative that you consult with counsel to understand your rights. This not only includes claims for property damage stemming from latent construction defects, but also personal injury stemming from such defects. There is a ten-year statute of repose to sue for latent construction defects. See Fla.Stat. s. 95.11(3)(c). After the expiration of this statute of repose you are out of luck, meaning you can no longer sue.
Now, I probably will not be the first to tell you that the statute of repose is not written so clear that you know the precise date it ends (or the last date you can sue for a latent defect). For this reason, you really want to operate conservatively, meaning it is always better to sue early if you think you could be running on the end of the statute of repose period. It is always advisable to avoid any legitimate argument that you filed your construction defect lawsuit too late.
In Harrell v. The Ryland Group, 44 Fla. L. Weekly D2054b (Fla. 1st DCA 2019), a subsequent owner of a house sued the original homebuilder in negligence for a construction defect causing a personal injury. The subsequent owner claimed the homebuilder defectively installed an attic ladder (that provided access to the attic for the original construction) which collapsed as he was using it. The homebuilder filed a motion for summary judgment that the statute of repose expired so the owner’s claim was time-barred. The First District agreed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Saudi Arabia Awards Contracts for Megacity Neom’s Worker Housing
September 16, 2019 —
Vivian Nereim - BloombergSaudi Arabia has awarded to two Saudi firms contracts to build worker housing for its futuristic mega-city called Neom, as plans for the $500 billion project move forward despite skepticism from investors.
Tamimi Group and Saudi Arabian Trading & Construction Co. won contracts to finance, build and operate three residential areas with capacity to house 30,000 people, Neom said in a statement on Sunday. The areas will be part of a so-called “Construction Village,” which Neom later plans to expand to accommodate more than 100,000 residents, it said. Neom did not say how much the contracts were worth.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim, Bloomberg
As Some States Use the Clean Water Act to Delay Energy Projects, EPA Issues New CWA 401 Guidance
August 26, 2019 —
Anthony B. Cavender - Gravel2GavelIn just the past few weeks, three states have used their Clean Water Act 401 authority to delay, for an indefinite period, FERC-authorized pipeline expansion projects. On May 6, 2019, the Oregon Department of Environmental Quality denied, without prejudice, Jordan Cove’s application for a Section 401 water quality certification. Jordan Cove plans to build an LNG export terminal at Coos Bay, Oregon, if it can obtain the necessary federal and permits. Under Section 401(a) of the Clean Water Act, any applicant for a federal permit to conduct any activity, including the operation of facilities which may result in any discharge into the navigable waters, shall provide the permitting agency a certification from the State in which the discharge may originate that any such discharge will comply with the applicable provisions of the Clean Water Act, including effluent limitations and state water quality standards. The States have a “reasonable time”—which shall not exceed one year after the receipt of the 401 application—in which to act, or the state’s authority may be waived by this inaction. The Oregon DEQ concluded that Jordan Cove has not demonstrated that its project, as presently configured, will satisfy state water quality standards. The 401 applications submitted by Transcontinental Gas Pipe Line Co. (Transco) to the New Jersey Department of Environmental Protection and the New York State Department of Environmental Protection were similarly rejected without prejudice on May 15, 2019 (New York) and June 5, 2019 (New Jersey). This use of the states’ 401 authority has frustrated plans to build and operate LNG pipelines around the country.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Massachusetts High Court: Attorney's Fee Award Under Consumer Protection Act Not Covered by General Liability Insurance Policy
September 19, 2022 —
Jeffrey J. Vita & David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of
Vermont Mutual Insurance Co. v. Poirier, 189 N.E.3d 306 (Mass. 2022), Massachusetts’ Supreme Judicial Court concluded that an award of attorney's fees pursuant to
Chapter 93A (Massachusetts’ Consumer Protection Act) is not covered under an insured’s general liability insurance policy. Applying Massachusetts law, the Court found that a statutory award of attorney’s fees stemming from a bodily injury claim is not reasonably considered “damages because of bodily injury” or “costs taxed against the insured” so as to trigger general liability coverage.
Facts of the Case
A Servpro company (owned by Mr. and Mrs. Poirier) was hired to clean up a basement after a sewage spill. The owners of the home were injured by fumes from chemicals used in the cleanup and accordingly brought suit against the Poiriers and their Servpro business. In the lawsuit, the homeowners alleged negligence, breach of contract, and also a Chapter 93A claim, asserting breach of warranty of merchantability and warranty of fitness for a particular purpose. Prior to trial, the plaintiffs waived the negligence and breach of contract claims and sought a bench trial on the Chapter 93A claims alone.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
David G. Jordan, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Board May Discipline Over Workers’ Comp Reporting
November 06, 2013 —
CDJ STAFFCalifornia recently passed AB 1794, which authorized the Employment Development Department to share information it received on new hires with other agencies. The bill also allows the Contractors State License Board to audit members based on this information to determine if contractors are engaging in workers’ compensation fraud.
Writing on the Cumming & White construction litigation blog, Iman Reza notes that “the new law is intended to deter contractors from cutting corners in underreporting employees.” The CSLB will be able to discipline contractors who seek to gain an illegitimate competitive advantage by circumventing the law.
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Halts Enforcement of the OSHA Vaccine or Test Mandate
January 17, 2022 —
Stephen E. Irving, Kevin J. O’Connor, Aaron C. Schlesinger & Lauren Rayner Davis - Peckar & AbramsonThe United States Supreme Court today stayed enforcement of the OSHA emergency temporary standard (ETS) requiring employers with 100 or more employees to require employees either be “fully vaccinated” against COVID-19 or submit to weekly testing. The ruling immediately stops enforcement of the rule which had gone into effect on January 10, 2022.
Today’s order raises significant doubt as to whether the ETS requirement will ever take effect in its current form. A 6 to 3 majority of the Supreme Court justices issued the profound statement that the parties opposed to the rule “are likely to succeed on the merits of their claim that the Secretary lacked authority to impose the mandate.” The Court went on to state that the OSH Act does not authorize the agency to “set . . . broad public health measures,” such as the found in the current emergency standard.
Reprinted courtesy of
Stephen E. Irving, Peckar & Abramson,
Kevin J. O’Connor, Peckar & Abramson,
Aaron C. Schlesinger, Peckar & Abramson and
Lauren Rayner Davis, Peckar & Abramson
Mr. Irving may be contacted at sirving@pecklaw.com
Mr. O'Connor may be contacted at koconnor@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Davis may be contacted at ldavis@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How is Negotiating a Construction Contract Like Buying a Car?
March 01, 2017 —
Christopher G. Hill – Construction Law MusingsI know, you’re probably looking for a punchline, and likely thinking something along the lines of “only a construction attorney would be sitting in his office and come up with such an analogy,” but I really do think it’s a good one.
When you are buying a car, you look for priorities. Is the color what you want? Is the motor a hybrid or a v-6? Does it have Android Auto? What is the fuel mileage? All of these things may be more or less important to you. If you can get your priorities for a price that is attractive, you will likely let some other less important items, e. g. trunk space or rear seat leg room, slide and purchase the car anyway. Furthermore, you may use these minor items as negotiating points to either get one of the priorities or a lower price. Of course the dealership will want to get its priorities, likely a sale and a profit, when negotiating and will have certain items that it won’t move on just as you have terms that you won’t move on.
Much like when you walk onto the car lot, and particularly as a subcontractor looking at a contract from a general contractor, or a GC looking at the contract from the owner of a project, a construction contract presented to you is the starting point. When looking at the contract, be sure to have some non-negotiable items in mind when taking a critical eye to the terms of that contract. Some of these terms may be more or less negotiable depending on your experience with the other party to the construction contract. For instance, striking a pay if paid clause may be less important with a paying party with whom you have a 10 year history without payment problems. On the other hand, if it is your first contract with the other party, a stricter list may be required. So, much like a dealer that you know will stand behind its cars, you may be more willing to take more “risk” in entering a construction contract with a trusted/known owner or GC.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com