Construction Manager’s Win in Michigan after Michigan Supreme Court Finds a Subcontractor’s Unintended Faulty Work is an ‘Occurrence’ Under CGL
August 03, 2020 —
Gabrielle Szlachta-McGinn - Newmeyer DillionOn June 29, 2020, the Michigan Supreme Court overturned a longstanding precedent that commercial general liability (“CGL”) insurers have historically relied upon to deny insurance coverage for claims involving pre-1986 CGL policies. See Hawkeye-Security Ins. Co. v. Vector Const. Co., 185 Mich. App. 369, 372, 460 N.W.2d 329, 331 (1990). In its recent ruling, the state Supreme Court unanimously agreed that an Insurance Services Office, Inc. (“ISO”) 1986 standard CGL policy, which is sold to construction contractors across the United States, provides coverage for property damage to a policyholder’s work product that resulted from a subcontractor’s unintended faulty workmanship. Skanska USA Bldg. Inc. v. M.A.P. Mech. Contractors, Inc., No. 159510, 2020 WL 3527909 (Mich. June 29, 2020).
In 2008, Skanska USA Building, Inc., the construction manager on a renovation project for Mid-Michigan Medical Center, signed a subcontract with defendant M.A.P. Mechanical Contractors (“MAP”) to install a new heating and cooling (“HVAC”) system. Id. During the renovation, MAP installed some of the expansion joints in the new HVAC system backwards. Id. The defective installation caused approximately $1.4 million in property damage to concrete, steel and the heating system, which Skanska discovered nearly two years after MAP completed the project. Id. After performing the repairs and replacing the damaged property, Skanska sought repayment for the repair costs from MAP and also submitted a claim to Amerisure seeking coverage as an insured under the CGL policy. Id. When Amerisure rejected Skanska’s claim, Skanska sued both parties. Id. Amerisure relied on the holding in Hawkeye and argued that MAP’s defective workmanship was not a covered “occurrence” under the CGL policy, which the policy defined as an accident. Id. at *4.
The Michigan Court of Appeals ignored the express language contained in the CGL policy and applied a prior appellate court precedent from Hawkeye, finding that MAP’s faulty work was not an “occurrence” and thus, did not trigger CGL coverage. Id. at *4. The Court of Appeals further reasoned that Skanska was an Amerisure policyholder and that the only property damage was to Skanska’s own work, which was not covered under the CGL policy. Id. at *5.
In a landmark decision, the Michigan Supreme Court reversed, holding unanimously that the Court of Appeals incorrectly applied the holding of Hawkeye because it failed to consider the impact of the 1986 revisions to standard CGL insurance policies. Id. at *10. Chief Justice Bridget M. McCormack explained that the Hawkeye decision rested on the 1973 version of the ISO form insurance policy, which specifically excluded certain business risks from coverage such as property damage to a policyholder’s own work. Id. The Supreme Court agreed that while Hawkeye was correctly decided, it did not apply here because the 1986 revised ISO policy includes an exception for property damage caused by a subcontractor’s unintentional faulty work. Id.
The Supreme Court said that under the plain reading of the current CGL policy language, an “accident” could include a subcontractor’s unintentional defective work that damaged a policyholder’s work product and thus, may qualify as an “occurrence” covered under the policy. Id. at *9. The Supreme Court defined an “accident” (which was not defined in the Amerisure policy) as “an undefined contingency, a casualty, a happening by chance, something out of the usual course of things, unusual, fortuitous, not anticipated, and not naturally to be expected.” Id. at *5; see Allstate Ins. Co. v. McCarn, 466 Mich. 277, 281, 645 N.W.2d 20, 23 (2002). The Supreme Court noted that there was no evidence suggesting that MAP purposefully installed the expansion joints backwards, nor was there evidence indicating that the parties affected by MAP’s negligence anticipated, foresaw, or expected MAP’s defective installation or property damage. Skanska, 2020 WL 3527909, at *4. Therefore, the Supreme Court concluded that an “occurrence” may have happened, which would trigger coverage under the CGL policy. Id. at *10.
Although this landmark decision changes Michigan law, the decision is limited to cases involving the 1986 ISO policy language revisions to CGL insurance policies. Id. The Supreme Court's decision does not overturn Hawkeye, but rather limits Hawkeye’s authority to cases involving the 1973 ISO form. Id.
Gabrielle Szlachta-McGinn was a summer associate at Newmeyer Dillion as part of the firm's 2020 summer class. You may learn more about Newmeyer Dillion's construction litigation services and find the group's key contacts at https://www.newmeyerdillion.com/construction-litigation/.
Read the court decisionRead the full story...Reprinted courtesy of
How Concrete Mistakes Added Cost to the Recent Frederick Douglass Memorial Bridge Project
December 16, 2023 —
Richard Korman - Engineering News-RecordA disputed insurance claim heading for trial next year over construction of Washington, D.C.'s two-year-old Frederick Douglass Memorial Bridge revolves around the design-build joint venture's problems in 2019 with concrete voids and honeycombing. The flaws required demolition and rebuilding costing millions of dollars.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Wall Street Journal Analyzes the Housing Market Direction
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFNick Timiraos of the Wall Street Journal listed “five takeaways” from this week’s housing reports. First, he stated that unless the May “seasonally adjusted annual rate isn’t revised down,” the sales of new homes were “at their highest levels in six years.”
Second, Timiraos claimed that “[s]ales have been soft, in part, because builders have been slow to ramp up production. While inventories are still very low, they are up 16% from last year.” For his final “takeaway,” Timiraos stated that while “home prices are up nearly 25% from their early 2012 levels, they’re still down 18% from their 2006 peak. There’s considerable variation, of course, from one city to another. Prices in Denver and Dallas have reached new highs. Others, such as Miami and Phoenix, have posted double digit increases over the past year, but prices are still off of their peak by more than a third.”
Read the court decisionRead the full story...Reprinted courtesy of
Administration Seeks To Build New FBI HQ on Current D.C. Site
February 28, 2018 —
Tom Ichniowski – ENRA Senate committee plans to examine a new $3.3-billion Trump administration proposal to demolish the Federal Bureau of Investigation's worn, outmoded headquarters in downtown Washington, D.C., and construct a new facility on that site.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, Engineering News-RecordMr. Ichniowski may be contacted at
ichniowskit@enr.com
How Technology Reduces the Risk of Façade Defects
March 20, 2023 —
Ori Aphek - Construction ExecutiveThe shell of the building is an onlooker’s first impression and crafts the architectural aesthetic, but it also plays a crucial role in enabling energy efficiency and protecting against the elements. Because façades are in direct contact with the elements, issues with water intrusion are the most common problem and the costliest to remedy, with anywhere from 30% to 70% of lawsuits related to water intrusion, half of it through the façade. Additionally, improperly installed façades pose significant safety risks because unsecured parts can fall and hit people below.
All these factors contribute to the façade being one of the most complex and costly aspects of a building to construct and inspect, making up 205 of the total project cost. Installing these systems correctly the first time is the most effective way to mitigate these threats. Teams should utilize data-informed technology that ensures plan adherence, reducing risk and avoiding errors during installation.
The Challenges of Façade Installation
Façade installation and subsequent inspection are inherently challenging, particularly for high-rise buildings. When performing post-installation verification manually, inspectors must review every element, joint by joint, window by window, stone by stone and brick by brick, which can take months to complete. Inspections of the entire building system are limited by this process, as inspectors can only access one portion of the building façade at a time and often have to inspect from indoors, on balconies or at the ground level, which doesn’t paint a complete picture. As a result, teams typically only perform spot checks on the façade and are rarely inspected to their fullest. This leaves many installation errors and defects, which serve as ticking bombs for future water intrusion or safety hazards.
Reprinted courtesy of
Ori Aphek, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Group Seeks Defense Coverage for Hard Rock Stadium Claims
December 09, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogIn an insurance coverage action pending in the S.D.N.Y., Hunt Construction Group (Hunt) contends that Berkley Assurance Company wrongfully denied defense coverage for claims arising out of the renovation of Hard Rock Stadium (home to the Miami Dolphins and Miami Hurricanes football teams).
The stadium owner, South Florida Stadium LLC (SFS), hired Hunt to serve as the construction manager for the renovation project. Hunt subcontracted with Alberici Constructors Inc. (Alberici) to design and fabricate roof structures for the stadium.
Hunt and SFS sued Alberici over its work on the project. In March 2017, Alberici asserted counterclaims against Hunt and SFS. In May 2018, SFS sought defense and indemnification from Hunt with respect to Alberici’s coverage claims.
Hunt is insured under claims made and reported professional liability insurance policies issued by Berkley with policy periods from June 15, 2016 to June 15, 2017 (with an automatic extended reporting period through August 14, 2017) and from July 15, 2017 to June 15, 2018. Hunt notified Berkley of Alberici’s counterclaim on July 20, 2017 (within the extended reporting period of the 2016-2017 policy) and of SFS’s indemnity claim on June 5, 2018 (within the 2017-2018 policy period).
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Extreme Rainfall Is Becoming More Frequent and Deadly
November 11, 2024 —
Lou Del Bello - BloombergTorrential rains that triggered floods and landslides have killed hundreds of people and displaced millions across parts of Africa, Europe, Asia and the US in recent months.
The unprecedented deluges overwhelmed even communities accustomed to extreme weather and showed the limitations of the early-warning systems and emergency protocols established in many countries to avoid major loss of life.
Climate scientists have warned that an accelerated water cycle is locked into the world’s climate system due to past and projected greenhouse gas emissions, and is now irreversible.
The communities that tend to pay the highest price are often in poorer countries, where environments can be more fragile and governance more patchy, and there are fewer resources to bounce back after a disaster.
Read the court decisionRead the full story...Reprinted courtesy of
Lou Del Bello, Bloomberg
Disjointed Proof of Loss Sufficient
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that when considered as a whole, separately filed proofs of loss and estimates of damage were sufficient to meet the requirements of a flood policy. Young v. Imperial Fire & Cas. Ins. Co., 2014 U.S. Dist. LEXIS 51863 (April 15, 2014).
On August 29, 2012, plaintiffs' property sustained flood damage due to Hurricane Isaac. After Imperial's adjustor inspected the property, advance payments were made for $5000 under the building coverage and $5000 under the contents coverage.
On October 26, 2012, the plaintiffs' adjustor submitted a proof of loss for building damages, stating the amount of loss was $175,100, which was the policy limit minus the deductible. The insured wife signed the proof of loss. The actual case value, full cost of replacement or repair, and applicable depreciation were listed "undetermined."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com