Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney
May 10, 2012 —
Douglas Reiser, Builders Council BlogI love writing this column, because I think it’s refreshing for contractors to hear that they don’t always need an attorney. Today’s post is the “Un-Save a Legal Fee” because I want to point out a specific illustration of when you definitely need your attorney. Using a construction contract template can be fine, but you always need to consider its application to each project ? or it could bite you in the rear.
Seattle attorney Paul Cressman published a prime depiction of bad contract management, last week. A Florida appellate court struck down a general contractor’s “pay if paid” clause when it became ambiguous because of some incorporated language from its prime contract. Specifically, a clause in the prime contract required the general contractor to pay all subcontractors before receiving payment from the owner, while the general contractor’s “pay if paid” clause required its subcontractors to wait for payment until it arrived from the owner.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Balfour Taps Qinetiq’s Quinn as new CEO to Revamp Builder
October 15, 2014 —
Benjamin Katz and Simon Thiel – BloombergBalfour Beatty Plc (BBY) named Leo Quinn as new chief executive officer to revamp Britain’s biggest builder which has suffered from mismanaged projects and a lack of demand.
Quinn will start on Jan. 1 after five years as CEO of defense specialist Qinetiq Group Plc, Balfour Beatty said today. The executive began his career at Balfour Beatty in 1979 as a civil engineer and later worked as president of Honeywell Building Controls and CEO of banknote printer De La Rue Plc. The stock gained 5.3 percent in London trading today.
Balfour Beatty, which rejected a merger proposal from British rival Carillion Plc in August, has struggled since the global recession slashed orders and prices. Its stock had fallen 48 percent this year before today, reducing the company’s value to 1 billion pounds ($1.6 billion). In September, Balfour Beatty cut its U.K. construction-services unit’s profit forecast and said Chairman Steve Marshall plans to leave.
Mr. Thiel may be contacted at sthiel1@bloomberg.net; Mr. Katz may be contacted at bkatz38@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Katz and Simon Thiel, Bloomberg
Properly Trigger the Performance Bond
January 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesOriginally Published by CDJ on January 5, 2017
A performance bond is a valuable tool designed to guarantee the performance of the principal of the contract made part of the bond. But, it is only a valuable tool if the obligee (entity the bond is designed to benefit) understands that it needs to properly trigger the performance bond if it is looking to the bond (surety) to remedy and pay for a contractual default. If the performance bond is not properly triggered and a suit is brought upon the bond then the obligee could be the one materially breaching the terms of the bond. This means the obligee has no recourse under the performance bond. This is a huge downside when the obligee wanted the security of the performance bond, and reimbursed the bond principal for the premium of the bond, in order to address and remediate a default under the underlying contract.
A recent example of this downside can be found in the Southern District of Florida’s decision in Arch Ins. Co. v. John Moriarty & Associates of Florida, Inc., 2016 WL 7324144 (S.D.Fla. 2016). Here, a general contractor sued a subcontractor’s performance bond surety for an approximate $1M cost overrun associated with the performance of the subcontractor’s subcontract (the contract made part of the subcontractor’s performance bond). The surety moved for summary judgment arguing that the general contractor failed to property trigger the performance bond and, therefore, materially breached the bond. The trial court granted the summary judgment in favor of the performance bond surety. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Mexico City Metro Collapse Kills 24 After Neighbors’ Warnings
May 17, 2021 —
Max De Haldevang & Maya Averbuch - BloombergThe collapse of a long-troubled Mexico City metro track killed 24 people and put two of President Andres Manuel Lopez Obrador’s top allies in the line of fire Monday night, after a decade of safety concerns and probes surrounding the project.
About 79 people were injured, Mayor Claudia Sheinbaum said Tuesday. A broken beam led to the incident on the Golden Line of the metro system, she said. An international agency and the attorney general’s office will investigate.
Reprinted courtesy of
Max De Haldevang, Bloomberg and
Maya Averbuch, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
The Construction Industry Lost Jobs (No Surprise) but it Gained Some Too (Surprise)
October 12, 2020 —
Garret Murai - California Construction Law BlogThe announcement this week by major airlines and then by Disney that they will be laying off tens of thousands of workers is just the latest in what we already know: The coronavirus pandemic has adversely impacted workers around the world. And the construction industry is no exception, although its impacts have been uneven, and in some cases surprisingly good.
According to a report by the Associated General Contractors of America, 39 states lost construction jobs between August 2019 and August 2020 while 31 states and the District of Columbia added construction jobs between July and August 2020.
California saw the largest decline in construction jobs between August 2019 and August 2020, down 52,000 jobs or 5.8%, followed by by New York (-46,000 jobs/-11.3%), Texas (-39,300 jobs/-5.0%), Massachusetts (-20,200 jobs/-12.4%) and Illinois (-17,200/-7.5%).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
No Collapse Coverage Where Policy's Collapse Provisions Deleted
July 26, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found there was no coverage for the homeowners' collapse claim because the collapse provisions were deleted from the policy. Gueng-Ho Kim v. State Farm Fire & Cas. Co., 2017 U.S. Dist. LEXIS 97871 (D. Conn. June 26, 2017).
The homeowners purchased their home in 2004. They also purchased a homeowners policy from State Farm. In the policy, State Farm deleted the additional coverage for collapse.Also deleted from the policy was language excluding coverage for "collapse, except as specifically provided in Section I - Additional Coverages, Collapse."
The homeowners discovered a problem with the property's foundation when they attempted to sell the house in 2014. The homeowners hired an engineer who found that the interior and exterior foundation had numerous spider-web cracks and the foundation walls in several locations bowed inward by as much as one and a half inches.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
You Are Not A “Liar” Simply Because You Amend Your Complaint
March 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn litigation, it is common for a plaintiff to amend their complaint. They may amend to add additional parties. To add new claims. To change the factual allegations. Or, to change the theme of their case.
Most of the time, complaints are not verified by the plaintiff. Instead, complaints are drafted and signed by the plaintiff’s counsel.
A question becomes: how prior reiterations of a complaint can be used against the plaintiff to show they are a bunch of “liars” by making amendments to their complaint. Sounds prejudicial to the plaintiff, right? Particularly if there is a jury.
The reality is that amending complaints for various reasons is routine. Doing so does NOT make the plaintiff a liar and is not a vehicle that a defendant should use to create this inference. A defendant that tries to do so simply wants to detract from the substantive facts and issues.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Montana Trial Court Holds That Youths Have Standing to Bring Constitutional Claims Against State Government For Alleged Climate Change-Related Harms
September 18, 2023 —
Paul A. Briganti & Julia Castanzo - White and Williams LLPOn August 14, 2023, in a “landmark” ruling, a Montana state court held that youth plaintiffs had standing to assert constitutional claims against the State of Montana, its governor and state agencies for “ignoring” the impact of greenhouse gas (GHG) emissions on climate change. Held v. State of Montana, Cause No. CDV-020-307 (1st Judicial Dist. Ct., Lewis & Clark Cty., Mt.). Agreeing with the plaintiffs, the court concluded that a limitation in the Montana Environmental Policy Act (MEPA), which prohibited the state from considering climate impacts when issuing permits for energy projects, violated the plaintiffs’ right under the state constitution to a “clean and healthful environment.”
MEPA, enacted in 1971, states that its purposes include “provid[ing] for the adequate review of state actions in order to ensure that . . . environmental attributes are fully considered by the legislature in enacting laws to fulfill constitutional obligations . . . .” In 2011, the legislature amended the statute to curtail the scope of environmental reviews. Under the so-called MEPA limitation, Montana agencies cannot consider “an evaluation of greenhouse gas emissions and corresponding impacts to the climate in the state or beyond the state’s borders.” Mont. Code Ann. § 75-1-201(2)(a). In 2023, the legislature added a provision that eliminated equitable remedies (i.e., the ability to “vacate, void, or delay a lease, permit, license, certificate, authorization, or other entitlement or authority”) for litigants who “claim that [an] environmental review is inadequate based in whole or in part upon greenhouse gas emissions and impacts to the climate in Montana or beyond Montana’s borders . . . .” Id. § 75-1-201(6)(a)(ii).
Reprinted courtesy of
Paul A. Briganti, White and Williams LLP and
Julia Castanzo, White and Williams LLP
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Ms. Castanzo may be contacted at castanzoj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of