Did the Court of Appeals Just Raise the Bar for California Contractors to Self-Report Construction-Related Judgments?
June 10, 2015 —
Garret Murai – California Construction Law BlogAn interesting construction case just came out from the California Court of Appeals for the Second District this past month – Pacific Caisson & Shoring, Inc. v. Bernards Bros., Inc., California Court of Appeals for the Second District, Case No. B248320 (May 19, 2015) – which discusses a number of intertwining issues that can be faced by contractors in California and concludes with a result that I’m not sure I quite agree with.
Among the issues discussed by the Court of Appeal were:
- The application of the dreaded Business and Professions Code section 7031 which: (1) precludes a contractor from making a claim for payment for work performed; and (2) requires a contractor to disgorge all monies received for work performed, if the contractor was not properly licensed at all times that work was performed;
- The impact of an unsatisfied judgment against one contractor on the license of another “related” contractor; and
- Whether a stipulated judgment providing for payments over time is an unsatisfied final judgment under the Licensing Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
WSHB Ranked 4th Most Diverse Law Firm in U.S.
July 14, 2016 —
Beverley BevenFlorez-CDJ STAFFAmerican Lawyer, in its annual Diversity Scoreboard Survey, ranked Wood Smith Henning & Berman LLP (WSHB) one of the four top law firms in the nation. Scores are based upon the firms’ combined percentage of minority lawyers as well as minority partners in U.S. offices.
“Historically, law has not been among the most diverse of professions,” Partner Domingo Tan, Chair of WSHB’s Recruiting Committee, stated according to the firm’s media release. “This trend has recently begun to change and I am proud that our firm is one of the national leaders in recognizing and celebrating diversity as a core value.”
WSHB Partner Jade Tran explained how the firm’s diversity benefits its clients: “At WSHB, we are a litigation powerhouse built upon the experiences drawn from our diverse attorney backgrounds. It’s this diversity that also makes our attorneys relatable to our clients who themselves stem from diverse backgrounds.”
Read the court decisionRead the full story...Reprinted courtesy of
The Construction Project is Late—Allocation of Delay
November 17, 2016 —
David Adelstein – Florida Construction Legal UpdatesThe construction project is late. Very late. The owner is upset and notifies the contractor that it is assessing liquidated damages. The contractor, in turn, claims that the project is late because of excusable, compensable delays and, perhaps, excusable, noncompensable delays. This is a common and unfortunate story between an owner and contractor on any late construction project. Now the fun begins regarding the allocation of the delay!
Through previous articles, I discussed that in this scenario the burden really falls on the contractor to establish that the liquidated damages were improperly assessed against it and, thus, it is entitled to additional time and/or extended general conditions as a result of excusable delays. Naturally, this requires the contractor to develop a critical path analysis (time impact analysis) allocating the impacts / delays (and the reasons for the impacts/ delays) to the project completion date. The reason the burden really falls on the contractor is because the owner’s burden is relatively easy – the project was not complete on time pursuant to the contract and any approved changed orders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
U.K. to Set Out Plan for Fire-Risk Apartment Cladding Crisis
March 01, 2021 —
Emily Ashton & Olivia Konotey-Ahulu - BloombergThe U.K. government will set out its plans for stripping cladding from potentially unsafe apartment blocks, more than three years after a fire at London’s Grenfell Tower killed 72 people.
Reports suggest Housing Secretary Robert Jenrick will set out a package of measures amounting to billions of pounds when he makes a statement to the House of Commons on Wednesday.
Ministers announced a 1.6 billion pound ($2.2 billion) “safety fund” to remove dangerous cladding last year but Jenrick is expected to announce additional support on top of this. The price for the repairs could be as high as 15 billion pounds, according to a parliamentary committee last June.
Reprinted courtesy of
Emily Ashton, Bloomberg and
Olivia Konotey-Ahulu, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Orlando Commercial Construction Permits Double in Value
October 01, 2013 —
CDJ STAFFThis August, permits were taken out for $102.3 million of commercial construction projects, a 95% increase over last August’s $52.4 million. Meanwhile, residential construction was up by a third, jumping from $205.6 million to $274.1 million. Overall that sent construction up by 46% in the Orlando area.
The construction industry is a major one in the Orlando area and its recovery provides some hope for the region.
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Information and Resources
May 04, 2020 —
Richard H. Glucksman, Esq. & Brian D. Kahn, Esq. – Chapman Glucksman Dean & Roeb BulletinINTRODUCTION
The current COVID-19 health crisis has greatly impacted nearly every aspect of our business and personal lives. The constant flow of rapidly evolving, and often contradictory information creates its own challenges for those who are responsible for ensuring compliance with relevant regulations and best practices while still moving forward with their business and family activities.
This bulletin differs from most Chapman, Glucksman, Dean & Roeb bulletins in that it does not highlight a recent case, statute or a single development, but rather acts as a resource and “links” to provide you with needed information and to simplify your search for critical information during this unusual and challenging time.
CIVIL LITIGATION: CLOSURES AND RESTRICTIONS
The State and Federal Court systems in California have drastically reduced their operations. The Governor issued Executive Order N-38-20, this suspends certain limitations on the Chief Justice’s authority, making it possible for orders to be issued adapting the Court’s operations to address the COVID-19 health crisis. As of this time, the most recent statewide order from the Chief Justice is the March 30, 2020 Order which allows Courts to utilize remote technology when possible. The March 30, 2020 Order also clarifies a prior Order suspending all trials for 60 days. As many of you are aware, civil trials in California must commence within five years of the initiation of the action, this is commonly referred to as the “five year rule”. While the five year time period was initially extended by the Chief Justice for 60 days, the Judicial Council subsequently adopted a series of Emergency Rules, including one which extends this to six months for all civil actions filed on or before April 6, 2020. The Judicial Council also adopted rules tolling the statutes of limitation for civil causes of action are tolled from April 6, 2020 to 90 days after the state of emergency has ended.
In addition to the statewide orders and rules, counties have enacted their own rules. Los Angeles Superior Court, for instance, has closed some locations while others remain open on a limited basis. On March 17, 2020 an Order was issued limiting the Court to “essential functions” through April 16, 2020. However, on April 15, 2020, a further Order extended the closure through May 12, 2020. While truly urgent Ex Partes may go forward, all regularly set hearings will be continued until after June 22, 2020. Trials will begin after June 22, 2020 with non-priority trials anticipated to start in later August or September. Notably, any deadlines imposed by current trial or hearing dates still stand until the specific dates are continued.
As with other aspects of the COVID-19 health crisis, the impact upon Civil Litigation continues to evolve, for the most up to date information we include the following links to the California Courts. The first page includes links to all the State and County Orders, the second page is for the Judicial Council Rules.
Links:
https://newsroom.courts.ca.gov/news/court-emergency-orders-6794321
https://newsroom.courts.ca.gov/news/judicial-branch-emergency-actions-criminal-civil-and-juvenile-justice
STATE AND LOCAL STAY AT HOME ORDERS
The State of California declared a state of emergency on March 4, 2020. On March 13, 2020 the President declared a national state of emergency. On March 19, 2020 Governor Newsom issued Executive Order N-33-20, also known as the “Stay at Home” order. This orders all Californian’s to stay at home, unless they are part of an essential businesses are exempt which generally includes construction and insurance. Generally, Californians are allowed to run essential errands, but they are not to congregate with those outside of their household.
In addition to the State, many cities and counties have enacted additional orders regarding whether certain types of businesses can remain open, use of parks, trails and other public amenities as well as what type of protective measures must be adhered to such as covering your face in public. As with Civil Litigation, the State and Local Government regulations continue to evolve. A link to the State’s COVID-19 page is below and we also encourage you to check your local City and County sites for additional information.
https://covid19.ca.gov/
BUSINESS AND FINANCIAL GUIDELINES
The impact of COVID-19 is unprecedented. While “essential businesses” may remain open for customers, steps must be taken to protect the health of both employees and customers. There are both State and, in many instances, Local Government regulations addressing these precautions. In addition to taking safety measures to protect the health of all involved, there are a multitude of financial concerns to be addressed. While most people have already heard about the moratorium on residential and commercial evictions, this does little to address how property owners will receive funds to pay their financial obligations, how tenants can pay their other obligations, how either can make payroll and most importantly, how employees who can no longer work due to their “non-essential” business being closed can put food on their tables.
The Coronavirus Aid, Relief, and Economic Security Act (the “CARES” act) may provide financial relief for many business by means of loans, some of which may be forgivable, and tax credits. The CARES act also modifies the Family Medical Leave Act (“FMLA”) to provide paid leave for those who cannot work due to COVID-19 as well as other benefits. The IRS has extended the deadline to file and pay taxes to July 15, 2020. Additionally, there are other Federal and State benefits which may be available for those whose jobs are impacted.
The financial impacts of COVID-19 are far reaching and continue to evolve. The Department of Insurance ordered insurance companies to return premiums for at least the months of March and April. This applies to certain lines of insurance where the risk of loss has fallen substantially. However, business interruption, environmental and pollution claims have increased exponentially. While most such policies require some physical damage in order to trigger an occurrence, there has been some discussion of legislation deeming the COVID-19 pandemic to fulfill the physical damage requirement.
If your business has been closed or impacted by COVID-19 we encourage you to review your insurance policies and key contracts to ascertain what your rights and obligations are as well as whether you may have any coverage for your losses. Just as importantly, speak with your business partners including vendors, customers and employees to ascertain their capabilities and willingness to work through this crisis.
US Department of Labor OSHA Guidelines:
https://www.osha.gov/SLTC/covid-19/
California Labor & Workforce Development Agency Resource Page:
https://www.labor.ca.gov/coronavirus2019/
California Employment Development Department:
https://www.edd.ca.gov/about_edd/coronavirus-2019.htm
CONSTRUCTION GUIDELINES
Many of our clients are involved in the construction industry. Construction has been deemed an essential activity and is exempt from many of the “stay at home” orders but certain protections and regulations still apply. In addition to the general workplace guidelines discussed above certain jurisdictions are providing guidance as to how to provide a safe construction site workplace. We have included a link the Los Angeles Department Building and Safety guidelines below.
However, in some instances work on a project may be delayed or may not be able to progress due to the project owner stopping work or the inability of subcontractors or suppliers to continue as originally intended. In this case one should review their contracts to see what justifies delay and inability to perform by either party and the impact thereof. Contracts should also be evaluated to ascertain whether the costs associated with compliance with the new COVID-19 regulations are a recoverable cost under the contract. As with the general business discussion above, contractors should review all available insurance, including builder’s risk to ascertain the existence of possible coverage.
LA DBS guidelines:
https://ladbs.org/docs/default-source/publications/misc-publications/construction-site-guidance.pdf
SUMMARY
The COVID-19 health crisis has had and, for the foreseeable future, will have a broad and severe impact on our society. The variety of evolving regulations on the Federal, State and Local Government levels make it challenging to comply, especially for businesses in operation. There are also a variety of resources available to help ensure compliance with these regulations as well as the financial and physical viability of our communities’ companies and employees. Please do not hesitate to contact us if you need any assistance in navigating these rules and resources.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean & Roeb and
Brian D. Kahn, Chapman Glucksman Dean & Roeb
Mr. Glucksman may be contacted at rglucksman@cgdrlaw.com
Mr. Kahn may be contacted at bkahn@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Lawsuits May Follow Hawaii Condo Boom
January 23, 2013 —
CDJ STAFFHawaii is having a bit of a building boom and with this, as Honolulu Civil Beat points out, comes a boom in construction defect litigation, noting that “if past experience is any indicator, the wave of construction will likely be followed by a surge in complex and, for attorneys at least, profitable litigation.” The article provides plenty of evidence to back up that assertion.
Defect claims are already resulted in a settlement at Pinnacle Honolulu, a 37-unit luxury condominium project. The owners received a $2.4 million settlement after building code violations were discovered, including fire partitions that either were not fully extended or were breached in some fashion.
Meanwhile, the owners of the Koolani Condominiums are still trying to collect on their $12 million arbitration award related to problems in the water system. Another luxury condominium project, the Hokua Condominiums, also has had problems with flooding from water pipes.
Read the court decisionRead the full story...Reprinted courtesy of
Civil RICO Case Against Johnny Doc Is Challenging
October 20, 2016 —
Wally Zimolong – Supplemental ConditionsNews that a non-union contractor had filed a Lawsuit against IBEW Local 98 and its leader, John Dougherty, made headlines this week. While making fodder for local media, the plaintiffs must bound several legal hurdles before IBEW Local 98 and “Johnny Doc” face any threat of liability.
Background on RICO
The lawsuit was filed under a set of laws known as the Racketeer Influenced and Corrupt Organizations Act (RICO). I have written about RICO’s impact on labor unions on this blog before and predicted that recent federal court cases made RICO claims against more viable. RICO is a Nixon era set of laws that were originally passed to combat organized crime. There is both a civil and criminal component to RICO. (Interestingly, the RICO act remained relatively dormant until then U.S. Attorney Rudy Giuliani began effectively using it to prosecute the mob in the 1980’s.) Although recent decisions have made RICO claims against unions more viable, any RICO claim is still challenging. Indeed, some courts require a plaintiff in civil RICO cases to file a separate RICO case statement detailing its allegations. RICO claims are powerful. Some have called RICO claims a “thermonuclear” litigation device because the law permits the award of trebel (triple) damages and attorneys fees.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com