Washington Supreme Court Sides with Lien Claimants in Williams v. Athletic Field
September 30, 2011 —
Douglas Reiser, Builders Council BlogThe Washington Supreme Court issued their opinion today on Williams v. Athletic Field, perhaps the most talked about construction law case in the past few years. I have discussed this case exhaustively here on Builders Counsel. Today we have a resolution.
In an unanimous opinion issued today, the high court sided with lien filers who followed a sample form provided in RCW 60.04.091. Additionally, the court found that a lien company - and presumably other persons - could sign the lien for the lien claimant, as an agent, without invalidating the lien.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Differences in Types of Damages Matter
June 22, 2016 —
Christopher G. Hill – Construction Law MusingsOver the last 7 and a half years (yes I have been doing this for that long), I have often “mused” on various contractual provisions and their application. Why? Because
the contract matters and will be enforced. Provisions like “no damages for delay” and “
pay if paid” litter construction contracts and will be enforced if properly drafted. These types of clauses affect whether and what types of damages you as a construction company can collect.
Of course, these clauses have their limitations. For instance, and as
pointed out by my pal Matt DeVries at his great Best Practices Construction Law blog, not all damages that a subcontractor or general contractor may attribute to coordination or other scheduling related issues are “delay damages” to which a “no damages for delay” clause may apply.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
After Restoring Power in North Carolina, Contractor Faces Many Claims
August 10, 2017 —
Jim Parsons - Engineering News-RecordHaving successfully helped to restore power to two North Carolina barrier islands, PCL Civil Constructors now faces the fallout from a July 27 construction incident that forced a week-long evacuation of 60,000 visitors, putting a potential multimillion-dollar dent in the region’s tourism-dependent economy.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
No Prejudicial Error in Refusing to Give Jury Instruction on Predominant Cause
November 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's judgment after the jury determined there was no coverage for a leaking pipe. Mendoza v. Pacific Spec. Ins. Co., 2024 Cal. App. Unpub. EXIS 5477 (Cal. Ct. App. Aug. 20, 2024).
The Mendoza's third amended complaint alleged their home was damaged "by overflow of water from the dwelling's plumbing system resulting from a broken pipe, which overflow undermined the structural integrity of the dwelling."
The Mendozas insured their home under a policy issued by Pacific. The policy insured the property against "sudden and accidental direct physical loss" except where expressly excluded. The Mendozas submitted a claim Pacific paid approximately $1800 for the loss and closed the claim. The amount paid did not include payment for any structural damage to the home. The Mendozas alleged that Pacific's failure to conduct a full and fair investigation into the structural damage and its inadequate payment of benefits was a breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Construction Project is Late—Allocation of Delay
November 17, 2016 —
David Adelstein – Florida Construction Legal UpdatesThe construction project is late. Very late. The owner is upset and notifies the contractor that it is assessing liquidated damages. The contractor, in turn, claims that the project is late because of excusable, compensable delays and, perhaps, excusable, noncompensable delays. This is a common and unfortunate story between an owner and contractor on any late construction project. Now the fun begins regarding the allocation of the delay!
Through previous articles, I discussed that in this scenario the burden really falls on the contractor to establish that the liquidated damages were improperly assessed against it and, thus, it is entitled to additional time and/or extended general conditions as a result of excusable delays. Naturally, this requires the contractor to develop a critical path analysis (time impact analysis) allocating the impacts / delays (and the reasons for the impacts/ delays) to the project completion date. The reason the burden really falls on the contractor is because the owner’s burden is relatively easy – the project was not complete on time pursuant to the contract and any approved changed orders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Claim for Punitive Damages Based on Insurers' Alleged Bad Faith Business Practices Fails
September 05, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss the bad faith claim based upon allegations of a general business practice of acting recklessly toward an insured's rights under the policy. Sandpiper Isle Condo. Ass'n v. Empire Indem. Ins. Co., 2022 U.S. Dist. LEXIS 114279 (M.D. Fla. June 28, 2022).
Sandpiper suffered property damage from Hurricane Irma. Empire accepted the claim but there was disagreement on the value of the damage. An appraisal issued an award in favor of Sandpiper but Empire failed to pay the benefits for two years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Applying Mighty Midgets, NY Court Awards Legal Expenses to Insureds Which Defeated Insurer’s Coverage Claims
February 10, 2020 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPIs an insured (or putative insured) entitled to recover its legal expenses if it is successful in coverage litigation? In some states, no. In many other states, yes – based on either a statute or the common law. In New York, an insured may recover such expenses if it was “cast in a defensive posture by the legal steps an insurer takes in an effort to free itself from its policy obligations,” and, while forced into that posture, the insured defeats the insurer’s claim. Mighty Midgets, Inc. v. Centennial Ins. Co., 389 N.E.2d 1080, 1085 (N.Y. 1979). As a corollary to that rule, the insured is not entitled to its expenses “in an affirmative action brought by [the insured] to settle its rights. . . .” Id. at 1085. Earlier this week, the New York federal court in United Specialty Ins. Co. v. Lux Maint. & Ren. Corp., 2019 U.S. Dist. LEXIS 201805 (S.D.N.Y. Nov. 20, 2019) became the latest to apply the Mighty Midgets rule, awarding several insureds their legal expenses after defeating the insurer’s declaratory judgment action.
In Lux, the CGL insurer of a façade-renovation contractor sued the contractor (its named insured) and several owners of a hospital (putative additional insureds) at which the façade-renovation work took place, claiming that the insurer did not owe a defense or indemnity to any of those companies in connection with an underlying bodily injury action brought by an employee of the contractor who was injured while performing the work. The insurer and the putative additional insureds filed cross-motions for summary judgment on the coverage issues, with the putative additional insureds also seeking to recover their legal expenses for defending against the insurer’s action. The U.S. District Court for the Southern District of New York concluded that, based on the contractor’s agreement to provide coverage for the hospital owners, and a comparison between the underlying allegations and the policy, the insurer owed the hospital owners coverage as additional insureds to the contractor’s policy; the court also concluded that the insurer owed coverage for the contractor’s contractual defense and indemnity obligations to the hospital owners. After concluding that the insurer’s claim that it did not owe coverage lacked merit, the court turned to the additional insureds’ request for their legal expenses.
The court examined the “well settled” rule under New York law “that an insured cannot recover his legal expenditure in a dispute with an insurer over coverage, even if the insurer loses and is obligated to provide coverage,” but also New York’s “limited exception” to that rule, “under which an insured who is ‘cast in a defensive posture by the legal steps an insurer takes in an effort to free itself from its policy obligations, and who prevails on the merits, may recover attorneys’ fees incurred in defending against the insurer’s action.’ ” Lux, 2019 U.S. Dist. LEXIS 201805, at *18 (quoting Mighty Midgets, 389 N.E.2d at 1085).
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Timothy A. Carroll, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com