Homeowners Must Comply with Arbitration over Construction Defects
January 06, 2012 —
CDJ STAFFThe California Court of Appeals has upheld a decision by the Superior Court of Kern County that homeowners must comply with arbitration procedures in their construction defect claim. The California Court of Appeals ruled on December 14 in the case of Baeza v. Superior Court of Kern County, denying the plaintiff’s petition that the trial court vacate its order.
The plaintiffs in the case are homeowners in various developments built by Castle & Cook. The homes were sold with a contract that provided for “nonadversarial prelitigation procedures, including mediation, and judicial reference.” The homeowners made defect claims and argued that Castle & Cooke failed to comply with statutory disclosure requirements and that some of the contracts violate related statutes.
The appeals court found that there was no ground for appeal of the lower court’s order to continue with prelitigation procedures. The court noted that the plaintiffs could not seek a review of the mediation until a judgment was issued, but that then the issue would be moot. The court felt that there were issues presented that needed clarification, and so they reviewed this case. This was cleared for publication.
The court considered the intent of the legislature in passing the Right to Repair Act, noting that “under the statutory scheme, the builder has the option of contracting for an alternative nonadversarial prelitigation procedure,” as established in Chapter 4. The court noted that Chapter 4 “contains no specifics regarding what provisions the alternative nonadversarial contractual provisions may or must include.”
The plaintiffs contended that the builder was in violation of the standards set out in Section 912, however the court responded that these sections set out one set of procedures, but they concluded that “if the Legislature had intended the section 912 disclosure provisions…it could have made the requirements applicable to all builders by locating them in a section outside Chapter 4.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Freddie Mac Eases Mortgage Rules to Limit Putbacks
May 13, 2014 —
Clea Benson and Jody Shenn - BloombergFreddie Mac, which along with Fannie Mae has forced home lenders to buy back tens of billions of dollars of flawed mortgages, said the companies are loosening rules that made banks more cautious about extending credit.
The government-backed companies will expand the pool of loans that become exempt from putback requests, Freddie Mac (FMCC) said in a memo to lenders today. Under the new rules, loans will typically be spared from such demands if borrowers make 34 of their first 36 scheduled monthly payments. Previously, borrowers needed to avoid delinquency for the first three years.
Ms. Benson may be contacted at cbenson20@bloomberg.net; Ms. Shenn may be contacted at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson and Jody Shenn, Bloomberg
Balfour in Talks With Carillion About $5 Billion Merger
July 30, 2014 —
Simon Thiel and Alex Webb – BloombergBalfour Beatty Plc (BBY), the U.K. construction company whose chief quit in May after predicting a profit drop, is in merger talks with rival Carillion Plc (CLLN) to form the country’s biggest builder with a market valuation of about 3 billion pounds ($5 billion).
A deal would create a market-leading service and construction business able to serve more clients and cut costs, the builders said in a statement yesterday, adding that they’re trying to develop a strategy and business plan. Balfour and Carillion surged as much as 13 percent and 14 percent respectively in London trading today.
Balfour, based in London, has struggled since the global recession, with a lack of building work in the U.K. and the cancellation of projects across Australia, where the company cut hundreds of jobs last year. A merged company would benefit from Carillion’s booming services business as the Wolverhampton, England-based builder expands its maintenance offerings for the rail, oil and telecommunication industries.
Mr. Thiel may be contacted at sthiel1@bloomberg.net; Mr. Webb may be contacted at awebb25@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Simon Thiel and Alex Webb, Bloomberg
NY Pay-to-Play Charges Dropped Against LPCiminelli Executive As Another Pleads Guilty
June 06, 2018 —
Mary B. Powers & Debra K. Rubin - Engineerings News-RecordThe former president of New York contractor LPCiminelli—the firm that has been at the center of an alleged pay-to-play scheme playing out since 2016 when he and two other executives were indicted—got a reprieve as federal prosecutors said they were dropping all charges against him, including wire fraud, conspiracy to commit wire fraud and making false statements to federal agents, according to a June 1 court filing.
Reprinted courtesy of
Mary B. Powers, ENR and
Debra K. Rubin, ENR
Ms. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds that the Notice-Prejudice Rule Applicable to Insurance is a Fundamental Public Policy of the State
October 14, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pitzer College v. Indian Harbor Ins. Co. (No. S239510, filed 8/29/19), the California Supreme Court held that California’s notice-prejudice rule is a fundamental public policy in the insurance context, supporting the application of California law under a choice of laws analysis. In addition, the Court held that the rule generally applies to consent (aka “no voluntary payments”) provisions in first party insurance policies but not to consent provisions in third party liability policies.
Pitzer College discovered soils contamination while building a new dormitory. Under pressure to complete construction before the start of the school year, Pitzer proceeded to remediate the soils, incurring $2 million in expense. Pitzer submitted a claim to Indian Harbor, which provided Pitzer insurance covering legal and remediation expenses resulting from pollution conditions discovered during the policy period.
The policy contained a notice provision requiring Pitzer to provide oral or written notice of any pollution condition to Indian Harbor and, in the event of oral notice, to “furnish … a written report as soon as practicable.” In addition, a consent provision required Pitzer to obtain Indian Harbor’s written consent before incurring expenses, making payments, assuming obligations, and/or commencing remediation due to a pollution condition. The consent provision had an emergency exception for costs incurred “on an emergency basis where any delay … would cause injury to persons or damage to property or increase significantly the cost of responding to any [pollution condition],” in which case Pitzer was required to notify Indian Harbor “immediately thereafter.” Lastly, a choice of law provision stated that New York law governed all matters arising under the policy.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Sudden Death”
October 17, 2023 —
Daniel Lund III - LexologyIt’s not football, though. Rather, just when you thought it was safe in Louisiana to wait to file a garden-variety construction contract payment claim, an appellate court slams the door on it – applying a statute of “repose” to your claim.
“Personal actions” – such as an action on contract – are generally subject in Louisiana to a 10-year “liberative prescription,” the applicable statute of limitations pursuant to Louisiana Civil Code article 3499.
Like some other states, Louisiana has a statute of “repose” – imposing “peremption” rather than prescription for claims having to do with construction projects – limiting those claims (generally speaking) to five years post-completion. Like other statutes of “repose,” Louisiana Revised Statute 9:2772 provides that claims on construction projects may not be filed after five years, a duration which is not subject to interruption or extension.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 —
Douglas Reiser, Builders Council BlogEver had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Affordable Global Housing Will Cost $11 Trillion
October 01, 2014 —
Flavia Krause-Jackson – BloombergReplacing the world’s substandard housing and building affordable alternatives to meet future global demand would cost as much as $11 trillion, according to initial findings in a McKinsey & Co. report.
The shortage of decent accommodation means as many as 1.6 billion people from London to Shanghai may be forced to choose between shelter or necessities such as health care, food and education, data disclosed at the 2014 CityLab Conference in Los Angeles show. McKinsey will release the full report in October.
The global consulting company says governments should release parcels of land at below-market prices, put housing developments near transportation and unlock idle property hoarded by speculators and investors. The report noted that China fines owners 20 percent of the land price if property is undeveloped after a year and has the right to subsequently confiscate it.
Read the court decisionRead the full story...Reprinted courtesy of