Minimum Wage on Federal Construction Projects is $10.10
November 26, 2014 —
Craig Martin – Construction Contractor AdvisorThe Department of Labor issued its final regulations to implement President Obama’s Executive Order raising the minimum wage to $10.10 per hour for workers on federal construction projects. The new minimum wage will not be effective until January 1, 2015, and will apply to most workers and most federal projects.
Covered Contracts
Executive Order 13658 applies to four major categories of contractual agreements:
- procurement contracts for construction covered by the Davis-Bacon Act (DBA) that exceed $2,000;
- service contracts covered by the Service Contract Act (SCA) that exceed $2,500;
- concessions contracts, including any concessions contract excluded from the SCA by the Department of Labor’s regulations at 29 CFR 4.133(b); and
- contracts in connection with Federal property or lands and related to offering services for Federal employees, their dependents, or the general public.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Bullet Train Clears Federal Environmental Approval
June 30, 2014 —
Michael B. Marois – BloombergThe U.S. Federal Railroad Administration has approved an environmental review needed to begin building a portion of a $68 billion California high-speed rail line that has been mired in lawsuits.
The agency, part of the Transportation Department, said in a release that it cleared a 114-mile (183-kilometer) stretch of the project in the Central Valley.
The California High-Speed Rail Authority has been blocked from selling bonds to begin construction of the first U.S. bullet train until a court decides whether details of the financing were adequately disclosed.
Read the court decisionRead the full story...Reprinted courtesy of
Michael B. Marois, BloombergMr. Marois may be contacted at
mmarois@bloomberg.net
Ex-San Francisco DPW Director Sentenced to Seven Years in Corruption Case
September 26, 2022 —
James Leggate - Engineering News-RecordA federal judge sentenced Mohammed Nuru, the former San Francisco public works director, to seven years in prison for bribery and kickbacks.
Nuru, 59, pleaded guilty to the charge of defrauding the public of its right to honest services earlier this year amid a federal investigation into public corruption in San Francisco’s government.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Surety’s Several Liability Under Bonds
March 20, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhen a payment or performance bond is issued on behalf of its bond-principal, the surety is jointly and severally liable with its bond-principal. This means the surety has several liability under the bond, i.e., you don’t need to pursue the principal of the bond to pursue liability under the bond, which is a separate written intrument. Thus, if you are claiming damages of $500,000, by way of example, you can sue both the principal and surety under the bond, you can ONLY sue the principal under the bond (which is rarely practical), or you can ONLY sue the surety under the bond (which, oftentimes, is very practical). In many instances where I am pursuing a bond claim on behalf of a client, particularly a payment bond claim, I only sue the surety and do not sue the bond-principal unless there are certain strategic reasons in doing so. This is because of the surety’s several liability under the bond and there may be solvency issues with the principal or contractual reasons that, strategically, make much more sense to exclude the principal from the action.
In MJM Electric, Inc. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2023 WL 2163087 (M.D.Fla. 2023), an electrical subcontractor was hired to perform electrical work by the prime contractor. The prime contractor had a payment bond. The project was delayed for two years. The electrical subcontractor claimed the prime contractor failed to compensate it for significant delays and out of scope work.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Harborside Condo Construction Defect Settlement Moves Forward
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Harborside Condominium Owners Association in Bremerton, Washington, “has an agreement to pursue $2.8 million in settlement costs for construction defects,” according to the Kitsap Peninsula Business Journal. Back in March of 2013, the association “filed a list of defects in its lawsuit against Kitsap County Consolidated Housing Authority [Housing Kitsap]” including water issues, drywall and foundation cracks, uneven cabinets, leaking showers and pipes, as well as other issues.
Housing Kitsap agreed that the association “has the right to pursue a settlement of $2.8 million from the authority’s contractors and insurance companies.” Marlyn Hawkins, the association’s attorney, stated that they have already received a payment for $840,000 from the insurance company “and will be negotiating or filing suit for the rest of the $2.8 million.”
Read the court decisionRead the full story...Reprinted courtesy of
New York Considers Amendments to Construction Industry Wage Laws that Would Impose Significant Burden Upon Contractors
August 04, 2021 —
Richard W. Brown & Michael D. Angotti - Saxe Doernberger & Vita, P.C.A bill that would amend the the wage and hour requirements of the New York Labor Law was recently passed by the New York State Legislature and is expected to be signed by Governor Cuomo. Bill Number S2766C (the “Bill”) is intended to protect construction workers against wage theft. However, it places a heavy burden on contractors to police the payroll practices of its downstream subcontractors and exposes them to potentially significant liability for the wage and hour violations of their subcontractors.
The proposed Bill would make a contractor or upstream subcontractor jointly and severally liable for any wages owed to employees of their subcontractors. The Bill allows for a private right of action for such subcontractor’s employee (or such employee’s representative) to bring a civil or administrative action seeking payment of unpaid wages owed pursuant to Section 198 of the New York Labor Law. In such an action against a subcontractor for unpaid wages, the contractor or upstream subcontractor is not only jointly and severally liable for any unpaid wages, but also for the prevailing claimant’s reasonable attorney fees, prejudgment interest, and, absent a good faith defense, liquidated damages equal to the amount of the wages owed.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Michael D. Angotti, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at RBrown@sdvlaw.com
Mr. Angotti may be contacted at MAngotti@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Drawing the Line: In Tennessee, the Economic Loss Doctrine Does Not Apply to Contracts for Services
December 11, 2023 —
Gus Sara - The Subrogation StrategistIn Commercial Painting Co. v. Weitz Co. LLC, No. W2019-02089-SC-R11-CV, 2023 Tenn. LEXIS 39 (Weitz), the Supreme Court of Tennessee (Supreme Court) considered whether the economic loss doctrine barred the plaintiff’s claims for fraud, negligent misrepresentation and punitive damages arising out of a contract with the defendant for construction services. The court held that the economic loss doctrine only applies to product liability cases and does not apply to claims arising from contracts for services. This case establishes that, in Tennessee, the economic loss doctrine does not bar tort claims in disputes arising from service contracts.
In Weitz, defendant, Weitz Co. LLC (Weitz), was the general contractor for a construction project and hired plaintiff Commercial Painting Co. (Commercial) as a drywall subcontractor. Weitz refused to pay Commercial for several of its payment applications, claiming that the applications were submitted untimely and contained improper change order requests. Commercial filed a lawsuit against Weitz seeking over $1.9 million in damages, alleging breach of contract, unjust enrichment, enforcement of a mechanic’s lien, and interest and attorney’s fees under the Prompt Pay Act of 1991. Weitz filed a counterclaim for $500,000 for costs allegedly incurred due to Commercial’s delay and defective workmanship. In response, Commercial amended its complaint to add claims for fraud, intentional and negligent misrepresentation, rescission of the contract and $10 million in punitive damages. Commercial alleged that Weitz received an extension of the construction schedule but fraudulently withheld this information from Commercial and continued to impose unrealistic deadlines.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com