Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Three Reasons Late Payments Persist in the Construction Industry
December 22, 2019 —
Patrick Hogan - Construction ExecutiveConstruction professionals are all too familiar with the payment issues that plague the construction industry. Contractors, subcontractors and material suppliers often have to deal with payment delays and even nonpayment—affecting cash flow and their ability to meet expenses.
According to an Atradius study, a quarter of all B2B invoices issued in North America are overdue. The construction industry accounted for one-third of those past-due invoices, and many contractors and construction business owners do not have a positive outlook on the industry's payment issues. The same survey found 55% of U.S. firms think there will be no change in the industry’s payment practices over the coming months—one-third even expects an increase in late payments.
These findings show that managing cash flow is a significant challenge in the construction industry. Having a negative cash flow will push the company toward financial trouble, which may ultimately lead to its demise. Understanding the reasons why payment issues persist in construction will help contractors protect their business, prevent these issues from happening or at least minimize their effect on the current operations.
Reprinted courtesy of
Patrick Hogan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Teaming Agreement is Still a Contract (or, Be Careful with Agreements to Agree)
November 18, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed teaming agreements in this past here at Construction Law Musings. These agreements are most typically where one of two entities meets a contracting requirement but may not have the capacity to fulfill a contract on its own so brings in another entity to assist. However, these agreements are contracts and are treated as such here in Virginia with all of the law of contracts behind them.
One illustrative case occurred here in Virginia and was decided by the Virginia Supreme Court. That case is CGI Fed. Inc. v. FCi Fed. Inc. While this is not strictly a “construction” case, it helps lay out some of the pitfalls of teaming agreements in general.
In this case, the parties entered into a fairly typical small business (FCI) Big Business (CGI) teaming arrangement for the processing of visas for the State Department. The parties negotiated the workshare percentage (read payment percentage) should FCI get the work and the teaming agreement set out a framework for the negotiation of a subcontract between FCI, the proposed general contractor, and CGI, the proposed subcontractor. After a while working together, FCI submitted a proposal to the State Department and as part of the negotiations of this proposal, the work percentage for CGI was lowered in exchange for some management positions for CGI relative to the work by amendment to the original teaming agreement. However, one day later FCI submitted a proposal to the State Department that not only didn’t include the management positions, but further lowered CGI’s workshare.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Failure to Consider Safety Element in Design Does Not Preclude Public Entity’s Discretionary Authority Under Design Immunity Defense
May 16, 2018 —
Garret Murai - California Construction Law BlogIn Rodriguez v. Department of Transportation, Case No. F074027 (March 27, 2018), the Court of Appeals for the Fifth District considered the following mind-twister: Can you knowingly approve something (which does not include something else) if you never considered the absence of that “something else?” Think about that for a moment . . . or, better yet, just read on.
Rodriguez v. Department of Transportation
In 2013, a pickup truck traveling westbound on State Route 152 toward Los Banos, California, ran off the road injuring Erik Rodriguez and the driver and killing another passenger. Rodriguez sued the California Department of Transportation (Caltrans) on the ground that the accident was caused by a dangerous condition on public property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
You Are on Notice: Failure to Comply With Contractual Notice Provisions Can Be Fatal to Your Claim
September 26, 2022 —
Jenifer B. Minsky - ConsensusDocsImagine your firm is the construction manager on a multi-million-dollar project. At the end of the project you are five million dollars out-of-pocket. You have a stack of claims for additional and extended work which led to the overrun, payment for which will easily cover the shortfall. However, the owner refuses to compensate you until you can satisfactorily answer their inquiry: “Where are the notices that are expressly required under the terms of the contract?” You had a good relationship with the owner’s field representative who was aware you were performing the work and understood that your company was compiling claims. The once cooperative owner, now suffering financial restraints of their own, is resolute in their refusal leaving you no choice but to expend substantial sums of money to litigate the claims, the success of which is far from assured.
What Contract Language Can Be A Trap For An Unwary Contractor?
While courts are generally hesitant to order a forfeiture and some courts disfavor condition precedents, a judge’s hands may be tied by particular contract language requiring the strict enforcement of notice requirements. Such provisions may include: (1) an explicit clause that there be precise compliance with notice requirements; (2) express consequences for noncompliance (e.g., if the required notice is not provided the claim will be waived, forfeited or abandoned); (3) a statement that the notice requirements are a condition precedent to recovery; (4) language such as “if,” “provided that,” “or else” or “on condition that” (e.g., the owner shall review the claim, “provided such claim” was received within the applicable notice period) or (5) prohibition of any waiver of the notice requirement. To the extent the notice provision includes such language, a contractor can be without recourse even when the owner has actual knowledge of the claims or cannot show prejudice by the lack of notice.
Read the court decisionRead the full story...Reprinted courtesy of
Jenifer B. Minsky, Peckar & Abramson, P.C.Ms. Minsky may be contacted at
jminsky@pecklaw.com
Insured Fails to Provide Adequate Proof of Water Damage Through Roof
December 10, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer's motion for summary judgment due on the insured's claims for water damage to a church. Unity Church of God in Christ of York v. Church Mutual Ins. Co., 2024 U.S. Dist. LEXIS 163204 (M.D. Pa. Sept. 11, 2024).
Unity Church alleged that it suffered a sudden and accidental direct physical loss to its church. Wind damage to the roof of the church allowed rainwater to leak into the sanctuary of the church. Notice was given to Church Mutual Insurance Company, but coverage was denied.
Unity Church filed suit alleging breach of contract. Church Mutual answered and asserted a counterclaim for a declaratory judgment that the water damage to the church was outside the policy's coverage because the damage was caused by rain. Church Mutual filed for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Don’t Forget to Mediate the Small Stuff
August 02, 2017 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I talked mediation here at Construction Law Musings. Those that read regularly (thanks) have likely missed my musings on the topic. Those who read this construction blog regularly also know that I am both a Virginia Supreme Court certified general district court mediator and a huge advocate of mediation as a method to resolve construction disputes. While many of us think of mediation as a method to resolve the major disputes or litigation that occasionally rear their heads in the course of running a construction law practice or construction business, my experience as both a construction attorney and a mediator has taught me something: mediation works for all sizes of cases.
As an advocate for my construction clients, I know that proper trial preparation requires the same diligence and attention to detail for a smaller case as it does for a larger case. While a smaller case in the Virginia general district court may not have the depositions, written discovery and motions practice that a Virginia circuit court case may have, it still requires witness preparation, document processing and review and many of the other aspects of a larger case. While construction litigation is never a money maker in the best of circumstances, in the smaller cases the attorney fees often total a larger percentage of the total potential recovery. For this reason, the small cases are almost better suited for a quick mediated resolution than the larger ones. The larger cases may cost more to prosecute or defend, but the fees are less likely to eat up such a large percentage of any recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Making the World’s Longest Undersea Railway Tunnel Possible with BIM
December 11, 2018 —
Aarni Heiskanen - AEC BusinessFinland and Estonia are Baltic sea neighbors separated by the Gulf of Finland. Over eight million travelers and 1.2 million cars travel between Helsinki and Tallinn every year by boat. However, a consortium of companies is now planning to build the Finest railway tunnel between the two countries.
The vision of such a tunnel has been around since the 1990s. In June 2016, Peter Vesterbacka, previously known as the marketer behind Rovio’s Angry Birds, made the latest endeavor public in his AEC Hackathon presentation.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at