Subcontractor’s Claim against City Barred by City’s Compliance with Georgia Payment Bond Statute
March 29, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPIn a recent Georgia Court of Appeals case, the Court was tasked with determining whether the City of Atlanta’s compliance with the Georgia Payment Bond Statutes barred a subcontractor from recovery against it after the general contractor failed to pay and the surety became insolvent.
Squared Plumbing Co., LLC (J. Squared), was a subcontractor on a project to clean up sewage spills in approximately 100 dwellings for the City of Atlanta. As required by the contract executed with the City, the general contractor, Scott and Sons Holdings, LLC (Scott and Sons), obtained a $200,000 payment bond from its surety, First Seaford Surety, Inc. (First Seaford). J. Squared sought to collect on the payment bond when Scott and Sons failed to pay J. Squared for the work it performed on the project. However, First Seaford became insolvent. J. Squared subsequently filed a claim against Scott and Sons and the City to recover $140,000 for its work on the project.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Construction Litigation Roundup: “A Close Call?”
August 05, 2024 —
Daniel Lund III - LexologyNot really, said a Florida state appellate court when a public construction project owner sued a defaulted general contractor after recovering from the general contractor’s surety.
The general contractor, Close Construction, entered into a contract for a lift station rehabilitation construction project with the City of Riviera Beach in Florida. During the course of the work the public owner terminated the contract, whereupon the GC and the owner brought claims against each other in court. A jury ultimately held against the general contractor and in favor of the public owner in the amount of approximately $1.9 million. The general contractor appealed.
On appeal, the general contractor noted that the public works surety which it was required by the contract to obtain for the project had hired another company to complete the work when the general contractor was terminated and had otherwise “settled with the District under its bond for $1,000,000.” Based on that settlement, the general contractor had moved, unsuccessfully, in the trial court for a post-trial setoff because the “settlement covered the same damages that the jury assessed” against the GC, and because the surety was “jointly and severally liable” with the GC – pursuant to the terms of the bond – for those damages. In essence, the general contractor sought to avoid having the public owner “obtain a double recovery.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Four Dead After Crane Collapses at Google’s Seattle Campus
July 29, 2019 —
The Associated Press (Lisa Baumann & Nicholas K. Geranios) - BloombergSeattle (AP) -- Four people died and three were injured when a construction crane on the new Google Seattle campus collapsed Saturday, pinning six cars underneath.
One female and three males were dead by the time firefighters got to the scene, Fire Chief Harold Scoggins said. Two of the dead were ironworkers, not crane operators, as had been previously stated, and the two others were people who had been in cars, Seattle Mayor Jenny Durkan said Saturday night.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
"Your Work" Exclusion Bars Coverage
July 06, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the appellate court agreed there was property damage caused by an occurrence, the "your work" exclusion barred the insured contractor's claim. King's Cove Marina, LLC v. Lambert Commercial Construction. LLC, 2019 Minn. App. LEXIS 389 (Minn. Ct. App. Dec. 16, 2019).
King's Cover Marina sought to expand and remodel its main building. The marina hired Lambert to perform the remodeling project. Lambert hired Roehl Construction, Inc. as a subcontractor to install new concrete footings on the main level of the building and to provide concrete for the second-level mezzanine floor.
After completion, the marina sued Lambert for breach of contract and negligence. The marina alleged that the concrete floors on the first and second levels were not constructed in accordance with industry standards or with project plans and specifications, resulting in excessive movement and cracking of the new concrete floors. Lambert tendered its defense to its insurer, United Fire & Casualty Company. United Fire defended under a reservation of rights and later sued Lambert for declaratory judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York State Trial Court: Non-Cumulation Provision in Excess Policies Mandates “All Sums” Allocation
October 02, 2018 —
Paul Briganti - White & Williams LLPOn August 18, 2018, the New York Supreme Court, New York County, confirmed a referee’s finding that “all sums” allocation was required under excess policies issued by Midland Insurance Company because they included a non-cumulation provision. See Matter of Liquidation of Midland Ins. Co., Index No. 041294/1986 (N.Y. Sup. Ct. Aug. 18, 2018).
Midland was a multi-line carrier that wrote a substantial amount of excess coverage for Fortune 500 companies. In the 1980s, Midland faced significant exposure for environmental, asbestos and product liability claims. In 1986, it was placed in liquidation and the New York State Superintendent of Insurance (the Liquidator) was appointed as its receiver. Since then, the New York Supreme Court has presided over the liquidation proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White & Williams LLPMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Construction Companies Must Prepare for a Surge of Third-Party Contractors
February 08, 2021 —
Kim Holly - Construction ExecutiveEconomists agree that the trajectory of the current recession has been different from any other. Looking back at the 2008 economic crisis, there are noticeable trends in the construction space that indicate a surge in third-party contractor hiring could be coming in 2021.
The demand for more contract work will come as no surprise for seasoned construction executives—the share of contractors at U.S. businesses has increased by 15% in the last decade. Contractors are a valuable asset in the construction industry, but organizations will need to prepare for the coming influx to ensure third-party contractors and full-time employees are set up for success to keep operations running smoothly.
THE CONTRACTOR SURGE BLUEPRINT
Managing a substantial influx of contractors on construction worksites can be an overwhelming task. However, with guiding principles in place, construction executives can successfully incorporate more contractors into their operations and effectively manage associated risks.
Reprinted courtesy of
Kim Holly, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Flooded Courtroom May be Due to Construction Defect
September 01, 2011 —
CDJ STAFFThe General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.
The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Clauses That May or May Not Have Your Vote – Part 3
November 23, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The third in a multi-part series, here are some other important construction contract clauses that may determine whether you come out a winner.
Provision: Supervisory Personnel, Employees, and Authority to Bind Provisions
- Typical Provision: ”At all times during performance of the Work, Subcontractor shall have at the job site a competent supervisor approved by Owner. Subcontractor’s supervisor shall be deemed a representative of Subcontractor and all communications given to Subcontractor’s supervisor shall be as binding as if such communications were given to Subcontractor. Should Contractor object to Subcontractor’s supervisor’s presence at the job site, or the presence at the job site, or the presence at the job site of any other employee or agent of Subcontractor or any employee or agent of Subcontractor of Subcontractor, Subcontractor shall cause such persons to be replaced immediately as directed by Contractor.”
- What it Means: Higher-tiered parties have a legitimate interest in ensuring that only competent individuals are allowed to perform work on a project and in ensuring that there are peaceable relations at a job site. Higher-tiered parties also have an interest in ensuring that directives and agreements made and reached in the field are followed. However, it is unreasonable for higher-tiered party or to require that such personnel be able to bind that lower-tiered party to agreements best decided by others.
- What You Can Do: Lower-tiered parties should seek to include language which provides that only “reasonable” changes to personnel are allowed and, as necessary, limit by category or issue the types of items on-site personnel can bind the lower-tiered party to.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com