Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Cost of Overlooking Jury Fees
February 07, 2022 —
Nicholas B. Brummel, Arezoo Jamshidi & Lawrence S. Zucker II - Haight Brown & BonesteelOn January 21, 2022, the Court of Appeal, Second Appellate District, Division Two (Los Angeles), certified for publication a 2-1 decision that serves as an important reminder to California attorneys to post jury fees in a timely manner and to use appropriate channels and consult with appellate counsel in seeking appellate relief from contested rulings.
In TriCoast Builders, Inc. v. Nathaniel Fonnegra, (B303300, Jan. 21, 2022), a construction defect dispute, the trial court set a jury trial at defendant’s request. However, on the day trial was set, defendant waived jury trial. Plaintiff objected and made an oral request for jury trial. The trial court denied the request finding that plaintiff waived its right to a jury trial by failing to timely post jury fees. The matter proceeded to a bench trial, and the court ruled in favor of defendant. Plaintiff appealed, having failed to seek a writ of mandate, which the appellate court noted “is the proper remedy to secure a jury trial allegedly wrongfully withheld.”
Reprinted courtesy of
Nicholas B. Brummel, Haight Brown & Bonesteel,
Arezoo Jamshidi, Haight Brown & Bonesteel and
Lawrence S. Zucker II, Haight Brown & Bonesteel
Mr. Brummel may be contacted at nbrummel@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Discretion in Determining Prevailing Party for Purposes of Attorney’s Fees
January 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn prior articles I have discussed that courts apply the significant issues test to determine the prevailing party for purposes of being entitled to attorney’s fees. A party that recovers an affirmative judgement is NOT the de facto prevailing party for purposes of an entitlement to attorney’s fees in a breach of contract action (or a construction lien foreclosure action). This was the issue in a recent appeal discussed here where the party that recovered an affirmative judgment on a breach of contract case was not deemed the prevailing party for purposes of attorney’s fees. While the party prevailed on one of its claims, it did not prevail on others, and it recovered less than half of the damages it originally sought. The appellate court, affirming the trial court, held that the trial court has discretion to determine that the party that recovered an affirmative judgement was not the prevailing party entitled to its attorney’s fees under the signifiant issues test. This was not what the party was expecting when the attorney’s fees it expended far exceeded the judgment it recovered.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Render Unto Caesar: Considerations for Returning Withheld Sums
January 18, 2021 —
William E. Underwood Partner, Jones Walker LLP - ConsensusDocsWithholding sums during a dispute can be an effective and perfectly legitimate means to protect against the harms caused by another party’s breach. However, withholding too much money during a dispute can turn a position of strength into one of weakness.
“Why should I fund the other side’s litigation war chest?” and “Isn’t this just a display of weakness?” are common questions raised by contractors when this issue is discussed. Often, the contractor is well within its contractual or legal rights to withhold money from a breaching subcontractor (another topic for another day). But it may not always be in a contractor’s best interest to withhold every single penny available.
This article addresses some of the long-term implications for failing to return withheld sums, including the potential to recover attorneys’ fees, possible bad faith, accruing interest, and overall litigation costs. Admittedly, it can be hard to give money back in the middle of a dispute. But sometimes it can positively impact the overall outcome of the case.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLP (ConsensusDocs)Mr. Underwood may be contacted at
wunderwood@joneswalker.com
Fort Lauderdale Partner Secures Defense Verdict for Engineering Firm in High-Stakes Negligence Case
June 10, 2024 —
Lewis Brisbois NewsroomFort Lauderdale, Fla. (June 3, 2024) - Fort Lauderdale Managing Partner Cheryl Wilke recently secured a defense verdict for civil engineering firm Gulfstream Design Group and its owner, Matthew Lahti, in a high-stakes professional negligence case in which the plaintiff sought more than $20 million. The verdict by a six-person jury in St. Augustine followed a nine-day trial.
The case involved a 100-acre tract of land in St. Johns County, Florida, owned by the plaintiff, Cynthia Taylor. The land was zoned for rural farming, and she wished to sell the property for development. She entered into a contract with Southeast Georgia Acquisitions (“SGA”) to sell the property with the goal of creating a 200-home subdivision. SGA hired Doug Burnett as land use counsel and our client, Gulfstream Design Group, as the civil engineer to design the project.
In St. Johns County, only a property owner can submit a Planned Unit Development Plan (“PUD”) for the purpose of rezoning. In this case, Burnett and Gulfstream created text and a proposed map for the PUD and submitted it for approval. The PUD was approved first at the staff level, then by planning and zoning and then by the County Commission. All the services were provided prior to closing with PUD approval, a condition of sale.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Equities Favor Subrogating Insurer Over Subcontractor That Performed Defective Work
August 04, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Valley Crest Landscape v. Mission Pools (No. G049060, filed 6/26/15, ord. pub. 7/2/15), a California appeals court held that equities favor an insurer seeking equitable subrogation over a subcontractor that agreed to defend and indemnify claims arising out of its performance of work under the subcontract.
Valley Crest contracted to build a pool at the St. Regis Hotel in Dana Point. Valley Crest subcontracted with Mission Pools to perform the work. The master contract contained an indemnity clause in favor of St. Regis, and the subcontract contained an indemnity clause in favor of Valley Crest. An intoxicated guest who was rendered quadriplegic after diving in the shallow end of the pool sued the hotel, Valley Crest, Mission and others involved in the design, construction and operation of the pool. The suit included allegations that the pool depth was improperly marked; there was inadequate warning signage; and the pool finish caused the pool to appear deeper than it was. Valley Crest tendered its defense to Mission Pools under the subcontract’s indemnity agreement. When Mission did not respond, Valley crest filed a cross-complaint for indemnity. All parties ultimately reached a settlement with the injured plaintiff, leaving Valley Crest’s cross-complaint against Mission Pools.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Effective Allocation of Damages for Federal Contract Claims
October 25, 2021 —
Dirk D. Haire, Joseph L. Cohen & Jane Han - ConsensusDocsFederal construction contracts law generally recognizes four basic methods for pricing damages: (1) Actual Cost Method (ACM); (2) Total Cost Method (TCM); (3) Modified Total Cost Method (MTCM); and (4) Jury Verdict Recovery Method (JVRM). In practice, it is difficult to obtain significant recoveries on TCM and JVRM claims, and only marginally easier on MTCM claims. That is because the courts and boards that hear federal government contracts cases have developed a clear preference for the ACM. Despite this preference, many contractors do not have systems in place to maximize their opportunity to recover damages under the ACM. This article introduces various strategies for tracking and allocating damages during project performance in a manner that will support an ACM analysis if a federal construction claim is litigated.
Background: Four Basic Methods for Pricing Damages
The four methods for pricing damages are described, below:
1. Actual Cost Method
The actual cost method claims damages based on records of “actual costs” that were documented during the performance of the contract. All additional costs must be separately recorded from the costs incurred in the normal course of contract performance. Because contractors provide the court or board with documented underlying expenses under the actual cost method, courts and boards prefer this method. However, the actual cost method may not always be feasible where a contractor is confronted with drastic changes early and often in a project.
Reprinted courtesy of
Dirk D. Haire, Fox Rothschild LLP,
Joseph L. Cohen, Fox Rothschild LLP and
Jane Han, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Cohen may be contacted at jlcohen@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Stop - In the Name of the Law!”
August 07, 2023 —
Daniel Lund III - LexologyIn a 5-4 decision, the United States Supreme Court settled a split among the federal appellate circuits on whether appeal of a district court refusal to compel arbitration stays the underlying litigation in the district court.
Having been denied relief by the district court on its motion to compel arbitration, plaintiff filed an interlocutory appeal to the Ninth Circuit under the Federal Arbitration Act, 9 U. S. C. §16(a), which authorizes an interlocutory appeal from the denial of a motion to compel arbitration. Plaintiff asked the district court to stay its proceedings pending resolution of the interlocutory appeal. The district court refused, and the Ninth Circuit also declined to stay the lower court proceedings pending appeal.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com