Mixing Concrete, Like Baking a Cake, is Fraught with Problems When the Recipe is Not Followed
February 26, 2015 —
Garret Murai – California Construction Law Blog“Mixing concrete, like baking a cake, is fraught with problems when the recipe is not followed.” – Justice Kenneth Yegan, State Ready Mix, Inc. v. Moffatt & Nichol, California Court of Appeal for the Second District, Case No. B253421 (January 8, 2015).
I love jurists who aren’t afraid to mix in a little humour in their opinions.
But “[t]he law,” as a framed needlepoint in one of my colleague’s offices says, “is serious business.” And the State Ready Mix case involved one of the thorniest problems in construction litigation:
What to do when you’re sued and you think someone else is to blame.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
GE to Repay $87 Million for Scaled-Back Headquarters Plan
February 27, 2019 —
Rick Clough - BloombergGeneral Electric Co. will reimburse the state of Massachusetts for funds used to develop the manufacturer’s future headquarters, a project that is now being scaled back under Chief Executive Officer Larry Culp.
GE and the state will jointly sell the property in Boston’s Fort Point neighborhood where the company will make its future home, according to an agreement revealed Thursday. GE still plans to move into the campus later this year -- as a tenant rather than owner -- but it’s scrapping plans to build an adjacent 12-story tower.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Clough, Bloomberg
No Additional Insured Coverage for Subcontractor's Work Outside Policy Period
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between two insurers, the district court determined that the contractor was not an additional insured under the subcontractor's policy. Navigators Spec. Ins. Co. v. St. Paul Surplus Lines Ins. Co., 2015 U.S. Dist. LEXIS 79338 (N. D. Cal. June 17, 2015).
McDevitt & McDevitt Construction Corporation was the general contractor for construction of a condominium complex. McDevitt was insured by Navigators Specialty Insurance Company. F&M was a subcontractor for the project for providing structural steel components. F&M's subcontract required it to obtain liability insurance and name McDevitt as an additional insured under a policy that was to be primary. F&M secured a policy with North American Capacity Insurance Company (NAC) which included an endorsement for additional insureds. The endorsement provided that an entity could be an additional insured only with respect to "occurrences resulting from work performed by you during the policy period, or occurrences resulting from the conduct of your business during the policy period."
McDevitt and F&M were sued for construct defect claims. Navigators defended McDevitt and NAC defended F&M. Navigators tendered McDevitt's defense to NAC because McDevitt was an additional insured under NAC's policy. NAC disclaimed coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case
August 04, 2011 —
CDJ STAFFOn July 28, the Washington Court of Appeals ruled in Clasen Fruit & Cold Storage v. Frederick & Michael Construction Co., Inc. that more than six years had passed since a contractor had concluded work and so granted a summary dismissal of the suit.
Frederick & Michael Construction Co., Inc. (F&M) was contracted to construct several buildings for Clasen Fruit and Cold Storage. These were completed in March, 1999. The buildings suffered wind damage to the roofs in 2001, 2003, 2005, and 2006. In the first two incidents, F&M repaired the roofs with Clasen paying for repairs.
In 2005, Clasen hired Continuous Gutter to make repairs. The final incident was the collapse of the roof of one building. This was attributed to “excessive moisture in the roof’s vapor barriers.” At this point, Clasen demanded that F&M pay for repair and replacement costs. In 2008, Clasen sued F&M for damages for breach of contract and negligent design and construction of the roof.
The decision then covered the meanings, in Washington law, of “termination of services” and “substantial completion.” The panel concluded that construction was “substantially completed in 1997” and “relevant services” by 2001. “But Clasen did not sue until 2008, some seven years after termination of any roof related services.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Conn. Appellate Court Overturns Jury Verdict, Holding Plaintiff’s Sole Remedy for Injuries Arising From Open Manhole Was State’s Highway Defect Statute
June 14, 2021 —
Christy Jachimowski - Lewis BrisboisSection 13a-149 of the Connecticut General Statutes, commonly known as Connecticut’s highway defect statute, provides that claims arising from injuries or damages to people or property resulting from a defective road or bridge can be asserted against a party responsible for maintaining that road or bridge. Conn. Gen. Stat. §13a-149. The statute also extends to sidewalks and further provides that written notice of an alleged injury must be given to a defendant municipality within ninety days of the injury.
Recently, in Dobie v. City of New Haven, 2021 Conn. App. LEXIS 162 (App. Ct. May 1, 2021), the Connecticut Appellate Court overturned the trial court’s denial of a municipal defendant’s post-trial motion to dismiss. The court held that even though the plaintiff attempted to assert allegations of negligence against the defendant municipality, Connecticut’s highway defect statute was the plaintiff’s exclusive remedy. Since the plaintiff failed to meet the requisite notice requirements, pursuant to the statute, the Appellate Court held that the trial court erred in denying the municipality’s motion to dismiss for lack of subject matter jurisdiction.
The Underlying Case
In February of 2013, Plaintiff William Dobie filed suit against the City of New Haven alleging injuries and damages as a result of the negligence of a City of New Haven snowplow operator. Dobie’s claims arose from an incident that occurred on January 21, 2011, in which he was driving behind the City snowplow driver, who was in the process of plowing snow from a municipal street located in New Haven, Connecticut. As the defendant employee was operating his snowplow, he knocked off a manhole cover, causing Dobie’s vehicle to drive over the open manhole. Dobie claimed personal injuries as a result of his vehicle dropping into the open manhole, including injuries to his jaw.
Read the court decisionRead the full story...Reprinted courtesy of
Christy Jachimowski, Lewis BrisboisMs. Jachimowski may be contacted at
Christy.Jachimowski@lewisbrisbois.com
Uniwest Rides Again (or, Are Architects Subject to Va. Code Section 11-4.1?)
October 16, 2018 —
Christopher G. Hill - Construction Law MusingsIn 2010, the Virginia Supreme Court held in Uniwest Const., Inc. v. Amtech Elevator Servs., Inc., that Va. Code Sec. 11-4.1 renders completely void and unenforceable any indemnification provision in a construction contract between a contractor and subcontractor that seeks to indemnify the indemnified party from its own negligent acts. In short, the Virginia Supreme Court stated that such overly broad provisions violate Section 11-4.1.
A recent case out of the Eastern District of Virginia Federal District Court examined a provision in a contract between a designer/architect and a contractor or owner on a project. In Travelers Indem. Co. of Conn. v. Lessard Design Inc. the Court examined the application of Section 11-4.1 to the following provision of a design contract where Lessard, the indemnitor, agreed to:
[i]ndemnify, defend and hold the Owner, Owner’s Developer, and Owner’s and Owner’s Developer’s wholly owned affiliates and the agents, employees and officers of any of them harmless from and against any and all losses, liabilities, expenses, claims, fines and penalties, costs and expenses, including, but not limited to reasonable attorneys’ fees and court costs relating to the services performed by the Architect hereunder . . .
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Spending Highest Since April 2009
October 25, 2013 —
CDJ STAFFThe Commerce Department has announced that construction spending has increased by 0.6 percent, but that modest gain puts it at the highest it has been in four and a half years. The last time construction spending was this high was April 2009.
The rise in construction spending is due to increases in both public and private construction project. Public construction was up, despite a decrease in spending by the federal government. Private residential construction is at a five-year high.
Read the court decisionRead the full story...Reprinted courtesy of
Pay-if-Paid Clauses, Nasty, but Enforceable
March 12, 2015 —
Craig Martin – Construction Contractor AdvisorI am preparing for a presentation this week on Troublesome Contract Clauses to the Construction Specifications Institute (“CSI”), Nebraska Chapter. One of the clauses we will be discussing is the dreaded Pay-if-Paid clause, a particularly nasty provision that places the risk of owner’s solvency squarely on the subcontractor’s shoulders. While pay-if-paid clauses can create tremendous problems for subcontractors, they are enforceable.
Pay-if-Paid clauses eliminate the obligation to pay the subcontractor until the general contractor is paid by the owner. Pay-if-paid clauses usually contain something akin to the following phrases:
- payment to subcontractors are “expressly and unequivocally contingent upon receipt of payment from the Owner for the Subcontract Work.”
- the subcontractor “expressly acknowledges that it relies on payment under the Subcontract on the creditworthiness of Owner, not that of the General Contractor.”
- the owner’s acceptance of the work and payment to the General Contractor are “conditions precedent to any obligation of the General Contractor to pay the subcontractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at