Approaches in the Absence of a Differing Site Conditions Clause
April 10, 2019 —
Parker A. Lewton - Smith CurrieA contractor who has encountered unforeseen conditions will typically rely on the contract’s differing site conditions clause as a means to recovery. Most construction contracts address those issues directly. In ConsensusDocs Standard Agreement and General Conditions between Owner and Constructor, the starting point is § 3.16.2. But what if the contract does not contain a differing site conditions clause? Or, what if the contract does contain such a clause, but the contractor failed to provide adequate notice or satisfy other conditions or requirements of the contract? When reliance on a differing site conditions clause is impractical, a contractor still may seek recovery in certain instances under one or more of the following legal theories: misrepresentation; fraud; duty to disclose; breach of implied warranty; and mutual mistake.
Misrepresentation
Misrepresentation occurs when an owner “misleads a contractor by a negligently untrue representation of fact[.]” John Massman Contracting Co. v. United States, 23 Cl. Ct. 24, 31 (1991) (citing Morrison–Knudsen Co. v. United States, 170 Ct. Cl. 712, 718–19, 345 F.2d 535, 539 (1965)). A contractor may be able to recover extra costs incurred, under a theory of misrepresentation, if it can show that (1) the owner made an erroneous representation, (2) the erroneous representation went to a material fact, (3) the contractor honestly and reasonably relied on that representation, and (4) the contractor’s reliance on the erroneous representation was to the contractor’s detriment. See T. Brown Constructors, Inc. v. Pena, 132 F.3d 724, 728–29 (Fed. Cir. 1997). These four requirements can be satisfied, for example, through the use of deposition testimony detailing the owner’s representations and the contractor’s reliance thereon. See, e.g., C & H Commercial Contractors, Inc. v. United States, 35 Fed. Cl. 246, 256–57 (1996).
Read the court decisionRead the full story...Reprinted courtesy of
Parker A. Lewton, Smith CurrieMr. Parker may be contacted at
palewton@smithcurrie.com
Indemnity Clauses That Conflict with Oregon Indemnity Statute Can Remain Partially Valid and Enforceable
November 30, 2016 —
Masaki James Yamada – Ahlers & Cressman PLLCWhen the indemnity provision of a contract conflicts with ORS 30.140, it is voided to the extent that it conflicts with the statute, but no more. Such provisions can remain partially valid and enforceable.[i] In Montara Owner Assn., the owner brought claims against the contractor for construction defects and damage relating to the construction of 35 townhouses. Contractor then brought third-party claims against more than 20 subcontractors for breach of contract and indemnity. Before trial, contractor settled with all but one subcontractor. The subcontract contained an indemnity provision requiring subcontractor to indemnify contractor for losses arising out of subcontractor’s work, including losses caused in part by contractor’s own negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki James Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com
Can a Lease Force a Tenant's Insurer to Defend the Landlord?
October 10, 2022 —
Kerianne Kane Luckett - Saxe Doernberger & Vita, P.C.Can an indemnification clause in a commercial lease obligate a tenant’s insurer to defend a landlord? Recently, the United States District Court for the Northern District of New York said, “Yes!” On August 9, 2022, the district court issued a decision in ConMed Corp. vs. Federal Insurance Company, holding that the indemnification clause in a policyholder’s lease triggered the insurer’s duty to defend the landlord in an action arising out of the tenant’s negligence.
Facts of the Case
ConMed is a medical technology company that leases warehouse space in Georgia from Breit Industrial Canyon (“the Landlord”) to sterilize its medical equipment. ConMed’s employees filed suit against ConMed and a contractor that performed the sterilization, alleging injuries caused by exposure to excessive amounts of chemicals used in the sterilization process (the “ConMed Action”). Thereafter, ConMed’s employees filed a separate lawsuit against the Landlord, alleging that the Landlord permitted storage of unsafe levels of the chemicals at the warehouse without adequate ventilation (the “Landlord Action”). The lease agreement required ConMed to indemnify the Landlord “except in the event of, and to the extent of, Landlord’s negligence or willful misconduct.”
Read the court decisionRead the full story...Reprinted courtesy of
Kerianne Kane Luckett, Saxe Doernberger & Vita, P.C.Ms. Luckett may be contacted at
KKane@sdvlaw.com
Allegations That COVID-19 Was Physically Present and Altered Property are Sufficient to Sustain COVID-19 Business Interruption Suit
May 24, 2021 —
Michael S. Levine & Joseph T. Niczky - Hunton Insurance Recovery BlogOn Wednesday, a federal judge in Texas denied Factory Mutual’s Rule 12(c) motion for judgment on the pleadings, finding that the plaintiffs adequately alleged that the presence of COVID-19 on their property caused covered physical loss or damage in the case of Cinemark Holdings, Inc. v. Factory Mutual Insurance Co., No. 4:21-CV-00011 (E.D. Tex. May 5, 2021). This is the third COVID-19-related business interruption decision from Judge Amos Mazzant since March, but the first in favor of a policyholder. Taken together, the three decisions have two key takeaways and provide a roadmap for policyholders in all jurisdictions.
First, the Cinemark decision recognizes that the alleged presence of COVID-19 viral particles that physically altered the policyholder’s property is sufficient under federal pleading standards and controlling state law. In its motion, FM relied on Judge Mazzant’s recent decision in Selery Fulfillment, Inc. v. Colony Insurance Co., No. 4:20-CV-853, 2021 WL 963742 (E.D. Tex. Mar. 15, 2021), which dismissed a lawsuit alleging that the policyholder’s losses were caused by government orders that closed its business, rather than from the actual presence of the virus on its property. The Court held that government orders alone do not constitute physical loss or damage, and declined to rule on whether the physical presence of the virus does. Judge Mazzant reached the same conclusion weeks later in Aggie Investments, L.L.C. v. Continental Casualty Co., No. 4:21-CV-0013, 2021 WL 1550479 (E.D. Tex. Apr. 20, 2021).
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joseph T. Niczky, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Niczky may be contacted at jniczky@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Use of Dispute Review Boards in the Construction Process
December 27, 2021 —
Sarah B. Biser - ConsensusDocsDispute Review Boards: Overview
Problems, disagreements and claims arise in most large and complex construction projects regardless of the project delivery method. These disputes can and do delay and significantly increase the cost of the project. Dispute Review Boards, also known as Dispute Resolution Board, Dispute Board, Dispute Avoidance Board or DRB, are often found in large construction projects to assist the parties to minimize, resolve or avoid disputes and mitigate adverse impacts to projects. To date, over $270 billion worth of construction projects have used the dispute review board process to avoid numerous disputes and achieve significant savings.[1]
Unlike mediation and arbitration, a DRB is convened at the very beginning of the project and conducts regular meetings and visits at the project site throughout, allowing the DRB to discuss, observe and monitor construction, progress and potential disputes. At these meetings, DRB members become familiar with many of the facts and acquaint themselves with the job site personnel. If a dispute is submitted to them, the panelists have a great deal of knowledge about the circumstances of the problem to aid them in reaching their recommendations or conclusions. DRBs also encourage open and honest communications among or between the parties during the project, which in turn, encourages avoidance or resolution of disputes before they become formal claims. In short, the DRP process involves real-time discussion of the dispute with highly qualified people who know the particular project from day one and can provide recommendations on how to resolve disputes.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLPMs. Biser may be contacted at
sbiser@foxrothschild.com
Development in CBF Green Building Case in Maryland
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsRemember that case I discussed a while back relating to the Chesapeake Bay Foundation (CBF) building in Annapolis, Maryland? Remember how it was a lawsuit over parallams and failure of those parallams? Do you even remember what a parallam is?
Well, that case was initially dismissed upon the Defendant’s Motion for Summary Judgment because the trial court determined that CBF did not file its lawsuit within the proper time frame after notice of the potential failure of the building materials. Of course, CBF appealed to the Fourth Circuit Court of Appeals under the caption The Chesapeake Bay Foundation, Inc., et. al. v. Weyerhaeuser Company (4th Circuit).
After a great review of the facts of the case, the engineering inspections and reports at issue and the trial court’s ruling, the Fourth Circuit vacated the dismissal and remanded the case for further proceedings. The Court of Appeals reasoned that the district court jumped the gun in dismissing the lawsuit so early in the process because:
a genuine dispute exists as to whether knowledge of the water infiltration problem would have put a reasonable person on notice that the Parallams were susceptible to premature deterioration and that their PolyClear 2000 treatment would not preserve them.
In short, the court ruled that the engineering reports relating to moisture issues would have put CBF on notice of the particular issue of deterioration that was at issue in the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Tips for Drafting Construction Contracts
May 04, 2020 —
Stuart Rosen - Construction ExecutiveWhen negotiating a construction contract, a contractor and its advisers must first determine the areas of greatest concern.
For example, if the contractor believes that the drawings that were prepared by the architect and other design professionals are deficient, the contractor may want to reference those deficiencies in the contract. The contractor should emphasize that it is not responsible for the drawings and to the extent the project schedule is extended to allow the parties to address such issues with the drawings, the contractor would be entitled to additional compensation.
This article provides contractors with additional tips, with a broad focus on project delays, for their protection when negotiating and drafting construction contracts, and helps contractors understand the rationale for such tips to better prepare contractors in such negotiations.
Contractor’s liability to the owner for delay damages
It is imperative that the contract include a waiver of claims for consequential damages. AIA Document A201TM – 2017 includes such a waiver, which provides, in pertinent part, “The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract … This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14.”
Reprinted courtesy of
Stuart Rosen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rosen may be contacted at
srosen@proskauer.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com