Negligence Per Se Claim Based Upon Failure to Pay Benefits Fails
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit affirmed the district court's issuance of the insurer's motion for summary judgment, thereby rejecting the insureds' negligence per se claim for failure to pay benefits. Braun-Salinas v. Am Family Ins. Group, 2016 U.S. App. LEXIS 19555 (9th Cir. Oct. 28, 2016).
The insureds argued that Oregon recognized a negligence per se claim based on an insurer's failure to pay benefits in violation of the statutory standard under state law. Oregon appellate courts, however, only allowed a negligence per se claim only where a negligence claim otherwise existed. The Oregon courts had previously rejected a statutory theory, holding that a violation of the statute did not give rise to a tort action.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insured’s Bad Faith Insurance Claim Evaporates Before its Eyes
August 03, 2020 —
Garret Murai - California Construction Law BlogSometimes it’s right there before your eyes. Then, poof, it’s gone. This was the experience of one insured, who brought a bad faith insurance denial claim against his insurer thinking that the facts were in his favor, only to discover they were not.
The 501 E .51st Street Case
The Water Main Break and AGI’s Report
The owner of a 10-unit apartment building built in 1963, 501 East 51st Street, Long Beach-10 LLC (just rolls off the tongue doesn’t it?), filed a bad faith action against its insurer Kookmin Best Insurance Co., Ltd., after it denied 501 East’s insurance tender following a water main break that caused the building’s foundation to subside.
The water main break occurred sometimes between December 31, 2015 and January 2, 2016 next to the southwest side of the building. 501 East tendered its insurance claim to Kookmin on March 8, 2016, and in April 2016, presented a report prepared by American Geotechnical, Inc. (“AGI”) concerning damage to the building. According to the report prepared by AGI, AGI conducted a “limited geotechnical investigation” to “evaluate site conditions relating to the reported building distress following a waterline breach near the south end of the building.” The scope of AGI’s investigation was limited to “observation, photo documentation of the site conditions, [and[ floor-level survey of the interior of the first level units.” AGI’s investigation did not involve any subsurface investigation or soil testing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Nancy Conrad Recognized in Lehigh Valley Business 2024 Power in Law List
July 31, 2024 —
White and Williams LLPNancy Conrad, Chair of the Higher Education Group, Managing Partner of the Lehigh Valley Office and the President of the Pennsylvania Bar Association (PBA), has been named to the Lehigh Valley Business 2024 Power in Law List, for her work as a leader in the legal field.
This year’s honorees were asked to relate inspiration that pushed the pursuit of their career. One of her inspirations, as explained by Nancy in the article, was the opportunity to instruct and impact students while teaching during the day and pursuing a legal career in the evening at Temple Law which cemented a “commitment to excellence in the practice of law and service to the community.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Inspired by Filipino Design, an Apartment Building Looks Homeward
May 22, 2023 —
Sarah Holder - BloombergAusterity and efficiency aren’t the first words that come to mind when you see the angled sawtooth bays of Tahanan Supportive Housing, or catch a glimpse of a rainbow through its lobby. But the dramatic exterior and joyful interior of this San Francisco building are both products of their constraints.
When David Baker Architects was approached to design the six-story development, the goal was aggressive: Produce 145 units of permanent supportive housing at under $400,000 a unit, and have the operation up and running in less than three years. The firm accepted the challenge, and by 2022, Tanahan was fully leased to residents, all of whom are San Franciscans who have struggled with chronic homelessness.
In a city where affordable units typically cost $600,000 to $700,000 each to construct, keeping in budget and meeting the deadline meant turning to the modular building company Factory OS. It also meant keeping variation at a minimum. The studios are identical, like Lego blocks; instead of being mirrored across a hallway, they’re just rotated 180 degrees. But nothing else about the building feels utilitarian.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Holder, Bloomberg
Before Celebrating the Market Rebound, Builders Need to Read the Fine Print: New Changes in Construction Law Coming Out of the Recession
November 26, 2014 —
Alan H. Packer - Newmeyer & Dillion, LLPAs the homebuilding market continues to improve, many builders find themselves maneuvering familiar roads. That said, important new realities have taken hold since the market collapse. Navigating these changes requires extra thought for practical and legal reasons.
Using Old Designs “Off the Shelf”?
The adoption of the California Building Standards Code in 2010, with an updated schedule to go into effect January 1, may complicate the use of older designs. In addition, some builders are contemplating building on pads constructed five or more years ago, temporarily shelved until market conditions improved. Because of changes in both the applicable Code and due to possible changes in the underlying soils and drainage, these projects require additional scrutiny before starting construction.
Mechanic’s Lien Law Changes
Not too long ago, the California Legislature recently overhauled the entire mechanic’s lien law system in California. New forms, new statutory references, new rules and deadlines are all applicable to projects under construction now. Make sure your documents are up to date, as the use of older forms (particularly for liens, progress payments, and final payments) could create legal problems in the future.
Indemnity Law Changes
Since 2006, California lawmakers have passed four rounds of legislation aimed at limiting indemnity provisions in construction contracts. The laws are aimed at two aspects of indemnity law: “Type 1” indemnity provisions, and liability for the costs of defending a claim.
Type 1 Indemnity. California law previously permitted a builder to obtain “Type 1” indemnity from its subcontractors for all claims. Under a Type 1 provision, if a claim arose out of the trade’s work, the trade was fully responsible to defend and indemnify the builder – even if other trades or the Builder were partially at fault. Some cases even allowed, typically in a commercial context, the builder to obtain Type 1 indemnity even if the trade was not negligent, as long as the claim involved its work.
Defense Obligation. In 2008, California’s highest court issued an opinion in Crawford v. Weather Shield, evaluating an indemnity provision requiring trade (a window supplier/manufacturer) to defend the builder in claims involving allegations of damages arising out of the trade’s work. Because the trade had contractually agreed to defend the builder, the Court held it responsible for the builder’s defense costs -- even though, ultimately, the trade was found
not liable for the actual damages claimed.
Recent legislation after Crawford has dramatically shifted how indemnity provisions will be enforced. Builders may no longer obtain Type 1 indemnity for residential construction defect claims covered by SB800; instead, indemnity is limited to the extent a claim arises out of the trade’s work. Even more recent legislation applied these changes to claims arising out of commercial construction projects. The recent legislation allows the trades “options” on how to defend the builder, with an eye toward requiring that they pay only a “reasonably allocated” portion for the builder’s defense costs.
Smart builders are refining their contract documents to take into account these new limitations on indemnity provisions.
Insurance Market Changes
Due to uncertainties in subcontractor insurance and other factors, many builders have also converted their liability insurance from a “bring your own” model to “wrap-up” insurance, where the builder’s policy also covers their trades. Builders should carefully examine their subcontracts in light of this change as well.
Trade Partner Changes
On a practical level, many trade partners, particularly in the residential sector, have gone out of business or moved on to greener pastures. Builders need to find and negotiate contracts with new trade partners on the fly, and educate them on the builders’ procedures for payment and construction.
SB800 documentation
A decade ago, most builders updated their purchase documents and subcontracts for California’s “Right to Repair Law” (also known as SB800), which set forth functionality standards for construction defects in residential housing, and procedures for resolving claims prior to litigation. Builders ramping up to meet market demand should examine how they implemented SB800 changes in contract documents. Issues to consider:
- Whether to opt out of -- or back into -- statutory procedures.
- Whether to include arbitration or judicial reference provisions to control where claims are litigated after the SB800 process.
- Re-training personnel to preserve SB800 rights, including sign-offs on purchase documentation and recordation of key documents.
- Recent Court of Appeal decisions have complicated the SB800 landscape, potentially opening the door to “common law” tort claims in at least subrogation contexts. Strategic planning at the document stage may be a good way to mitigate this risk as the cases wind their way through the judicial process.
The continuing surge in building activity is a welcome sign for builders who have weathered the storm. Before taking too many steps, builders should consult with counsel, their designers, and their insurance advisors to take into account the new realities of this recovering housing market.
About the Author
Alan H. Packer is a partner in the expanding Walnut Creek, CA, office of the law firm of
Newmeyer & Dillion LLP whose specialties include real estate, insurance, and construction litigation. To reach Alan, call 925.988.3200 or email him at alan.packer@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Montana Significantly Revises Its Product Liability Laws
May 22, 2023 —
William L. Doerler - The Subrogation StrategistOn May 4, 2023, Montana changed its product liability laws when the Governor signed SB 216, which was effective upon passage and applies to claims that accrue on or after May 4, 2023. Among the changes is the adoption of a sealed container defense and the application of comparative negligence principles in strict liability actions. Montana also adopted a defense based on certain actions not being brought within 10 years. In addition, Montana adopted a rebuttable presumption with respect to a product’s defective condition. A jury must be informed about this rebuttable presumption with respect to certain warnings claims, premarket licensing procedures or claims involving drugs and/or medical devices. The changes to the Montana Code are further described below.
- In situations where there are multiple defendants, a defendant in a strict liability or breach of warranty action may now assert, as a defense, that the damages of the claimant were caused in full or in part by a person with whom the claimant has settled or released from liability. See MCA § 27-1-703(6)(a) (as revised). Comparative negligence or fault defenses are also available in actions against sellers, even where there are not multiple defendants. See MCA § 27-1-719(4)(e) (discussing a seller’s defenses in situations other than multiple defendant situations) (as revised).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Construction Litigation Roundup: “Stuck on You”
March 04, 2024 —
Daniel Lund III - LexologyA “contract of adhesion” is referred to as a standard form contract – usually preprinted – “prepared by a party of superior bargaining power for adherence or rejection of the weaker party.” Yet, it is not the nature of the contract alone which determines its enforceability, but, instead, “whether a party truly consented to all of the printed terms.”
A Louisiana plaintiff fighting a forum selection clause in a construction contract sought to have the clause nullified, urging that the clause was “buried” in the agreement and in small font, arguing also that the contractor had “superior bargaining position at the time of entering into the contract… because [plaintiff] needed to repair the hurricane damage” to his home as soon as possible.
In response, the contractor urged that the contract was not executed under rush conditions, and that, in any event, the contract was only two pages long – and the forum selection clause was not hidden and was in the same font as all of the other provisions in the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
The Almost-Collapse of a Sarasota, Florida Condo Building
July 11, 2021 —
Beverley BevenFlorez – CDJ StaffFive years ago, residents of the Dolphin Tower in Sarasota, Florida were forced to evacuate after cracks appeared in their fourth-floor condominium units.
“My assistant calls me and says, ‘[Kris] thinks the building is falling down,’” David Karins of Karins Engineering told Sarasota Magazine. “I said, ‘I doubt that.’ Then I got there and saw what was going on and I said, ‘You know, the building may be falling down.’”
In July of 2010, city officials ordered all residents to evacuate. Five years and $11 million dollars in rehabilitation and residents were finally able to move back in last month.
The Herald-Tribune had previously interviewed John Bonacci, an engineer at Sarasota’s Karins Engineering: “I’d say yes, there was grave danger. It was luck that it didn’t come all the way down. Getting shoring in there quickly was instrumental in preventing it from collapsing.”
Read the full story, Sarasota Magazine...
Read the full story, Herald-Tribune...
Read the court decisionRead the full story...Reprinted courtesy of