Providing “Labor” Under the Miller Act
January 28, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Northern District of California discusses the “labor” required to support a Miller Act payment bond claim on a federal construction project. It is a good case that discusses the type of labor required to support a Miller Act payment bond claim.
In Prime Mechanical Service, Inc. v. Federal Solutions Group, Inc., 2018 WL 619930 (N.D.Cal. 2018), a prime contractor was awarded a contract to design and install a new HVAC system. The prime contractor subcontracted the work to a mechanical contractor. The mechanical contractor with its sub-designer prepared and submitted a new HVAC design to the prime contractor and provided 4-5 onsite services to determine the location and layout for the new HVAC equipment, perform field measurements, obtain security passes, and plan site access and crane locations. The mechanical contractor submitted an invoice to the prime contractor and the invoice remained unpaid for more than 90 days, which the prime contractor refused to pay. The mechanical contractor than filed a Miller Act payment bond lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
When it Comes to Trials, it’s Like a Box of Chocolates. Sometimes You Get the Icky Cream Filled One
October 14, 2019 —
Garret Murai - California Construction Law BlogAccording to the California Judicial Council you have about a one in three chance your case will go to trial. In 2018, of the 210,028 unlimited civil cases that were filed (i.e., cases with an amount at issue of more than $25,000) only 33 percent made it all the way to trial. The odds are even less if you’re involved in a limited civil case (i.e., cases with an amount at issue of less than $25,000) where only 15 percent make it all the way to trial.
The reason: Lawyers are expensive. The other reason: Trials are risky. As well prepared as your counsel may be for trial, when it comes to trials, like boxes of chocolates, “Ya never know what you’re gonna get.” And sometimes you really, really don’t know what you’re going to get.
I had a client involved in a trial once. The defendant’s representative at trial was a well-to-do young man and heir to a hotel fortune. He was young, athletic and had a confident, carefree way about himself that reminded me of “Dickie” Greenleaf from the Talented Mr. Ripley. And I wasn’t the only one who noticed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Suffolk Pauses $1.5B Boston Tower Project for Safety Audit After Fire
April 22, 2024 —
James Leggate - Engineering News-RecordThe team building the $1.5-billion, 51-story South Station Tower in Boston voluntarily shut down the jobsite April 9 for a safety stand down and audit after a small fire broke out, according to contractor Suffolk Construction. No one was injured.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
No Prejudicial Error in Refusing to Give Jury Instruction on Predominant Cause
November 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's judgment after the jury determined there was no coverage for a leaking pipe. Mendoza v. Pacific Spec. Ins. Co., 2024 Cal. App. Unpub. EXIS 5477 (Cal. Ct. App. Aug. 20, 2024).
The Mendoza's third amended complaint alleged their home was damaged "by overflow of water from the dwelling's plumbing system resulting from a broken pipe, which overflow undermined the structural integrity of the dwelling."
The Mendozas insured their home under a policy issued by Pacific. The policy insured the property against "sudden and accidental direct physical loss" except where expressly excluded. The Mendozas submitted a claim Pacific paid approximately $1800 for the loss and closed the claim. The amount paid did not include payment for any structural damage to the home. The Mendozas alleged that Pacific's failure to conduct a full and fair investigation into the structural damage and its inadequate payment of benefits was a breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Are Modern Buildings Silently Killing Us?
May 16, 2022 —
Michael Rubino - Construction ExecutiveConstruction, in general, is a rapidly evolving industry as contractors, architects, and engineers are tasked with keeping up with government regulations, building practices and technological innovations. While growth and evolution are pivotal components of successful projects and businesses, it’s led to a few issues, one of which involves mold.
Like the construction industry, the world of mold is evolving as more research, understanding, and awareness develops, highlighting its prevalence in buildings and the effect it can have on the health of those exposed. What industry professionals are witnessing time and again is an increasing occurrence of individuals reaching out and asking for help after experiencing exposure that led to chronic illness. The reality is that modern buildings are contributing to this rise.
The Top of the Funnel
An issue aiding in mold’s prevalence in modern-day buildings is the way in which they are built. In an effort to achieve net-zero energy-efficient buildings, construction professionals have adopted the technique of sealing buildings as tightly as possible. While this transition reduces energy costs in the building, it also introduces a few new problems that aren't always addressed in modern construction. One such issue is how the lack of airflow between the indoor and outdoor environments can lead to a buildup of contaminant particles in the building.
Reprinted courtesy of
Michael Rubino, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion to Dismiss "Redundant Claims" Denied
June 21, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion to dismiss was more appropriate for an eventual summary judgment motion and was consequently denied. Sivan Lam v. Scottsdale Ins. Co., 2024 U.S. Dist. LEXIS 81262 (M.D. Fla. April 12, 2024).
Lam suffered a loss to her home due to Hurricane Ian. When only a portion of the claim was paid, Lam sued his insurer, Scottsdale, for breach of contract (Count I) and declaratory relief (Count II).
Scottsdale argued that Lam's request for declaratory relief was redundant of her breach of contract claim. The court noted that Rule 12 (b)(6), Fed. R. Civil P., was a vehicle to challenge a claim's sufficiency. Redundancy was not insufficiency, and it was not a ground for dismissal under Rule 12 (b)(6).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Peak of Hurricane Season Is Here: How to Manage Risks Before They Manage You
September 21, 2020 —
Vincent E. Morgan - Construction ExecutiveThe Atlantic hurricane season runs from June 1 to Nov. 30, but it peaks sharply during August, September and October. The latest forecasts predict this will be one of the most active seasons in history, in terms of frequency and severity, though it is always important to remember that even a single hurricane or tropical storm making landfall can still be a devastating event.
Hurricanes pose unique risks to the construction industry ranging from project and labor force disruptions to concerns about the availability and price of construction materials. This is even more true this year, which requires merging hurricane preparedness and response plans with the realities of COVID-19. Because hurricanes cannot be avoided, preparing for them is the only way to manage these risks. Ensuring the personal safety and wellbeing of affected individuals is the first priority. After that, here are some key issues, and suggestions for handling them, that may help guide construction companies through the storm.
SITE PROTECTION
Construction contracts often place responsibility for site protection on contractors. Where those duties exist, failing to properly carry them out can lead to enormous losses that then turn into liability claims. This could be anything from removing materials that can become projectiles, covering exposed ventilation shafts, and sealing electrical conduits to ensuring that key equipment such as generators and pumps can remain functional in a storm. One way to approach it is to imagine sustained 100-mph winds and relentless water, and then make sure preparedness efforts are likely to survive that kind of test. This is not the time for guessing. It is far better to go through a rigorous analytical process now than in a courtroom years later.
Reprinted courtesy of
Vincent E. Morgan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of