Court Throws Wet Blanket On Prime Contractor's Attorneys' Fees Request In Prompt Payment Case
September 03, 2015 —
Steven M. Cvitanovic & Abigail E. Lighthart – Haight Brown & Bonesteel LLPPrompt payment penalty cases do not come around very often, but when they do, there is bound to be fireworks.
In James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., et al. (No. C072169, filed 8/27/15), the California Court of Appeal for the Third Appellate District upheld the trial court's discretion to not award prevailing party attorneys' fees to the party who won a prompt payment dispute. California Business and Professions Code §7108.5 and Public Contract Code §§7107 and 10262 are the mechanisms for obtaining prompt payment relief in California. As shown by the outcome, it is possible to win and lose at the same time.
West Bay Builders, Inc. (“West Bay”) was the prime contractor on a school construction project for Stockton Unified School District. West Bay entered into a subcontract agreement with James L. Harris Painting & Decorating, Inc. (“Harris”) on the project. During construction there were disagreements between West Bay and Harris regarding the contractual scope of work, and Harris performed work it believed was outside the contract, believing it would be paid for the additional work. After West Bay refused to pay for the additional work, Harris left the project, and West Bay hired another subcontractor to complete the work.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Abigail E. Lighthart, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Begins Enforcement of its Respirable Crystalline Silica in Construction Standard. Try Saying That Five Times Real Fast
November 02, 2017 —
Garret Murai - California Construction Law BlogOn October 23, 2017, the U.S. Occupational Safety and Health Administration (OSHA) began enforcement of its Respirable Crystalline Silica in Construction Standard (Construction Silica Standard). OSHA enforcement of its Construction Silica Standard actually began on September 23, 2017, but for a period of 30 days, OSHA offered compliance assistance in lieu of enforcement for employers who were making good faith efforts to comply with the Construction Silica Standard.
California’s Occupational Safety and Health Administration (Cal/OSHA) has a nearly identical construction silica standard that requires employers to limit worker exposure to respirable crystalline silica above 25 micrograms per cubic meter of air (25 μg/m3) as an 8-hour time-weighted average (TWA) under any foreseeable condition.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
California Imposes New Disabled Access Obligations on Commercial Property Owners
October 07, 2016 —
Garret Murai – California Construction Law BlogThe following article was written by my colleague
David Goldman on the new ADA accessibility legislation which was signed into law this past month by Governor Brown.
Since July 1, 2013, California Civil Code section 1938 has required commercial property owners to disclose in every commercial lease whether the property being leased has been inspected by a Certified Access Specialist (“CASp”). A CASp is an individual certified by the State of California as qualified and knowledgeable of construction-related access to public accommodations by persons with disabilities. In addition to disclosing whether or not the property being leased has been CASp inspected, if a CASp inspection has occurred, the commercial lessor must disclose in the lease whether the premises has or has not met all the applicable construction-related accessibility standards established by law. These lease requirements, along with other disability access obligations, were discussed in an
earlier article written in 2012.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Marlena Ellis Makes The Lawyers of Color Hot List of 2022
January 17, 2023 —
Marlena Ellis - White and Williams LLPIn just her first year of practice, Marlena Ellis, Associate, is included in the Lawyers of Color Hot List of 2022.
Marlena joined the firm in 2021 as a full-time associate practicing both Commercial Litigation, Insurance Coverage, and Bad Faith Practice. She advises a variety of clients including corporations, commercial entities and insurance companies in complex disputes and breach of fiduciary duty matters.
The Lawyers of Color Hot List of 2022 honors junior and mid-level attorneys of color who exemplify integrity, leadership, and a passion for diversity in their roles. The selection committee spent months reviewing nominations to identify the right candidates for the list, and Marlena was one of the few chosen for this year.
Read the court decisionRead the full story...Reprinted courtesy of
Marlena Ellis, White and Williams LLPMs. Ellis may be contacted at
ellism@whiteandwilliams.com
Attorneys Fees Under California’s Prompt Payment Statutes. Contractor’s “Win” Fails the Sniff Test
October 02, 2015 —
Roger Hughes – California Construction Law BlogThis past month, the California Court of Appeals for the Third District, in James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., Case No. C072169 (August 27, 2015), handed down a decision in a construction contract battle that has raged since 2007. And, once again, the winner is . . . in the words of Justice Andrea Lynn Hoch who authored the opinion . . . . “no prevailing party in [the] case” and hence “no prevailing party attorney’s fees [ ] awarded.”
Background
In Harris, subcontractor James L. Harris Painting & Decorating, Inc. (“Harris”) sued general contractor West Bay Builders, Inc. (“West Bay”) for extra work performed on a school construction project in Stockton, California. Among its claims, Harris asserted that West Bay was liable under California’s prompt payment statutes for failure to timely pay Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
An Uncharted Frontier: Nevada First State to Prohibit Defense-Within-Limits Provisions
July 10, 2023 —
Geoffrey B. Fehling & Andrew S. Koelz - Hunton Insurance Recovery BlogNevada recently became the first state to prohibit defense-within-limits provisions in liability insurance policies. Defense-within-limits provisions—resulting in what’s called “eroding” or “wasting” policies—reduce the policy’s applicable limit of insurance by amounts the insurer pays to defend the policyholder against a claim or suit. These provisions are commonly included in errors and omissions (E&O), directors and officers (D&O) and other management liability policies. This is in contrast to other policies, most commonly commercial general liability policies, which provide defense “outside of limits” where defense costs do not reduce the policy’s limit.
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth and
Andrew S. Koelz, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Koelz may be contacted at akoelz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Mutual Or Concurrent Delay Caused By Subcontractors
March 23, 2020 —
David Adelstein - Florida Construction Legal UpdatesHow are delay damages treated when two subcontractors cause a mutual or concurrent delay to the project?
Assume multiple subcontractors concurrently contributed to an impact to the critical path resulting in a delay to the project. The delay caused the prime contractor to: (1) be assessed liquidated damages from the owner and (2) incur extended general conditions. The prime contractor will be looking to the subcontractors for reimbursement for any liquidated damages it is assessed along with its extended general conditions costs.
There is really no great case that addresses this point when two (or more) subcontractors mutually or concurrently delay the project. It is also not uncommon, and frankly expected, that a subcontractor will point the finger at another subcontractor for the cause of the delay or that another subcontractor was concurrently delaying the project.
The prime contractor should absolutely, without any exception, undertake efforts with a scheduling consultant to allocate the delay caused by subcontractors. Taking an approach that joint and several liability applies between multiple subcontractors and/or not trying to apportion delay because the subcontractors concurrently delayed the critical path at the same time is probably not the best approach. The prime contractor should have an expert render an opinion as to the allocation of the delay period amongst responsible subcontractors that delayed the critical path. Not doing so, in my opinion, is a mistake.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Thank Your Founding Fathers for Mechanic’s Liens
August 04, 2015 —
Craig Martin – Construction Contract AdvisorYep, our founding fathers, Thomas Jefferson and James Madison specifically, Craig Martin, Construction Attorney Lamson Dugan & Murray LLPwere responsible for proposing the first mechanic’s lien laws in the United States. Mechanic’s liens were not a new concept when the first law was passed in the United States; France, Spain and other countries already had them. But, in England, where landownership was limited to the upper classes, the concept of giving a tradesman an interest in the land for his labors was a truly foreign concept.
The Early Years—Pre Mechanic Lien
In the 1700s, there was no right to a mechanic’s lien. The possession of land was never deemed to be changed by its improvement and the laborer or material supplier was held to have acquired no right of lien in the property. The only remedy the laborer or material supplier had was to bring an action against the land owner. If the laborer or material supplier obtained a judgment, he would acquire the lien of a judgment creditor. A Treatise on the law of Mechanics’ Liens on Real and Person Property, 1893.
Read the court decisionRead the full story...Reprinted courtesy of