Exclusion Does Not Bar Coverage for Injury To Subcontractor's Employee
April 28, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Third Circuit reversed the district court and held that the additional insured was covered for injury to the subcontractor's employee despite an employee's exclusion in the policy. ArcelorMittal Plate, LLC v. Joule Technical Serv, Inc., 2014 U.S. App. LEXIS 2905 (3d Cir. Feb. 18, 2014).
ArcelorMittal Plate, LLC (AMP) owned a steel production facility. AMP contracted with Joule, an industrial staffing and engineering firm, for regular performance of maintenance and repair work at its plant. Joule was obligated to provide a CGL policy adding AMP as an additional insured "for all claims including, but not limited to, claims by Joule's employees."
Joule added AMP as an additional insured to its policy with Liberty Surplus Ins. Corp. The policy had an "employee exclusion" which stated, “This insurance does not apply to bodily injury to (1) an employee of the insured arising out of and in the course of (a) employment by the insured or (b) performing duties related to the conduct of the insured's business.”
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
TLSS Partner Burks Smith and Associate Katie Keller Win Summary Judgment on Late Reported Water Seepage Case in South Florida
November 18, 2019 —
Burks A. Smith, III & Kathryn Keller - Traub LiebermanOn July 9, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner, Burks A. Smith, III and Associate, Kathryn A. Keller, secured Summary Judgment on behalf of a major homeowners’ insurer in a breach of contract action in the United States District Court for the Southern District of Florida. See Lehrfield v. Liberty Mutual Fire Insurance Company, 2019 WL2994270 (S.D. Fla. 2019). The underlying claim involved a water loss at the Plaintiffs’ residence allegedly resulting in $91,147.32 worth of damage to their home. The claim was reported eight (8) months after the alleged date of loss, and during the inspection, the adjuster observed rot, decay, mold, and warping wood, prompting the carrier to deny the claim based on the Seepage Endorsement. The Plaintiffs filed a breach of contract action alleging that the insurer breached the Policy by denying the claim.
Mr. Smith and Ms. Keller argued that Plaintiffs’ Policy with the insurer imposes a duty on the Plaintiffs to comply with the Duties After Loss conditions of the Policy, including the requirement to provide prompt notice of the loss and show the damaged property. As mentioned above, the Plaintiffs provided notice of the claim eight (8) months late, and performed various repairs prior to notifying the insurer of the claim. After the close of discovery, Mr. Smith and Ms. Keller filed a Motion for Summary Judgment on behalf of the insurer based on the late reporting, and further argued that the Plaintiffs had the burden of proving direct physical loss to property within the first 13 days of the loss, given the recent decision of Hicks v. American Integrity Insurance Company of Florida, 241 So.3d 925 (Fla. 3d DCA 1018). In Florida, when an insured fails to comply with their Duties After Loss, a presumption of prejudice to the insurer arises. Bankers Ins. Co. v. Macias, 475 So. 2d 1216, 1218 (Fla. 1985)). In order to recover, the Plaintiffs bear the burden of overcoming the presumption, and must prove that no prejudice existed. Id. Mr. Smith and Ms. Keller’s comprehensive arguments successfully proved to the Court that the Plaintiffs’ failure to timely report the claim prejudiced the insurer by prohibiting the insurer from being able to independently validate the loss, or distinguish between multiple causes of loss. Mr. Smith and Ms. Keller further argued that Plaintiffs did not meet their burden to prove that the insurer was not prejudiced by the Plaintiffs’ failure to comply with the Duties After Loss provision of the Policy. The Motion cited numerous cases and extensive analysis supporting the insurer’s position.
Reprinted courtesy of
Burks A. Smith, III, Traub Lieberman and
Kathryn Keller, Traub Lieberman
Mr. Smith, may be contacted at bsmith@tlsslaw.com
Ms. Keller may be contacted at kkeller@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Meet Daniel Hall, Assistant Professor at TU Delft
January 17, 2023 —
Aarni Heiskanen - AEC BusinessWe sat down with
Daniel M. Hall, an assistant professor at
TU Delft, to discuss ways of achieving circularity in the built environment. Daniel will be a keynote speaker at WDBE in September 2023, where he’ll talk more about future circular cities.
Daniel is internationally known for his research on construction management and construction informatics. He did his Ph.D. at Stanford and worked for almost five years as an Assistant Professor of Innovative and Industrial Construction at ETH Zurich. In September 2022, he moved to the Netherlands.
The Delft University of Technology, Daniel’s new home base, strongly emphasizes the circular economy and circularity and has a long history of excellent teaching and research. It provides an inspiring environment for innovating the future.
Why we need to improve circularity in cities
“We cannot keep building the way we’ve been building. We don’t have enough resources; we don’t have enough materials,” Daniel asserts. “Obviously, we have questions around carbon impact. Around 40 percent of all CO2 emissions come from a combination of building operations and building materials.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Force Majeure and COVID-19 in Construction Contracts – What You Need to Know
April 06, 2020 —
Brenda Radmacher & Jason Suh - Gordon & Rees Construction Law Blog“Force Majeure” – While most construction contracts contain these provisions, they are often not understood in relation to the implications they may have on construction projects. With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts. The following is a brief primer on how to understand your construction contract and its potential implications on your business in this season of change.
What is a Force Majeure?
Construction contracts usually take into consideration that the parties want to agree at the outset on who bears the risk of unforeseen incidents that may affect the project’s progression. These issues are generally handled in a “force majeure” clause. Force majeure, according to Mariam Webster’s Dictionary is a “superior or irresistible force; or an event or effect that cannot be reasonably anticipated or controlled.” To be deemed a force majeure, generally the circumstances must be outside of a party’s control which makes performance impossible, inadvisable, commercially impractical, or illegal. In addition to being unforeseeable, the circumstances must have external causation, and be unavoidable. However, the key to understanding if COVID-19 will be deemed a condition that will excuse a contractor’s performance is the specific language in the provision.
Generally force majeure events are unavoidable events such as “acts of God,” most notably weather conditions including hurricanes, tornadoes, floods, earthquakes, landslides, and wildfires, as well as certain man-made events like riots, wars, terrorism, explosions, labor strikes, and scarcity of energy supplies. However, there is not much case law or specifics on conditions similar to COVID-19.
Reprinted courtesy of
Brenda Radmacher, Gordon & Rees and
Jason Suh, Gordon & Rees
Ms. Radmacher may be contacted at bradmacher@grsm.com
Mr. Suh may be contacted at jwsuh@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Points on Negotiating Construction Claims
December 30, 2013 —
CDJ STAFFEugene Heady of Smith Currie and Hancock offers some pointers on the effective negotiation of construction claims. He notes that “claims and disputes in the construction industry are commonplace,” but that “settlement usually comes after much pain, suffering, and expense.” He offers nine points to consider when negotiating construction claims.
His first two points are to develop a claim position and then document that claim. He says that “the facts underlying the claim should be nonnegotiable.” The documentation “suggests to your opponent that you have done your homework and are serious about the pursuit of your claim.” He also notes that you need to understand the strengths and weaknesses of your position.
On the other side, you need to “understand your opponent’s positions,” and also “your opponent’s strengths.” He points out that “an appreciation for what is truly important to your opponent is the starting point for the development of creative solutions to the dispute.
Further, bargaining should be done in good faith, negotiation should be done on the merits, and you are well advised to “choose a seasoned and skilful negotiator. “A prolonged and expensive legal battle is not likely to change the outcome,” he warns.
Read the court decisionRead the full story...Reprinted courtesy of
New York Restaurant and Bar Fire Caused by Electric Defect
February 04, 2014 —
Beverley BevenFlorez-CDJ STAFFA fire at McGill’s Restaurant and Bar located in Schuyler, New York, resulted in “a total loss” according to the Little Fall Times. Schuyler Fire Chief Don Kane told the Little Fall Times, “no one was inside the building at the time of the fire, as the bar had closed at 2:30 a.m.” and the fire was reported at 3:52 a.m. Weather hindered the firefighters abilities to deal with the situation as “a small squall moved through the area.”
An investigation concluded that an “electrical malfunction is to blame,” reported the Utica Observer-Dispatch. The Herkimer County Office of Emergency Services stated that the “fire was caused by an electrical defect within the base of the front wall.”
The restaurant owner, who leased the building, “did not carry fire loss insurance for his business,” though the “building owner was insured,” according to the Utica Observer-Dispatch.
Read the full story at The Little Falls Times...
Read the full story at The Utica Observer-Dispatch... Read the court decisionRead the full story...Reprinted courtesy of
Former NJ Army Base $2B Makeover is 'Buzzsaw' of Activity
June 14, 2021 —
Tom Stabile - Engineering News-RecordTake a developed property the size of New York City’s Central Park with 5 million sq ft of building area, program in new construction or renovation over 20 years and across three dozen parcels for 1,600 housing units, 300,000 sq ft of civic or government space, 500,000 sq ft for retail and 2 million sq ft of offices, and you have a pretty ambitious undertaking. The $2-billion effort to redevelop Fort Monmouth, a decommissioned former U.S. Army base in the thick of New Jersey’s suburban sprawl, is all kinds of ambitious.
Reprinted courtesy of
Tom Stabile, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Proving Contractor Licensure in California. The Tribe Has Spoken
October 21, 2015 —
Garret Murai – California Construction Law BlogAs I mentioned in an earlier post, in California you must “prove” you’re a licensed contractor in a construction case. But in whose hands are you entitled to place your fate – the judge or the jury?
Well, the tribe has spoken.
Jeff Tracy, Inc. v. City of Pico Rivera
In Jeff Tracy, Inc. v. City of Pico Rivera, Case Nos. B258563 and B258648, California Court of Appeals for the Second District (September 15, 2015), general contractor Jeff Tracy, Inc. doing business as Land Forms Construction (“Land Forms”) was walloped with a nearly $5.5 million judgment for being improperly licensed on a park project owned by the City of Pico Rivera (“City”). The judgment followed a bench trial over Land Form’s objection that it was entitled to a jury trial.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com