PSA: Pay If Paid Ban Goes into Effect on January 1, 2023
December 05, 2022 —
Christopher G. Hill - Construction Law MusingsI have
written a couple of times here at Musings regarding the new pay-if-paid legislation passed by the General Assembly last session. While the statute has some inconsistencies and a working group has made
some recommendations, the legislation as passed will go into effect on January 1, 2023, without any changes (at least until next session). As always, such action by our legislature here in Virginia will create work for construction attorneys assisting their clients to amend contracts to meet the new rules.
Essentially (and with minor inconsistencies between public and private contracts), the bill requires that any construction contract entered into after January 1, 2023 have the following provisions:
- On public projects: A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor’s payment with the reason for nonpayment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Pennsylvania Modular Home Builder Buys Maine Firm
December 11, 2013 —
CDJ STAFFExcel Homes, a modular home builder based in Liverpool, Pennsylvania, has bought Keiser Homes, a modular home builder based in Oxford Hills, Maine. Excel sought to increase their capacity, which acquisition of the Oxford Hills facility allows. Excel had previously shown an interest in the property of an Oxford Hills modular home builder that had closed, Oxford Homes, but a decrease in sales of modular homes lead Excel to reconsider the purchase.
Excel Homes plans on doubling the current output of the Oxford Hills facility and will be hiring additional employees. The purchase included all of Keiser’s machinery, trucks, trailers, equipment, and the customer list.
Read the court decisionRead the full story...Reprinted courtesy of
New York Assembly Reconsiders ‘Bad Faith’ Bill
May 17, 2021 —
Copernicus T. Gaza, Adam Krauss, Robert S. Nobel, Craig Rokuson & Eric D. Suben - Traub LiebermanThe New York State Assembly is considering A07285, which creates a private right of action for bad faith “if the insurer unreasonably refuses to pay or unreasonably delays payment without substantial justification.” The bill was first introduced in 2013 but was reintroduced on May 3, 2021 and has received some recent attention. According to the bill, an insurer acts unreasonably when it (among other things):
- Fails to provide the claimant with accurate information regarding policy provisions relating to the coverage at issue; or
- Fails to effectuate in good faith a prompt, fair, and equitable settlement of a claim or portion of a claim and where the insurer failed to reasonably accord at least equal or more favorable consideration to its insured's interests as it did to its own interests, and thereby exposed the insured to a judgment in excess of the policy limits or caused other damage to a claimant; or
- Fails to provide a timely written denial of a claimant's claim, or portion thereof, with a full and complete explanation of such denial, including references to specific policy provisions wherever possible; or
Reprinted courtesy of
Copernicus T. Gaza, Traub Lieberman,
Adam Krauss, Traub Lieberman,
Robert S. Nobel, Traub Lieberman,
Craig Rokuson, Traub Lieberman and
Eric D. Suben, Traub Lieberman
Mr. Gaza may be contacted at cgaza@tlsslaw.com
Mr. Krauss may be contacted at akrauss@tlsslaw.com
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Mr Suben may be contacted at esuben@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Basics: No Damages for Delay
May 06, 2024 —
Christopher G. Hill - Construction Law MusingsAfter WAY too long a hiatus, I am back with another in my series of “Construction Contract Basics” posts. In past posts, I’ve covered venue provisions, attorney fee provisions, and indemnity clauses. In this post, I’ll share a few thoughts (or “musings”) on the topic of so-called “no damages for delay” clauses. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the owner or general contractor, is an extension of time to complete the work.
These types of clauses generally make it impossible for a subcontractor (if found in a Subcontract) or Contractor (if found in a Prime Contract) that is delayed through no fault of its own to recover any damages relating to the expenses that are inevitably caused by such delays. Such expenses/damages could include additional supervisory time (including more high-dollar superintendent payments), acceleration costs, demobilization/mobilization costs, and other related expenses. These can add up to real money. Couple that with the inevitable liquidated damages or delay damages that will occur should a contractor or subcontractor cause any delay, and this becomes a very one-sided proposition.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Lis Pendens – Recordation and Dissolution
July 28, 2016 —
David Adelstein – Florida Construction Legal UpdatesWhen you file a construction lien foreclosure lawsuit, you must also record a lis pendens in the official (public) records against the property. This lis pendens serves as written notice that there is a lawsuit concerning the real property, and more specifically, title relating to that real property. If the property is then sold or rented, the buyer or tenant will ultimately be bound by a final determination relating to the lawsuit concerning title to the property. This is the value in recording a lis pendens and why it is a MUST in any foreclosure lawsuit. (This is the same value in any mortgage foreclosure lawsuit and why lis pendens are recorded in these lawsuits too.) A lis pendens will show up in a title report. In most instances, title companies will not issue a title policy if there is a lis pendens or may require a certain amount of money escrowed as a result of the lis pendens and pending action in order to issue a title policy. Also, a buyer, in particular, and a tenant are not going to want to invest in property where the title to that property is at-issue in a lawsuit. Hence, the lis pendens impacts the sale and potential re-financing of the property.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
When Do Hard-Nosed Negotiations Become Coercion? Or, When Should You Feel Unlucky?
October 21, 2019 —
Stan Millan, Jones Walker, LLP - ConsensusDocsConflict in a negotiation is to be expected and is arguably healthy for the process. Owners and contractors are constantly engaged in negotiations; whether it be negotiating changes to the work, changes to the schedule, or changes to the contractual terms. But at what point does taking a strong position in a negotiation cross the line and become coercion or bad faith?
A recent decision from the Armed Services Board of Contract Appeals touched on this very issue. While this is a government contract case, the issues discussed in this case (namely negotiating a change) are routinely encountered in just about every construction project. This decision is instructive because it adds to a trending line of cases that limit an owner’s and contractor’s negotiation tactics.
On August 5, 2019, the board issued an opinion in the appeal of Sand Point Services, LLC vs. NASA, ASBCA Nos. 6189. In Sand Point Services, the contractor was hired by the owner to repair the Wallops Flight Facility’s aircraft parking apron. During its work, the contractor hit a differing site condition, namely unsuitable soils. The contractor sought additional time and money for this differing site condition. The owner ultimately responded with a show cause letter to the contractor claiming, among other breaches, that the contractor was significantly behind schedule. This was generally viewed by all parties as the start of default proceedings against the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Stan Millan, Jones Walker, LLPMr. Millan may be contacted at
smillan@joneswalker.com
HHMR Lawyers Recognized by Best Lawyers
December 27, 2021 —
David M. McLain – Colorado Construction LitigationFor over twenty years, Higgins, Hopkins, McLain & Roswell has embodied and exemplified the principles of service and stewardship. In everything we do, we focus on serving our clients selflessly and to the best of our ability. In doing so, we always have in the forefront of our minds our obligation to act as the stewards of our clients’ trust, confidences, and resources. The firm itself, along with Carin Ramirez (in the area of Litigation - Insurance), and Dave McLain (in the area of Construction) were all recognized in this year's edition of the U.S. News Best Lawyers Journal. We could not be more proud of the firm we have created, or the service we are able to provide to Colorado's construction industry and its insurers.
Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell
Mr. McLain may be contacted at mclain@hhmrlaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Default Should Never Be An Option
June 19, 2023 —
Christopher G. Hill - Construction Law MusingsEvery time I think that the construction industry has learned that failure to respond to a lawsuit is never the correct response, another case of default judgment comes out. I’ve discussed on multiple occasions that failure to respond can only lead to disaster. Aside from being barred from making any substantive response to the allegations against you, there are other consequences including the inability to seek a reasonable settlement because the other side has no reason to negotiate.
One of the more disastrous results recently came about in the Norfolk Division of the Eastern District of Virginia District Court. The case of L & W Supply Corp v. Driven Construction et. al. involved a supplier that sought to enforce its credit agreement against both the corporate entity of the contractor, Driven, and the guarantor, a principal of the company. Needless to say, there was no response to the lawsuit and the Plaintiff filed for default judgment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at