No Signature, No Problem: Texas Court Holds Contractual Subrogation Waiver Still Enforceable
April 10, 2023 —
Gus Sara - The Subrogation StrategistIn Chubb Lloyds Inc. Co. of Tex. v. Buster & Cogdell Builders, LLC, No. 01-21-00503-CV, 2023 Tex. App. LEXIS 676, the Court of Appeals of Texas, First District (Court of Appeals) considered whether the lower court properly dismissed the plaintiff’s subrogation case by enforcing a subrogation waiver in a construction contract which was not fully executed. The contract was signed by only one of the two subrogors and was not signed by the defendant general contractor. The Court of Appeals affirmed the trial court’s decision, holding that despite the lack of signatures, the evidence established mutual assent to the contractual terms by all parties.
The plaintiff’s subrogors, Jeffrey and Mary Meyer (collectively, the Meyers), retained defendant Buster & Codgell Builders (BCB) to expand their residence. BCB drafted a contract using the American Institute of Architects (AIA) standard form contract for residential construction. The AIA contract included, by reference, a subrogation waiver that applied to BCB and its subcontractors. Prior to beginning the work, BCB emailed Jeffrey Meyer a version of the contract that only had one signature block for both Jeffrey and Mary Meyer. Minutes later, BCB sent a second version of the contract which had a signature line for each of the Meyers. However, Jeffrey Meyer signed the first version of the contract and emailed it back to BCB. In the subject line of his email, Mr. Meyers asked that BCB countersign and return the contract. BCB did not sign and return the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Wildfire Insurance Coverage Series, Part 2: Coverage for Smoke-Related Damages
July 03, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogFor many policyholders, smoke emanating from wildfire causes as much if not more damage than the fire itself. In this post in the Blog’s Wildfire Insurance Coverage Series, we discuss damages caused by smoke emanating from wildfires.
Some insurers argue that policies are limited to fire damage to the insured property and do not include smoke damage associated with nearby fires. A treatise frequently cited by insurers states otherwise: “The concept that fire insurance covers non-fire damage which is the proximate result of fire finds application also when the fire occurs on other property and causes harm to the insured property. In such case, the harm to the insured property, even though it is a non-fire harm, has long been recognized to be the result of fire, and, therefore, within the policy coverage.”
[1]
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
AAA Revises Construction Industry Arbitration Rules and Mediation Procedures
July 22, 2024 —
Patrick McKnight - The Dispute ResolverThe American Arbitration Association (AAA) recently revised its Construction Industry Arbitration Rules and Mediation Procedures (“the Rules”). Several notable changes went into effect March 1, 2024, involving the scope of confidentiality, regular and fast track procedures, and updates to certain monetary thresholds.
I. Revisions to Regular Track Procedures
Rule 45: Confidentiality
For the first time, confidentiality is now the default standard. Under Rule 45(a), arbitrators must keep all matters confidential unless otherwise required by law, court order or the agreement of the parties. Rule 45(b) allows a mediator to issue confidentiality orders and “take measures for protecting trade secrets and confidential information.”
Rule 7: Consolidation and Joinder
Under the new provisions, consolidation and joinder requests must be filed before confirmation of the Merits Arbitrator’s appointment. This language eliminates a previous option that allowed confirmation up to 90 days after filing of such requests. A failure to timely respond to a joinder request will result in a waiver of objections. Now, a party must establish both good cause and prejudice for a successful joinder request after confirmation of the arbitrator.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Gehry-Designed Project Seen Bringing NYC Vibe to L.A.
April 28, 2014 —
Nadja Brandt and John Gittelsohn – BloombergBillionaire Stephen Ross’s Related Cos. new project in the sleepy end of downtown Los Angeles is designed to invigorate Grand Avenue the way its Time Warner Center helped energize New York’s Columbus Circle.
“The notion of bringing together this diverse mix of uses, and allowing for a lot of public spaces and public events, has proven to be very powerful in the right locations and with the right planning.” said William Witte, president of Related’s California division.
The New York-based firm formed a joint venture with Los Angeles-based SBE Entertainment Group LLC to restart plans for a $650 million-to-$700 million complex with entertainment, shopping, apartments, condominiums and a luxury hotel, Witte said. After going back and forth with local officials for most of the past year, Related won approval in January for the Frank Gehry-designed project from Los Angeles County supervisors.
Ms. Brandt may be contacted at nbrandt@bloomberg.net; Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt and John Gittelsohn, Bloomberg
Lockton Expands Construction and Design Team
July 19, 2011 —
CDJ STAFFLockton Companies, LLC, the largest privately held independent insurance broker, has announced that it is expanding its construction and design team with the hiring of Karen Erger and Tom Miller.
Ms. Erger will provide professional liability practice management, loss prevention, contract and complex claims management consulting services to Lockton's architectural, engineering and construction clients in her role as Vice President, Director of Practice Management. Her background includes construction litigation at a leading construction law firm, professional liability claims defense and claims consulting for major professional liability underwriters.
Miller joins Lockton as a Senior Vice President within the Design and Construction Unit. His role will be dedicated to serving the needs of engineering, architecture and construction firms performing services around the globe. He has spent more than 15 years concentrating on professional liability for design professionals and contractors in multiple roles. He previously managed the professional liability underwriting of one of the largest construction insurers and has developed numerous manuscript insurance products as well as focused on strategic planning to enhance business unit opportunities.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
A Primer on Suspension and Debarment for Federal Construction Projects
August 10, 2020 —
Hal J. Perloff - Construction ExecutiveWe’ve all heard the expression that those who deal with the government must turn square corners. This is because the government has a broad array of tools at its disposal to motivate, coax and cajole contractors and federal grant recipients to play by the rules. Those tools include harsh measures such as criminal prosecution and civil false claims act enforcement on the one hand and poor CPARS ratings on the other. A seemingly less severe administrative option available to the government is suspension and debarment. However, any entity that has been suspended or debarred knows that these measures can prove harsh and disruptive.
While the numbers of suspensions and debarments have declined from the all-time high in 2011, there is still significant activity. In its FY 2018 report, the Interagency Suspension and Debarment Committee reported 2444 referrals, 480 suspensions, 1542 proposed debarments and 1334 debarments. The number of referrals for suspension and debarment in FY 2018 is almost exactly the same as the number of GAO bid protests filed that year.
WHAT IS SUSPENSION AND DEBARMENT?
Suspension and debarment are the government’s tools to avoid entities it views as a high risk for poor performance, fraud, waste and abuse. Suspension and debarment preclude a business entity or individual from contracting with the government or from receiving grants, loans, loan guarantees or other forms of assistance from the government. A suspension is a temporary exclusion when the government determines immediate action is necessary pending the completion of an investigation or legal proceeding. A debarment is an exclusion for a defined, reasonable period of time—often three years.
Reprinted courtesy of
Hal J. Perloff, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Perloff may be contacted at
hal.perloff@huschblackwell.com
Court Calls Lease-Leaseback Project What it is: A Design-Bid-Build Project
August 19, 2015 —
Garret Murai – California Construction Law BlogFirst there was “Prince.”
Then there was “The Artist Formerly Known as Prince.”
Then there was “The Artist Formerly Known as Prince (Because he Changed His Name to a Symbol), But Then Realized That No One Could Pronounce the Symbol (and What Good is a Symbol if Everyone Has to Wave Their Hands Wildly at You to Get Your Attention or Scream ‘Hey You!’), and So Changed His Name Back to Prince Again.”
Whatever name (or symbol) he was going by, everyone knew him as the guy who told us to party like it was 1999 (when 1999 still seemed like the distant future), who sang about a girl with a “pocket full of horses” (which totally flew past my junior high school brain at the time), and gave us such great metaphors as “if the elevator tries to bring you down, go crazy, punch a higher floor!”
Like Prince or his symbol, sometimes it doesn’t matter what label you put on something when everyone knows what that something is. In law, we call it looking at the “substance” rather than its “form.” And, in the next case, Davis v. Fresno Unified School District, the California Court of Appeals for the Fifth District made quick work of a purported “lease-leaseback” project – a project delivery method available to school districts whereby a school district leases property it owns to a developer for a minimum of $1, who in turns builds a school facility on the site and leases the facility and the site back to the school district, who in turn takes ownership of the facility and site at the end of the lease – and called it for what it was: a run-of-the-mill “design-bid-build” project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
#5 CDJ Topic: David Belasco v. Gary Loren Wells et al. (2015) B254525
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFChapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto, and
David A. Napper analyzed the above mentioned Belasco case, in which “the Second District Court of Appeal made clear that settlement agreements containing waviers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld.” Glucksman, et al. explained that “the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.”
Read the full story...
In another article on the subject,
Edward A. Jaeger, Jr. and
William L. Doerler of
White and Williams LLP concluded, “The Court of Appeal’s holding establishes that, despite the prohibition against the release of unknown claims set forth in section 1524 and the protections provided to homeowners by the Right to Repair Act, California homeowners can, in fact, release or waive claims against homebuilders for future, latent construction defects. To release or waive such claims, the language of any settlement agreement should be unequivocal.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of