You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Sustainability Puts Down Roots in Real Estate
January 27, 2020 —
Stephanie Amaru - Gravel2Gavel Construction & Real Estate Law BlogSustainability has evolved from a passing trend or niche preference into an undeniable, growing driver of the real estate market. This is particularly true as millennials comprise an increasing proportion of the workforce, home-buying population, and individuals influencing the future of real estate development in the United States.
If anything illustrates the significance of younger generations’ increasing interest in sustainability, it is the Global Climate Strike that drew participation of many thousands of young people, with 2,500 events scheduled in over 150 countries. In New York City, 1.1 million public school students were excused from school to join the strike in an event planned to precede the UN Summit, which itself was intended to push countries toward a commitment to faster transition to renewable energy and stricter climate targets. While both policymakers and citizens of previous generations have been split on their willingness to address global climate change with urgency, younger generations are feeling a stronger sense of responsibility for curbing the world’s trajectory towards a climate catastrophe, which will be inherited by them and their children. This has manifested in action that promotes awareness of and political action with respect to these issues—such as the Global Climate Strike—as well as evolving habits and preferences in both consumer goods and real estate.
Greener Space
In recent years, real estate developers have recognized that there is a market for “greener” developments that reduce annual expenditures on buildings, whether it be through small spaces requiring less electricity and promoting energy efficiency, or through renewable energy options such as solar photovoltaic power. Some real estate developers have chosen to install these options themselves, while others seek out sustainable financing options to cover the costs of renewable energy. If installing renewable energy is too costly, real estate developers will seek out more cost-effective locations for their brick-and-mortar operations.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Amaru, PillsburyMs. Amaru may be contacted at
stephanie.amaru@pillsburylaw.com
Suffolk Pauses $1.5B Boston Tower Project for Safety Audit After Fire
April 22, 2024 —
James Leggate - Engineering News-RecordThe team building the $1.5-billion, 51-story South Station Tower in Boston voluntarily shut down the jobsite April 9 for a safety stand down and audit after a small fire broke out, according to contractor Suffolk Construction. No one was injured.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Airbnb Declares End to Party!
January 27, 2020 —
Patrick J. Paul - Snell & Wilmer Real Estate Litigation BlogAs municipalities around the country evaluate changes to their respective codes in an effort to exert greater control over bad actors in the vacation rental market, Airbnb announced on November 2nd that it is banning party houses. The move comes in response to the shooting deaths of five people at a Halloween party hosted at an Airbnb rental house in Orinda, CA. CEO Brian Chesky announced on Twitter that starting November 2, Airbnb would ban “party houses” and redouble the company’s efforts to “combat unauthorized parties and get rid of abusive host and guest conduct.” twitter.com/bchesky
The four-bedroom rental reportedly had been rented on Airbnb by a woman who advised the owner her family members had asthma and needed to escape smoke from a wildfire burning in Sonoma County about 60 miles north of Orinda earlier in the week. Nevertheless, the homeowner was suspicious of a one-night rental on Halloween and reminded the renter that no parties were allowed. Having received complaints from neighbors and witnessing some party activity via his camera doorbell, the homeowner called police who were en route to the home, but arrived after the shooting. The Halloween party apparently was advertised on social media as an “Airbnb Mansion Party,” with an admission fee of $10 per person.
Independently owned vacation rentals are currently growing at a faster rate than hotels or motels, and in some instances are owned by out-of-state investors seeking not only a real estate return on investment, but also a return on investment associated with revenue streams generated by “pay to play” parties promoted on social media.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Paul, Snell & WilmerMr. Paul may be contacted at
ppaul@swlaw.com
Is The Enforceability Of A No-Damage-For-Delay Provision Inappropriate For Summary Judgment
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIs the enforceability of a no-damage-for-delay provision inappropriate for resolution on a summary judgment? The recent decision in U.S. f/u/b/o Kingston Environmental Services, Inc. v. David Boland, Inc., 2019 WL 6178676 (D. Hawaii 2019), dealing with Florida law, suggests that it is inappropriate for a summary judgment resolution, particularly when there is a right to a jury trial.
In this case, a prime contractor was hired on a federal construction project in Hawaii. The prime contractor hired a subcontractor and the subcontractor sued the prime contractor and its surety under the Miller Act. Of interest, the subcontractor was seeking to recover for the costs it incurred due to construction delays. The prime contractor moved for summary judgment as to the no-damage-for-delay provision in the subcontract. The no-damages-for-delay provision read as follows (and it is a well-written no-damage-for-delay provision):
The Subcontractor expressly agrees that the Contractor shall not be liable to the Subcontractor for any damages or additional costs, whether foreseeable or unforeseeable, resulting in whole or in part from a delay, hindrance, suspension, or acceleration of the commencement or execution of the Work, caused in whole or in part by the acts or omissions, whether negligent or not, of the Contractor including other subcontractors or material suppliers to the Project, its agents, employees, or third parties acting on behalf of the Contractor. The Subcontractor’s sole remedy for any such delay, hindrance, suspension, or acceleration shall be a noncompensable time extension.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Virginia General Assembly Helps Construction Contractors
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsAs reported last week at the Virginia Real Estate, Land Use and Construction Law Blog (authored by my good friend Tim Hughes (@timrhughes)), the Virginia General Assembly has passed an amendment to the jurisdictional limitations of Virginia General District Courts. The new statute, going into effect July 1, 2011, increases the jurisdiction of these courts to $25,000 from the present level of $15,000.
Why is this a big deal? As a solo practitioner who represents contractors and subcontractors in cases big and small, this increase is a boon to my practice and the collect-ability of some debts. I think back to the numerous conversations I have had with clients who had bona fide claims for around $20,000. These conversations inevitably turned toward the cost of Circuit Court versus General District Court and whether it would be better to leave money out of the claim to avoid the ramped up attorney fee and filing costs (not to mention the time from filing to judgment). This conversation was especially relevant in the instance where the contracts did not contain an attorney fees provision.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
N.J. Governor Signs Bill Expanding P3s
September 04, 2018 —
Nick Steingart - Construction ExecutiveGovernment entities in New Jersey that enter into public-private partnerships to help finance public construction projects are now required to utilize a project labor agreement (PLA) and pay state prevailing wages, among other requirements. Previously, P3s were only available to state and county colleges, but did not contain prevailing wage or PLA mandates.
The new law, Senate Bill 865, allows the state and its subdivisions, including counties, municipalities and school districts, to enter into agreements with private funding sources provided they follow the additional mandates such as abiding by the state’s prevailing wage law and utilizing a union-only PLA for construction of the project.
Reprinted courtesy of
Nick Steingart, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Steingart may be contacted at
steingart@abc.org
The Dog Ate My Exclusion! – Georgia Federal Court: No Reformation to Add Pollution Exclusion
September 28, 2017 —
Philip M. Brown-Wilusz - Saxe Doernberger & Vita, P.C.While schoolchildren know that the classic “the dog ate my homework” excuse doesn’t work, insurance companies are willing to try a variation of that excuse. Ace American Insurance Company (Ace), sold a property policy (the Policy) to Exide Technologies, Inc. (Exide). Exide sought coverage under the Policy for acid damage at its former battery factory. Ace denied coverage, citing to the pollution exclusion. The only problem? The Policy contained no pollution exclusion!
Exide had procured policies from other insurers for several years prior to the inception of the Policy, all of which contained pollution exclusions. Exide instructed Marsh USA Inc. (Marsh), its broker, to procure insurance “on the same or better terms and conditions.” The resulting policy contained no pollution exclusion, and Exide sought coverage under the Policy for pollution-related losses.
Read the court decisionRead the full story...Reprinted courtesy of
Philip M. Brown-Wilusz, Saxe Doernberger & Vita, P.C.Mr. Brown-Wilusz may be contacted at