The Future of Construction Defects in Utah Unclear
December 11, 2013 —
CDJ STAFFIn recent years, more courts have started to view construction defects as accidents, covered under insurance policies. In a post on the Parr Brown Gee & Loveless web site, Jeffrey D. Stevens writes that “the number of courts siding with insurance companies to deny contractors and subcontractors insurance coverage in construction defect lawsuits has been shrinking.” Recently, the Supreme Court of West Virginia “switched sides on this issue completely.”
The Utah Supreme Court has not made a ruling on this, but the Federal District Court for the District of Utah and the Tenth Circuit have looked at Utah law and concluded that “under Utah law damage caused by construction defects is not accidental.” But in another case, “the district court determined that property damage allegedly caused by defective or defectively installed windows was caused by an accident.”
Mr. Stevens thinks that “it is likely” that the Utah Supreme Court “will follow the increasing number of courts that have held that damage caused by construction defects is an accident for insurance purposes.
Read the court decisionRead the full story...Reprinted courtesy of
The Relevance and Reasonableness of Destructive Testing
August 17, 2017 —
David Adelstein - Florida Construction Legal UpdatesDestructive testing is a routine investigatory procedure in construction defect disputes. The destructive testing is necessary to determine liability (causation), the extent of damage, and the repair protocol. Destructive testing is designed to answer numerous questions: Why did the building component fail? Was the building component constructed incorrectly? What is the magnitude of the damage caused by the failure? What specifically caused the damage? What is the most effective way to fix the failure and damage? There are different iterations to the same questions, but in many instances, destructive testing is necessary to answer these questions.
Claimants sometimes prohibit destructive testing. Of course, destructive testing is intrusive. In many instances, it is very intrusive. But, this testing is a necessary evil. Without this testing, how can a defendant truly analyze their potential exposure and culpability? They need to be in a position to prepare a defense and figure out their liability. This does not mean destructive testing is warranted in every single construction defect dispute. That is not the case. However, to say it is never warranted is irrational.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
In Appellate Division First, New York Appellate Team Successfully Invokes “Party Finality” Doctrine to Obtain Dismissal of Appeal for Commercial Guarantors
December 23, 2024 —
Dean Pillarella - Lewis BrisboisNew York, N.Y. (November 20, 2024) - In Roc-Le Triomphe Associates, LLC v. DeSouza, 2024 NY Slip Op 05654 (1st Dep’t 2024), Associate Dean Pillarella, a member of the Appellate Practice, successfully invoked the party finality doctrine to obtain the dismissal of an appeal for the firm’s commercial guarantor clients.
The action concerned rent allegedly due and owing under a commercial lease by the lease’s tenant and guarantors. Pursuant to a 2022 order, the guarantors were awarded summary judgment and dismissal of all claims against them, with the landlord’s claims against the tenant left intact. After the decision and order was served with notice of entry by the prevailing party, the landlord did not file a notice of appeal from the order but, instead, filed a notice of appeal from a later judgment months after the time to appeal the order had expired.
Read the court decisionRead the full story...Reprinted courtesy of
Dean Pillarella, Lewis BrisboisMr. Pillarella may be contacted at
Dean.Pillarella@lewisbrisbois.com
Is Solar the Next Focus of Construction Defect Suits?
June 28, 2013 —
CDJ STAFFThere’s been a rapid growth in the sale of solar panels, and that’s lead some industry observers to wonder if manufacturers have been cutting back on quality. Current use of solar is six times what it was in 2008, with more than forty percent of that in the last year. The growth shows no sign of stopping, either. The Solar Energy Industry Association expects the amount of power generated by solar to increase by more than two-thirds in 2013.
With the oversupply, some fear that companies are relaxing their quality control. The New York Times found that there were widespread problems of defective units in solar cells, chiefly those manufactured in China. The Times article noted that at two solar plants in Spain, defect rates reached 34.5 percent.
Some industry observers disagree. The Insurance Journal quoted Andy Klump, the CEO of Clean Energy Associates, a Shanghai firm that provides quality assurance in the solar industry, who said that if a business had a 34 percent failure rate, “they would be out of business in a heartbeat.” Mr. Klump described the Times article as “not realistic.”
If the Times is right, Scott Turner, a construction insurance attorney, feels that the industry should ready itself for “a wave of large lawsuits.” Turner feels that “this litigation wave could make the battles over liability and insurance coverage for Chinese drywall seem like a small claims dispute.”
Read the court decisionRead the full story...Reprinted courtesy of
Florida Lien Law and Substantial Compliance vs. Strict Compliance
April 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesThere are literally some (or, perhaps, many!) disputes that will make you say “hmm!” The “hmm” is a euphemism for “what is a party thinking?!?” The case of Trump Endeavor 12 LLC v. Fernich, Inc., 42 Fla. L.Weekly D830a (Fla. 3d DCA 2017) is one of these cases because a party (the owner) is banking its defense on a technical “all-or-nothing” argument pertaining to whether a lienor (a supplier) substantially complied with Florida’s Lien Law because a supplier’s Notice to Owner identified the wrong general contractor. This is a challenging argument because the owner has to prove how they were adversely affected / prejudiced by the lack of substantial compliance, which is not an easy burden.
This case concerns the Trump National Doral Miami project. The project consisted of a lodge project and a separate clubhouse project, both of which had different general contractors. On the lodge project, the general contractor hired a painter which, in turn, procured paint from a supplier (the lienor). The supplier visited the project and obtained the Notice of Commencement from the owner so that it could perfect its lien rights. The owner furnished the supplier the Notice of Commencement for the clubhouse project that had a different general contractor. Relying on this Notice of Commencement, the supplier served a Notice to Owner. The Notice to Owner was timely serviced however it identified the wrong contractor – it identified the general contractor for the clubhouse project instead of the lodge project. Although the supplier later learned there was a different general contractor on the lodge project, it did not remedy the issue by serving a Notice to Owner on the correct contractor. Indeed, the contractor for the lodge project learned of the Notice to Owner furnished by the supplier and that the supplier was furnishing paint to the painting subcontractor for purposes of that project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
The Conscious Builder – Interview with Casey Grey
February 16, 2017 —
Aarni Heiskanen – AEC BusinessIn this podcast interview, Casey Grey talks about Conscious Building, passive houses, and and how we can make our homes healthier.
About Casey Grey
Casey Grey is the founder and CEO of The Conscious Builder Inc., an Ontario company.
Casey is one of those very few people who knew what he wanted from a very young age. Although his goals have changed over the years, they have always revolved around building homes. From Lego, to tree houses to custom homes, he is constantly looking for ways to build better homes.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
Hunton Insurance Partner Syed Ahmad Serves as Chair of the ABA Minority Trial Lawyer Committee’s Programming Subcommittee
January 13, 2020 —
Michelle M. Spatz - Hunton Insurance Recovery BlogSyed Ahmad, a partner in Hunton Andrews Kurth’s Insurance Coverage practice, has volunteered to serve as Chair of the
ABA Minority Trial Lawyer Committee’s Programming Subcommittee. The Minority Trial Lawyer Committee (MTL) serves as a resource for minority litigators, in-house counsel and law students, aiming to foster professional development, legal scholarship, advocacy and community involvement. As Chair of the Programming Subcommittee, Syed, who was named to Benchmark Litigation’s 40 & Under Hot List earlier this year, will help advance MTL’s mission of facilitating discussions about diversity and the law and providing career network opportunities for minority trial lawyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle M. Spatz, Hunton Andrews KurthMs. Spatz may be contacted at
mspatz@HuntonAK.com
When is Forum Selection in a Construction Contract Enforceable?
September 29, 2021 —
Christopher G. Hill - Construction Law MusingsIf there is one mantra that is repeated often here at Construction Law Musings, it is that your construction contract will be strictly construed and Virginia Courts will enforce the provisions as written. This rule includes forum selection clauses. For those that aren’t attorneys, this means that absent a statute to the contrary, the parties can pick the location of any litigation or arbitration by contract. However, the timing of signing that contract makes a difference as a relatively recent Eastern District of Virginia case points out.
Marathon Res. Mgmt Grp v. C. Cornell, Inc. examined what happens when work is performed by one party to the contract prior to the execution of the written contract that contains the forum selection provision. In this case, the defendant C. Cornell, Inc. obtained a default judgment in Texas for non-payment by Marathon for painting and cleaning of rooms at Texas A & M University for work invoiced on August 22, 2017, and September 11, 2017. Upon receipt of the garnishment from the Texas Court, Marathon sued C. Cornell in Virginia state court and the defendant removed the case to federal court. Marathon alleged two separate breaches of contract, the first was that C. Cornell violated the forum selection clause of a Master Services Agreement (“MSA”) executed on September 23, 2017. The second was a violation of another clause of the MSA that barred direct communication with any of Marathon’s customers. The second breach was alleged to be by virtue of the garnishment summons to one of Marathon’s customers.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com