Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson
April 25, 2011 —
Beverley BevenFlorez CDJ STAFFThe Texas Court of Appeals conditionally grant mandamus relief to Anderson Construction Company and Ronnie Anderson (collectively “Anderson”)… from the trial court in a construction defect lawsuit filed by Brent L. Mainwaring and Tatayana Mainwaring. See Tex. Prop. Code Ann. 27.001-.007 (West 2000 & Supp. 2010). Relators contend the trial court abused its discretion by compelling discovery while the case was abated by operation of law.
The Court of Appeals opinion describes what led up to the proceedings: “The Mainwarings’ original petition identified certain defects in their Anderson-constructed home. Those defects concerned the roof trusses and framing, air conditioning, mortar and masonry, exterior doors and windows, and weep holes. With respect to the five areas of defects identified in their original petition, the Mainwarings gave Anderson the statutorily required notice on January 13, 2010. After implementing agreed extensions, Anderson made an offer of settlement for the defects the Mainwarings identified in their notice. Almost eight months later, the Mainwarings filed an amended petition adding defects they had not included in their original petition and notice. The additional defects the Mainwarings included in their amended petition had not been addressed by Anderson’s offer of settlement.”
Following these events, Anderson claimed the Mainwarings did not respond in writing to their settlement offer. “Anderson filed a verified plea in abatement on December 2, 2010. In the trial court, Anderson claimed that the Mainwarings failed to respond in writing to Anderson’s settlement offer, as required by Section 27.004(b) of the RCLA. See Tex. Prop. Code Ann. 27.004(b)(1). The Mainwarings moved to compel discovery responses from Anderson. The Mainwarings alleged that they rejected Anderson’s settlement offer, and that if their response was insufficient, they contend that Anderson’s offer was rejected by operation of law on the twenty-fifth day after the Mainwarings received it. See Tex. Prop. Code Ann. 27.004(i). The Mainwarings’ motion to compel was not supported by affidavit. See Tex. Prop. Code Ann. 27.004(d)(2). On January 13, 2011, Anderson filed a verified supplemental plea in abatement. Anderson alleged that the Mainwarings failed to provide written notice concerning the newly alleged defects and complained the Mainwarings were attempting to circumvent the inspection and resolution procedure of the RCLA. Over Anderson’s objection that the lawsuit had been abated, the trial court granted the Mainwarings’ motion to compel discovery.”
After listening to both sides, the Court of Appeals offered this reasoning for their opinion: “The parties do not dispute that Anderson inspected the property before the Mainwarings alleged the existence of additional defects in their amended pleading, nor do the Mainwarings claim that Anderson has been given an opportunity to inspect the additional defects the Mainwarings identified in their amended pleadings. We conclude the trial court did not have the discretion to deny or lift the abatement until the Mainwarings established their compliance with the statute. In other words, the Mainwarings are required to provide Anderson a reasonable opportunity to inspect the additional defects identified by their amended pleading, which will allow Anderson the opportunity to cure or settle with respect to the newly identified defects.”
The Court of Appeals spoke directly on the issue of mandamus relief: “The Mainwarings contend that mandamus relief is not available because the trial court’s ruling does not prevent Anderson from making settlement offers during the discovery process. ‘An appellate remedy is “adequate” when any benefits to mandamus review are outweighed by the detriments.’ In re Prudential Ins. Co. of Am., 148 S.W.3d 124, 136 (Tex. 2004). The failure to abate a case is typically not subject to mandamus. See In re Allstate Cnty. Mut. Ins. Co., 85 S.W.3d 193, 196 (Tex. 2002) (citing Abor v. Black, 695 S.W.2d 564, 567 (Tex. 1985)). In this case, however, the case was abated by operation of law. By ignoring the statutory abatement, the trial court interfered with the statutory procedure for developing and resolving construction defect claims. See In re Kimball Hill Homes Tex., Inc., 969 S.W.2d 522, 525 (Tex. App. Houston [14th Dist.] 1998, orig. proceeding) (An appeal provides an inadequate remedy for the trial court’s failure to observe automatic abatement pursuant to the RCLA.). The benefits of mandamus review are not outweighed by the detriments of mandamus review in this case.“
In conclusion, “The trial court had no discretion to compel discovery while the case was abated, and Anderson, who has been compelled to respond to discovery during a period the case was under an automatic abatement, has no adequate remedy on appeal. Accordingly, we conditionally grant the petition for writ of mandamus. The writ will issue only if the trial court fails to vacate its order of February 3, 2011, and fails to refrain from proceeding with the case until a motion to reinstate is filed that establishes compliance with the notice and inspection requirements of the Residential Construction Liability Act.”
Read the trial court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Keep It Simple: Summarize (Voluminous Evidence, That Is...)
October 02, 2023 —
Steve Swart - The Dispute Resolver"The most complex analyses grow beautifully simple as they become public objects.” Philip Rieff, Fellow Teachers (1973), quoted in JOHN BARTLETT, BARTLETT’S FAMILIAR QUOTATIONS 800 (Geoffrey O’Brien gen. ed., 18th ed. 2012)
In a recent ABA Forum on Construction Law Webinar, a panelist with substantial experience as an arbitrator explained that documents are the most important evidence in a construction dispute. Fact-finders, she said, focus on contemporaneous project records more than witness testimony to vet what happened.
But, even a small to mid-sized construction project can generate millions of pages of documents. That is particularly true when disputes involve loss of productivity, delay, acceleration, and disruption. The volume of records related to entitlement and damages (e.g., timesheets, accounting, equipment logs, schedule files, meeting minutes, etc.) can overwhelm and confuse — not to mention bore — the fact finder.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Swart, Williams MullenMr. Swart may be contacted at
sswart@williamsmullen.com
Contractors Liable For Their Subcontractor’s Failure To Pay Its Employees’ Wages And Benefits
November 01, 2022 —
Edward O. Pacer & David J. Scriven-Young - ConsensusDocsRecently, Illinois Governor J.B. Pritzker signed two House Bills that amend the Illinois Wage Payment & Collections Act, 820 ILCS 115 et. seq. (“Wage Act”), to provide greater protection for individuals working in the construction trades against wage theft in a defined class of projects. Pursuant to this new law, every general contractor, construction manager, or “primary contractor,” working on the projects included in the Bill’s purview will be liable for wages that have not been paid by a subcontractor or lower-tier subcontractor on any contract entered into after July 1, 2022, together with unpaid fringe benefits plus attorneys’ fees and costs that are incurred by the employee in bringing an action under the Wage Act. This new wage theft law follows several other states that have considered and passed similar legislation.
These amendments to the Wage Act apply to a primary contractor engaged in “erection, construction, alteration, or repair of a building structure, or other private work.” However, there are important limitations to the amendment’s applicability. The amendment does not apply to projects under contract with state or local government, or to general contractors that are parties to a collective bargaining agreement on a project where the work is being performed. Additionally, the amendment does not apply to primary contractors who are doing work with a value of less than $20,000, or work that involves only the altering or repairing of an existing single-family dwelling or single residential unit in a multi-unit building.
Reprinted courtesy of
Edward O. Pacer, Peckar & Abramson, P.C. (ConsensusDocs) and
David J. Scriven-Young, Peckar & Abramson, P.C. (ConsensusDocs)
Mr. Pacer may be contacted at epacer@pecklaw.com
Mr. Scriven-Young may be contacted at dscriven-young@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Good-To-Know Points Regarding (I) Miller Act Payment Bonds And (Ii) Payment Bond Surety Compelling Arbitration
December 22, 2019 —
David Adelstein - Florida Construction Legal UpdatesEvery now and then I come across an opinion that addresses good-to-know legal issues as a corollary of strategic litigation decisions that are questionable and/or creative. An opinion out of the United States District Court of New Mexico, Rock Roofing, LLC v. Travelers Casualty and Surety Company of America, 2019 WL 4418918 (D. New Mexico 2019), is such an opinion.
In Rock Roofing, an owner hired a contractor to construct apartments. The contractor furnished a payment bond. The contractor, in the performance of its work, hired a roofing subcontractor. A dispute arose under the subcontract and the roofer recorded a construction lien against the project. The contractor, per New Mexico law, obtained a bond to release the roofer’s construction lien from the project (real property). The roofer then filed a lawsuit in federal court against the payment bond surety claiming it is entitled to: (1) collect on the contractor’s Miller Act payment bond (?!?) and (2) foreclose its construction lien against the lien release bond furnished per New Mexico law.
Count I – Miller Act Payment Bond
Claiming the payment bond issued by the contractor is a Miller Act payment bond is a head scratcher. This claim was dismissed with prejudice upon the surety’s motion to dismiss. This was an easy call.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Filling Out the Contractor’s Final Payment Affidavit
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights. If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.” (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)
There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights. Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.
There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid. This case, however, predated, a 1998 statutory change to Florida’s Lien Law.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Appellate Court Rules That Mistakenly Grading the Wrong Land Is Not an Accident
June 27, 2022 —
Jared De Jong & Scott S. Thomas - Payne & FearsIn a decision that further muddies the already murky waters of “occurrence” jurisprudence, the California Court of Appeal has ruled that a general liability policy does not cover a homeowner who mistakenly grades the wrong piece of land because the act of grading land is not “accidental.”
In Ghukasian v. Aegis Security Insurance Company, ___ Cal. App. 5th ___, 2022 WL 1421511 (2022), a homeowner instructed her contractor to clear and level a piece of land that the homeowner believed was part of her property. Unfortunately, the land was owned by a neighbor, who sued the homeowner and the contractor for trespass and negligence. The homeowner tendered to her insurer, Aegis. The homeowner’s policy contained a standard insuring agreement creating coverage for property damage caused by an “occurrence,” defined by the policy as an “accident, including continuous or repeated exposure to substantially the same general harmful conditions.” The insurer denied coverage, arguing that intentionally grading land is not an accident. Coverage litigation ensued.
Reprinted courtesy of
Jared De Jong, Payne & Fears and
Scott S. Thomas, Payne & Fears
Mr. De Jong may be contacted at jdj@paynefears.com
Mr. Thomas may be contacted at sst@paynefears.com