Consequential Damages Can Be Recovered Against Insurer In Breach Of Contract
July 22, 2019 —
David Adelstein - Florida Construction Legal UpdatesIn a favorable case for insureds, the Fifth District Court of Appeal maintained that “when an insurer breaches an insurance contract, the insured is entitled to recover more than the pecuniary loss involved in the balance of the payments due under the policy in consequential damages, provided the damages were in contemplation of the parties at the inception of the [insurance] contract.” Manor House, LLC v. Citizens Property Insurance Corp., 44 Fla. L. Weekly D1403b (Fla. 5thDCA 2019) (internal citations and quotation omitted). Thus, consequential damages can be recovered against an insurer in a breach of contract action (e.g., breach of the insurance policy) if the damages can be proven and were in contemplation of the parties at the inception of the insurance contract.
In Manor House, the trial court entered summary judgment against the insured holding the insured could not seek lost rental income in its breach of contract action against Citizens Property Insurance because the property insurance policy did not provide coverage for lost rent. However, the Fifth District reversed this ruling because the trial court denied the insured the opportunity to prove whether the parties contemplated that the insured, an apartment complex owner, would suffer lost rental income (consequential damages) if the insurer breached its contractual duties.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Supreme Court Raises the Bar on Dangerous Conditions on Public Property Claims
February 16, 2016 —
Roger Hughes – California Construction Law BlogEarlier we wrote about the affirmative defense of “design immunity” which can be used by public entities to shield themselves from personal injury claims dangerous conditions on public property. Under the design immunity doctrine a public entity can avoid liability for dangerous conditions on public property if it can show:
1.A causal relationship between the plan or design and the accident;
2.Discretionary approval of the plan or design prior to construction; and
3.Substantial evidence supporting the reasonableness of the plan or design.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Pennsylvania Federal Court Addresses Recurring Asbestos Coverage Issues
March 04, 2019 —
Craig O’Neill & Laura Rossi - Complex Insurance Coverage ReporterIn a pair of recent asbestos coverage decisions, a Pennsylvania federal court issued rulings addressing expedited funding orders, number of “occurrences,” and the applicability of aggregate limits under the Fourth Circuit’s Wallace & Gale approach.
Zurn Industries, LLC v. Allstate Insurance Company, 2018 U.S. Dist. LEXIS 197481 (W.D. Pa. Nov. 20, 2018)
Policyholder Zurn, a manufacturer and distributor of boilers, was named as a defendant in thousands of underlying asbestos-related bodily injury suits. After its primary insurers claimed exhaustion, Zurn moved on an expedited basis to require two of its excess insurers to each assume fifty percent of its defense and indemnity costs until they reached a permanent cost-sharing agreement. In denying Zurn’s expedited request for interim funding, the court held that the record was insufficient “in the opening stages of litigation, before discovery has occurred” to determine whether the underlying coverage had been properly exhausted but left the door open for Zurn to refile its motion on a more developed record.
Reprinted courtesy of
Craig O’Neill, White and Williams LLP and
Laura Rossi, White and Williams LLP
Mr. Levine may be contacted at oneillc@whiteandwilliams.com
Ms. Rossi may be contacted at rossil@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Practical Distinction Between Anticipatory Breach and Repudiation and How to Deal with Both on Construction Projects
June 10, 2024 —
Devon Griger - ConsensusDocsWhen a multilevel construction project is underway and a contractor or subcontractor isn’t performing as expected, it can be difficult to know how to address the low performance without putting the parties’ contract and good working relationship at risk. However, there may come a time when poor performance lapses into a something much worse: an anticipatory breach or repudiation of the subject contract.
Imagine Scenario One: You are a general contractor managing a large-scale construction project and one of your subcontractors is falling behind on their work. The project manager for the subcontractor calls you and says, “Look, I don’t think we’re going to be able to hit our next milestone, and probably not the next one after that.” A conversation like this would generally trigger concern for most general contractors, but it would not necessarily invoke panic. These types of delay conversations are not uncommon on large scale projects.
Compare that example, however, with Scenario Two, where the subcontractor instead says, “We received an offer to work another job for much more money, so we’re leaving the project site today and will not be returning.” This is obviously different (and potentially worse) than Scenario One, and likely cause for much greater concern.
Read the court decisionRead the full story...Reprinted courtesy of
Devon Griger, Jones WalkerMs. Griger may be contacted at
dgriger@joneswalker.com
Hartford Stadium Controversy Still Unresolved
September 22, 2016 —
Scott Van Voorhis - Engineering News-RecordThe Hartford Yard Goats and the city of Hartford, Conn., say Arch Insurance—the surety for the dual developer/prime contractor of the minor-league baseball team’s new, unfinished stadium—has committed to helping complete the project now that the team and its developer have acrimoniously split.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, Engineering News-RecordENR may be contacted at
enr.com@bnpmedia.com
Accounting for Payments on Projects Became Even More Crucial This Year
September 21, 2020 —
Christopher G. Hill - Construction Law MusingsI discussed
several of the statutory changes affecting the construction industry here at Construction Law Musings in the run-up to July 1, 2020. One of those changes, an amendment to
Virginia Code Section 43-13, may add another arrow to the collection quiver of subcontractors and suppliers. As part of the previously-linked rundown, I highlighted one of the big additions in 2020, namely the amendment making those pesky clauses that let those up the payment chain from you hold money on “this or any other project” void as against public policy.
The other big addition to 43-13 is the change that adds a possible civil cause of action for downstream and unpaid subcontractors and suppliers in the event that funds paid to a general contractor or subcontractor are not first used to pay their downstream contractors and suppliers. Prior to July 1, 2020, this statute provided criminal penalties for such behavior but did not contain the possibility of a civil penalty. The operative language for the change is as follows:
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
WA Supreme Court Allows Property Owner to Sue Engineering Firm for Lost Profits
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFIn the Daily Journal of Commerce, Scott A. Smith and James H. Wendell discussed the recent Washington Supreme Court decision in Donatelli v D. R. Strong Consulting Engineers. The court’s ruling casts “doubt on a company's ability to limit its liability for economic losses arising out of a contract dispute.”
The Donatellis hired D. R. Strong Consulting Engineers to develop vacant land in King County, however, the “project did not go according to plan and the real estate market collapsed before the project was completed,” according to the Daily Journal of Commerce. The “Donatellis lost their property through foreclosure” and then “sued the engineering firm for more than $1.5 million in lost profits.”
D. R. Strong Consulting Engineers asked for the negligence claims to be dismissed “because the parties' contract contained a provision limiting the engineering firm's liability to the amount of its fee for ‘any injury or loss on account of any error, omission, or other professional negligence.’” However, the Washington Supreme Court ruled that “the case could proceed in the trial court on a theory that the engineers could be liable if they made negligent misrepresentations that induced the Donatellis to enter into the contract in the first place.”
Smith and Wendell stated that because of “this decision, engineering, architectural, construction, and other professional service companies may now face damage claims they thought they were contractually protected against.”
Read the court decisionRead the full story...Reprinted courtesy of
Dispute Over Amount Insured Owes Public Adjuster Resolved
January 14, 2025 —
Tred R. Eyerly - Insurance Law HawaiiThe court addressed a dispute over fees that the insureds allegedly owed the public adjuster. Public' Adjuster's, LLC v. Mark Gottesdiener & Co., et al., 2024 Conn. Super. LEXIS 2352 (Conn. Super. Ct. Nov. 6. 2024).
The insureds owned an apartment building that was substantially damaged by a fire. The building was insured by Quincy Mutual Group. The insureds signed a Public Adjuster Employment Contract with The Public's Adjuster, LLC (Adjuster). The contract authorized Adjuster to negotiate the reimbursable damages with Quincy on the insureds' behalf. Adjuster was to recover 8 1/2% of any amounts received by the insureds.
Because of the extent of the fire damage, the work of negotiating a settlement with Quincy proved to be complex. Adjuster meticulously prepared several detained written estimates to by submitted to Quincy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com