Contractors with Ties to Trustees Reaped Benefits from LA Community College Modernization Program
March 03, 2011 —
Gale Holland, Michael Finnegan and Doug Smith, Los Angeles TimesIn the latest installment of the “Billions To Spend” series of investigative reports focused on construction defects, management, and cost issues relevant to LACC’s Community College Modernization Projects, the LA Times examines the costs associated with the various layers of construction management and benefits that accrued to contractors with ties to LACC trustees.
The reporting by the Times is seemingly critical of the project’s utilization of “body shops” an industry term for companies that function as employers of record. The article segment published today cites a number of circumstances wherein their utilization appears to have escalated costs substantially.
“To gauge the cost of the staffing system, The Times reviewed thousands of pages of financial records from April 2007, when URS began managing the program, to July 2010. Reporters identified two dozen contractors serving as conduits for pay and benefits for employees they did not supervise.
At least 230 people were employed in this manner, at a total cost of about $40 million, the records show.
Approximately $18 million of the total was paid to the employees, according to the Times analysis. The remaining $22 million went to profit and overhead for contractors, the records indicate.
For employees on its own payroll, the district says that medical and other benefits increase compensation costs 40% above base salaries. So if the district had employed its construction staff directly, the total cost for the period studied would have been $25 million instead of $40 million, a savings of $15 million, The Times calculated.”
Read Full Story...
Read the court decisionRead the full story...Reprinted courtesy of
Developer Transition – Washington DC Condominiums
June 29, 2017 —
Nicholas D. Cowie - Maryland Condo Construction Defect Law BlogDeveloper transition is the process by which governance over a condominium unit owners’ association (“condominium association”) is transferred from condominium developer to unit owner control. Below is an overview of the legal requirements in the District of Columbia that govern this transition process as well as a “transition checklist” for unit owner-elected boards of directors that have recently transitioned from developer control.
TRANSITION LAW OVERVIEW
PERIOD OF DEVELOPER CONTROL
A developer initially controls a condominium association because it owns all unsold units in the newly created condominium. As such, the condominium developer has the controlling votes associated with majority ownership and can appoint its own employees as the initial members of the board of directors and thereby control how the association conducts its affairs. This is referred to as the “period of developer control,” during which the condominium developer makes all decisions on behalf of the condominium association.
The developer also creates a condominium association’s governing documents allowing it to dictate, subject to applicable law, the procedures and time periods under which control over the association’s board of directors is ultimately transferred to the unit owners.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at
ndc@cowiemott.com
The Cost of Overlooking Jury Fees
February 07, 2022 —
Nicholas B. Brummel, Arezoo Jamshidi & Lawrence S. Zucker II - Haight Brown & BonesteelOn January 21, 2022, the Court of Appeal, Second Appellate District, Division Two (Los Angeles), certified for publication a 2-1 decision that serves as an important reminder to California attorneys to post jury fees in a timely manner and to use appropriate channels and consult with appellate counsel in seeking appellate relief from contested rulings.
In TriCoast Builders, Inc. v. Nathaniel Fonnegra, (B303300, Jan. 21, 2022), a construction defect dispute, the trial court set a jury trial at defendant’s request. However, on the day trial was set, defendant waived jury trial. Plaintiff objected and made an oral request for jury trial. The trial court denied the request finding that plaintiff waived its right to a jury trial by failing to timely post jury fees. The matter proceeded to a bench trial, and the court ruled in favor of defendant. Plaintiff appealed, having failed to seek a writ of mandate, which the appellate court noted “is the proper remedy to secure a jury trial allegedly wrongfully withheld.”
Reprinted courtesy of
Nicholas B. Brummel, Haight Brown & Bonesteel,
Arezoo Jamshidi, Haight Brown & Bonesteel and
Lawrence S. Zucker II, Haight Brown & Bonesteel
Mr. Brummel may be contacted at nbrummel@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Haggerty Promoted to Counsel
May 24, 2021 —
Patrick Haggerty - White and Williams LLPWhite and Williams is pleased to announce the promotion of Patrick Haggerty to the position of Counsel. Pat is a member of the Real Estate and Finance groups and practices in the Philadelphia office.
Pat focuses his practice on a wide range of commercial real estate transactions and financings. He represents real estate developers, owners, and investors, international and domestic banks, private equity firms, hedge funds, and insurance companies in the financing, acquisition, development, repositioning and disposition of commercial real estate assets.
“Pat’s unique skillset and impressive experience enhances the services which we can provide to our real estate and finance clients. We are proud to promote such a talented lawyer,” said Tim Davis, Chair of the Business Department. “We look forward to his continued success.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Haggerty, White and Williams LLPMr. Haggerty may be contacted at
haggertyp@whiteandwilliams.com
Protect Against Design Errors With Owners Protective Professional Indemnity Coverage
March 14, 2018 —
Joseph Nawa – New Day Underwriting Managers, LLCPrior to the devastation caused by Hurricanes Harvey, Irma and Maria, the AIA Consensus Construction Forecast had predicted “slower growth for the construction industry for the remainder of 2017 and through 2018.” But, given the hundreds of billions of dollars in damages caused by these horrific events, Mark Zandi, chief economist at Moody's Analytics, estimates a lift to the economy through the rebuilding of these areas. This, of course, is dependent on insurer funds and the amount of aid offered through government sources.
Nonetheless, the process will be costly, timely and exhaustive. Under such circumstances, speed is a necessity. In addition to being drawn into the earliest stages of the project development cycle, the services of construction professionals have merged so intensely that even their “consultative advice” have produced exposures in “collaborative” environments rife with liability.
A challenge for contractors in today’s design/build marketplace is securing professional liability insurance policies that will not only manage the risks associated with their own errors and omissions, but also the problems caused by designers and others contracted to work on the project. However, this too is not very easy. Such policies when purchased by contractors can be exceedingly cost prohibitive.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph Nawa, Construction Executive, a Publication of Associated Builders and Contractors. All Rights ReservedMr. Nawa may be contacted at
joseph.nawa@newdayunderwriting.com
Fracking Fears Grow as Oklahoma Hit by More Earthquakes Than California
July 09, 2014 —
Zain Shauk – BloombergSquinting into a laptop perched on the back of his pickup, Austin Holland searches for a signal from a coffee-can-sized sensor buried under the grassy prairie.
Holland, Oklahoma’s seismology chief, is determined to find the cause of an unprecedented earthquake epidemic in the state. And he suspects pumping wastewater from oil and gas drilling back into the Earth has a lot to do with it.
“If my research takes me to the point where we determine the safest thing to do is to shut down injection -- and consequently production -- in large portions of the state, then that’s what we have to do,” Holland said. “That’s for the politicians and the regulators to work out.”
So far this year, Oklahoma has had more than twice the number of earthquakes as California, making it the most seismically active state in the continental U.S. As recently as 2003, Oklahoma was ranked 17th for earthquakes. That shift has given rise to concern among communities and environmentalists that injecting vast amounts of wastewater back into the ground is contributing to the rise in Oklahoma’s quakes. The state pumps about 350,000 barrels of oil a day, making it the fifth largest producer in the U.S.
Read the court decisionRead the full story...Reprinted courtesy of
Zain Shauk, BloombergMr. Shauk may be contacted at
zshauk@bloomberg.net
NARI Addresses Construction Defect Claim Issues for Remodeling Contractors
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFThe blog of the National Association of the Remodeling Industry (NARI) reported on issues for remodeling contractors that could result in construction defect claims. The most common problems "include water intrusion and water damage (windows, roofs, siding, etc.), heaving/settlement of flatwork areas, structural deficiencies/damage and material defects, etc."
NARI suggests starting by analyzing contractual provisions. A few of the provisions addressed by NARI include Dispute Resolution, Performance Guidelines, and Notice of Claim Provisions. The article also covers Warranties, Applicable Laws, Potential Legal Action, and Insurance Coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Actual Cost Value Includes Depreciation of Repair Labor Costs
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss after determining that benefits paid for actual cost value (ACV) did not include repair or replacement labor costs. Shahan v. Allstate Vehicle & Prop. Ins. Co., 2022 U.S. Dist. LEXIS 135488 (W.D. La. July 29, 2022).
Hurricane Laura damaged the insured's home. She filed a claim with Allstate under her homeowners policy. Allstate issued payment. The insured filed suit alleging Allstate wrongfully withheld amounts by depreciating labor when calculating the ACV of the damaged property. Allstate moved to dismiss.
The policy was a replacement cost policy where the insured would receive the actual cash value of her insured property when it was damaged or destroyed by a covered peril. ACV was calculated by taking the repair/replacment which included both material and labor, and then deducting for depreciation. If no repairs or replacements were made, the insured was paid the ACV. If repairs or replacement was done, Allstate reimbursed the insured for the depreciation deduction. The insured challenged Allstate's refusal to pay 100% of the future labor costs, without any depreciation, even if the insured did not replace or repair the damaged property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com