Caltrans Hiring of Inexperienced Chinese Builder for Bay Bridge Expansion Questioned
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFThe construction of the new eastern span of San Francisco’s bay bridge has been criticized for the $6.5 billion cost, welding crack violations, and alleged cover ups by Caltrans. The Sacramento Bee reported that the company Shanghai Zhenhua Port Machinery Co. Ltd. (ZPMC) “had never built a bridge.” In fact, ZPMC “was a manufacturer of giant cranes for container ports.”
How then did ZPMC manage to obtain the contract? The Sacramento Bee stated that the company “had established a reputation as fast and cost-effective, offering savings of about $250 million compared to the competing bidder.” The project was already “years behind schedule and billions of dollars over budget by political squabbles and construction delays” and there were some fears that the “old bridge might not survive a major quake.”
Caltrans was told by an outside expert that ZPMC was a “high risk,” however, the company received a “contingent pass.” Sacramento Bee reported that an audit showed “ZPMC didn’t have enough qualified welders or inspectors…and routinely welded in the rain, a basic error that often causes defects.” Regardless, Caltrans signed off on the project.
“In August 2007, Caltrans auditors approved ZPMC outright, although the firm still lacked adequate quality control, even for ‘fracture critical’ materials,” the Sacramento Bee reported.
During the California Senate committee hearing in January, Doug Coe, a senior Caltrans engineer, said “’The race for time’ created overwhelming pressure to keep moving as planned….But there’s no excuse for building something defective like that because we are in a race for time.”
Read the court decisionRead the full story...Reprinted courtesy of
DoD Will Require New Cybersecurity Standards in 2020: Could Other Agencies Be Next?
September 09, 2019 —
Alexander Gorelik - Smith CurrieThe Department of Defense (DoD) has announced a new five-tier standard for cybersecurity certification, which it calls the Cybersecurity Maturity Model Certification, or “CMMC”. Taking an unusual approach to informing the industry, the DoD has provided only limited information about the new standard through its website and a “road tour” led by the newly-appointed head of the DoD’s Chief Information Security Office (CISO), Ms. Katie Arrington.
During her recent presentation at the National Institute of Standards and Technology’s (NIST’s) Information Security and Privacy Advisory Board (ISPAB) meeting, on August 8, 2019, Ms. Arrington revealed several new details about the requirements. Outlined below are the most significant facts from that presentation and the DoD’s website:
All companies doing business with DoD (and all tiers of subcontractors) will need to obtain CMMC certifications.
DoD will require the new certifications from all contractors (including suppliers and subcontractors) that are performing under a DoD contract. Even contractors that do not process or handle Controlled Unclassified Information (CUI) must obtain CMMCs.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander Gorelik, Smith CurrieMr. Gorelik may be contacted at
agorelik@smithcurrie.com
Tax Increase Pumps $52 Billion Into California Construction
April 20, 2017 —
JT Long - Engineering News-RecordThe first wave of new road projects could go out at the beginning of 2018 now that the California legislature has approved $52.4 billion over 10 years from a new 12-cent-per-gallon gasoline tax. SB-1 was approved late in the evening on April 6; by April 7, the California Dept. of Transportation was already working on a list of projects that could start construction by summer of 2018.
Read the court decisionRead the full story...Reprinted courtesy of
JT Long, ENRENR may be contacted at
ENR.com@bnpmedia.com
Recent Regulatory Activity
October 25, 2021 —
Anthony B. Cavender - Gravel2GavelSelected federal regulatory actions taken or proposed by several federal agencies, including the Environmental Protection Agency:
EPA Actions.
On September 15, 2021, EPA’s Water Office issued a memo rescinding a January 2021 guidance document that purported to provide the regulatory community with EPA’s understanding of the Supreme Court’s Clean Water Act ruling in the case of County of Maui v. Hawaii Wildlife Fund. That case involved a discharge of pollutants to groundwater which eventually made their way to the Pacific Ocean. Was an NPDES permit required to authorize this discharge, which was not initially made to a navigable body of water? The text of the Clean Water Act provided little guidance, and the matter has become very controversial. The Court held that if the discharge was the “functional equivalent” of a direct discharge, a permit may be required, and the Court described some factors that could influence a determination that there was the functional equivalent of a direct discharge. However, EPA has rescinded the January 2021 guidance, opining that EPA’s earlier analysis was inconsistent the Court’s opinion, and that the guidance was issued without proper deliberation within EPA or with its federal partners. Until new guidance is prepared, EPA will continue to apply “site-specific, science-based evaluations” to resolve these questions. On October 1, 2021, EPA released its “Climate Adaption Action Plan.” Briefly, EPA will take steps to ensure that its programs and policies consider current and future impacts of climate change and how the impacts disproportionately affect certain underserved or environmental justice communities. The agency’s air and water quality programs, contaminated sites activities and chemical safety and pollution prevention programs will be analyzed to determine their impact. Also on October 1, 2021, EPA released its draft FY 2022-2026 Strategic Plan to protect health and the environment. The plan, essentially an internal directive to all offices and regions, reflects a new “foundational principle”—to advance justice and equity by taking on the climate crisis and taking decisive action to advance civil rights and environmental justice.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Finding an "Occurrence," Appellate Court Rules Insurer Must Defend
March 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiReversing the trial court, the Wisconsin Court of Appeals found the insurer must defend a cross-claim against the insured owner of a building after an explosion occurred. LBC, LLC v Spectrum Brands, Inc., 2023 Wis. App. LEXIS 1251 (Wis. Ct. App, Nov. 30, 2023).
LBC leased commercial property to Spectrum. Spectrum stored lithium on the property. The lithium exploded when it came into contact with water that entered the premises during historic flooding in August 2018. Spectrum remediated the premises, vacated the premises prior to the lease's termination date, and stopped paying rent.
LBC sued Spectrum, alleging that Spectrum negligently stored the lithium and that Spectrum breached the lease. Spectrum counterclaimed, alleging that LCB breached the lease in various respects, that LCB negligent allowed water to infiltrate the premises, and that Spectrum was constructively evicted. LCB tendered the counterclaim to its insurer, General Casualty. The tender was denied and LCB sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida Law: Interplay of SIR and the Made-Whole Doctrine
March 12, 2015 —
Beverley BevenFlorez-CDJ STAFFAmanda Baggett of Roger Towers explained the nuances of self-insured retention or “SIR,” which “typically refers to a dollar amount stated in a liability policy that the insured must satisfy before the insurer is required to defend or indemnify a claim.” Baggett stated that most of the time, the SIR is satisfied by the insurer paying the initial defense costs up to the SIR. However, “the Florida Supreme Court has held that an insured may satisfy the SIR using funds received from a third party. Intervest Construction of Jax, Inc. v. General Fidelity Ins. Co., 133 So. 3d 494 (Fla. 2014).”
Read the court decisionRead the full story...Reprinted courtesy of
Buffett Says ‘No-Brainer’ to Get a Mortgage to Short Rates
October 08, 2014 —
Noah Buhayar – BloombergWarren Buffett, the billionaire chairman of Berkshire Hathaway Inc. (BRK/A), said he was puzzled by the sluggish rebound in U.S. home construction amid near record-low interest rates and a broader recovery in the economy.
“You would think that people would be lining up now to get mortgages to buy a home,” Buffett said today at a conference hosted by Fortune magazine in Laguna Niguel, California. “It’s a good way to go short the dollar, short interest rates. It is a no-brainer. But so far home construction pickup has been slower than I had anticipated.”
Housing starts slumped in August from the highest level in almost seven years to a 956,000 annualized rate, Commerce Department data show. Slow wage growth and tighter lending standards have kept some would-be borrowers from buying a home.
Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, BloombergMr. Buhayar may be contacted at
nbuhayar@bloomberg.net
Construction Robots 2023
May 08, 2023 —
Aarni Heiskanen - AEC BusinessHere’s AEC Business’s
catalog of construction robotics companies.
About Construction Robotics
Construction robots have been around since the 1960s. In the 1970s and 1980s, Japanese companies such as the Shimizu Corporation, Obayashi Corporation, and Takenaka Corporation created robots and remote-controlled machines for excavating, material handling, concrete placing, finishing, fireproofing, earthworks, rebar placing, and other construction tasks. However, the overall robotization of the industry has been slow.
The rapid development of artificial intelligence and machine learning has changed the robotic scene. Robotic hardware is also becoming affordable. Coupled with the poor availability of professional construction workers and the urge to industrialize construction, the use of robots will inevitably increase in the coming years.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi