The Risk of A Fixed Price Contract Is The Market
August 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen performing work on a fixed price or unit, there is risk that is being assumed on your end. One risk is the market. You are ultimately banking on the fact that the market is not going to make your fixed prices unprofitable. That’s not an unforeseeable occurrence because the market shifts and that shift can have a negative ripple effect.
In a recent case out of the Federal Circuit, U.S. Aeroteam, Inc. v. U.S., 2022 WL 243176 (Fed.Cir. 2022), this market risk played a role in a fixed price contract. Here, a contractor was hired by the federal government to produce ground support trailers. A key component of these trailers was a running gear. The contractor relied on a vendor for these running gears. Due to financial difficulties, the vendor had to raise its unit price for the running gears. Based on the increased price, the contractor elected to manufacture the running gears itself. The contractor asked the government if this was ok and the government approved the request. Once the contractor started manufacturing these running gears, it had an “awe” moment – the manufacturing costs were higher than anticipated. The contractor submitted a request for equitable adjustment which the government denied. The Contractor than sued the government raising three arguments to support its entitlement to additional costs: (1) constructive change; (2) cardinal change; and (3) commercial impracticability. The contractor lost on all arguments. It probably should have lost on all arguments.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Show Me the Money: The Good Faith Dispute Exception to Prompt Payment Penalties
March 13, 2023 —
Garret Murai - California Construction Law BlogCalifornia has a number of
prompt payment penalty statutes on the books. Among them is Civil Code section 8800 which requires project owners on private works projects to pay progress payments to direct contractors within 30 days after demand for payment pursuant to contract or be subject to prompt payment penalties of two percent (2%) per month on the amount wrongfully withheld. Like California’s other prompt payment penalty statutes, however, there is an important carve out: If there is a good faith dispute between the project owner and the direct contractor the project owner may withhold up to 150% of the dispute amount and not be subject to prompt payment penalties. And that, my friends, is a higher-tiered party’s “get out of jail free” card.
In a case of first impression, the 1st District Court of Appeals, in
Vought Construction Inc. v. Stock (2022) 84 Cal.App.5th 622, examined whether a project owner’s claim for liquidated damages constitutes a good faith dispute under Civil Code section 8800.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Thank You for 17 Years of Legal Elite in Construction Law
December 16, 2023 —
Christopher G. Hill - Construction Law MusingsThank you once again to those in the Virginia legal community who elected me to the Virginia Business Legal Elite in the Construction Law category for the 17th consecutive year. The 17 consecutive years of election to the Legal Elite in the Construction Category span my entire close to 14 years as a solo construction attorney. The fact that you all have continued to elect “100%” of the lawyers at The Law Office of Christopher G. Hill, PC for the last 13 years is most gratifying and only confirms that my decision to “go solo” over 13 years ago was a good one. To be included in this list of top construction attorneys is both humbling and gratifying. For the complete list of the Virginia construction lawyers who were elected along with me, see the 2023 Virginia Business Legal Elite in Construction Law.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Google, Environmentalists and University Push Methane-Leak Detection
December 21, 2016 —
Mary B. Powers – Engineering News-RecordNational Grid, which serves New York, Massachusetts and Rhode Island, is set to be the second U.S. natural-gas utility to use technology advanced by Google Earth, the Environmental Defense Fund (EDF) and Colorado State University to boost large-scale methane-leak detection. It is launching a $3-billion effort to replace gas pipelines in New York. The technology uses cutting-edge spatial analytics methods and methane sensors, specially fitted to Google Street View cars, to identify leaks and accurately measure the amount of methane escaping.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
No Coverage for Subcontractor's Faulty Workmanship
November 28, 2022 —
Tred R. Eyerly - Insurance Law HawaiiFinding faulty workmanship that did not cause property damage beyond the subcontractor's work, the court found there was no coverage under the CGL policy. Middlesex Ins. Co. v. Dixie Mech., Inc., 2022 U.S. Dist. LEXIS 175190 (N. D. Ga. Sept. 27, 2022).
The case involved a construction project on Elba Island, Georgia. IHI E&C International Corporation (IHI) filed suit against Robinson Mechanical Contractors ("Robinson") for faulty construction work, including a pipe rack and process module installation. The pipe racks allegedly contained defective welds. Robinson filed a third-party complaint against Patriot Modular, Inc. (Patriot), Robinson's subcontractor, for faulty work for IHI. Finally, Patriot filed a fourth-party complaint against Dixie Mechanical, Inc. (Dixie), alleging it subcontracted with Dixie to perform fabrication, welding, testing, and inspection of pipes under Patriot's subcontract with Robinson. Patriot contended that to the extent it was found liable to Robinson for any defective work, delays or breaches of contract for Dixie's work, Patriot was entitled to recover such amounts from Dixie.
In this case, Dixie's insurer, Middlesex Insurance Company, sought a declaration that it had no duty to defend or to indemnify Dixie. Middlesex contended that the claims of faulty workmanship in the underlying complaints constituted neither an "occurrence" nor "property damage."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Subcontractor Allowed to Sue Designer for Negligence: California Courts Chip Away at the Economic Loss Doctrine (Independent Duty Rule)
August 30, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCAn architect may have to pay over $1 million to a subcontractor who was contractually obligated to rely on the designer’s plans – even though the architect was not a party to the contract.[1] That was the ruling in U.S. f/u/b/o Penn Air Control, Inc. v. Bilbro Constr. Co., Inc.[2]
The dispute involved a $7.3 million design-build contract award to Bilbro Construction (“Bilbro”) to renovate a facility for the Naval Facilities Engineering Command in Monterey, California. Bilbro hired an architect (“FPBA”) to serve as the designer of record and provide all the architectural design services. FPBA’s design team included an acoustical sub-consultant (Sparling). The general contractor (design builder) also retained Alpha Mechanical (Alpha) as the mechanical electrical and plumbing (“MEP”) design/build subcontractor. Alpha, in turn, subcontracted the MEP design to Shadpour Consulting Engineers. During the design phase of this project, Alpha’s MEP design was reviewed by FPBA, Bilbro, and Sparling at the 35, 75, and 100 percent design completion levels. Alpha demonstrated that it regularly received direct communications during design development from Sparling and FPBA, including comments, changes, and revisions. One example Alpha cited was it raised some concerns about anticipated noise level in eight rooms. Sparling made several recommendations to Alpha and Shadpour that were implemented.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Breach Of Duty of Good Faith And Fair Dealing Packaged With Contract Disputes Act Claim
March 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting opinion on a motion to dismiss came out of the United States Court of Federal Claims dealing with the claim that the government breached its duty of good faith and fair dealing in administering the prime contract. The contractor’s argument was that the government breached its duty of good faith and fair dealing by denying the contractor’s claim under the Contract Disputes Act (CDA). This was a creative claim and argument that deserves consideration because it tied in the contracting officer’s denial of the CDA claim for additional money with a breach of the duty of good faith and fair dealing.
In this case, Aries Construction Corp. v. U.S., 2023 WL 2146598 (Fed. Cl. 2023), a prime contractor was hired for a water pipeline construction project. The contractor encountered unexpected difficult site conditions that required additional equipment and labor. The contractor informed the contracting officer and alleged it was instructed to proceed with the additional equipment and labor. The contractor submitted a claim under the CDA but the contracting officer denied the claim. The contractor pursued the claim in the United States Court of Federal Claims arguing the government breached the contract and, of interest, breached its duty of good faith and fair dealing.
The government moved to dismiss the breach of good faith and fair dealing claim arguing that besides failing to state a cause of action the Court of Federal Claims had no jurisdiction because the breach of the duty of good faith and fair dealing was not properly presented to the contracting officer under the CDA. The Court of Federal Claims denied the government’s motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Changes to Pennsylvania Mechanic’s Lien Code
July 13, 2017 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome Jim Fullerton. Jim is the President of the law firm of Fullerton & Knowles, P.C., which has attorneys licensed in Virginia, Maryland, Pennsylvania, and the District of Columbia, is a Martindale Hubbell Peer Rated Lawyer AV® Preeminent.™ The firm represents owners, lenders, design professionals, suppliers, subcontractors, general contractors and other members of the real estate and construction industries, filing mechanic’s liens, surety bond and other construction claims across all of the states in the Mid Atlantic region. He also represents creditors in bankruptcy issues nationwide, particularly defense of bankruptcy preference claims; advises owners and lenders in real estate lending and acquisition transactions; on all real estate and construction law issues; contract formation and disputes.
The firm’s Construction Law Survival Manual is well known and widely used by participants in the construction process. The 550 page manual provides valuable information about construction contract litigation, mechanic’s liens, payment bond claims, bankruptcy and credit management and contains over 30 commonly used contract forms. All of this information and recent construction law issues are constantly updated on the firm’s website.
There are two changes to the Pennsylvania Mechanic’s Lien Code that became effective September 2014. First, residential properties built by an owner for their own residence will now have a defense of payment to subcontractor mechanic’s liens. This protects homeowners from mechanic’s liens if they have paid their general contractors in full. Second, construction loan open end mortgages will have priority over mechanic’s liens, as long as at least sixty per cent (60%) of the loan proceeds are used for construction costs. This change was pushed by Pennsylvania lenders in response to a recent court case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com