Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 —
CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
Chambers USA 2020 Ranks White and Williams as a Leading Law Firm
June 15, 2020 —
White and Williams LLPWhite and Williams is once again recognized by Chambers USA as a leading law firm in Pennsylvania for achievements and client service in the area of insurance law. In addition, four lawyers received individual honors – two for their work in insurance, one for his work in banking and finance and another for his work in commercial litigation.
White and Williams is acknowledged for its renowned practice offering expert representation to insurers and reinsurers across an impressive range of areas including coverage, bad faith litigation and excess liability. The firm is recognized for its notable strength in transactional and regulatory matters, complemented by its adroit handling of complex alternative dispute resolution proceedings and is described as "reasoned and respectful." Chambers also acknowledged the firm's broad trial capabilities, including handling data privacy, professional liability and toxic tort coverage claims as well as its experience in substantial claims arising from bodily injury and wrongful death suits. White and Williams' cross-disciplinary team is also highlighted, characterized for "work[ing] well together and provid[ing] exceptional representation."
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Quick Note: Don’t Forget To Serve The Contractor Final Payment Affidavit
July 30, 2019 —
David Adelstein - Florida Construction Legal UpdatesIf you are a contractor in DIRECT CONTRACT with an owner, serve a contractor final payment affidavit on the owner, as a matter of course, and without any undue delay, particularly if you are owed money and have recorded a construction lien. In numerous circumstances, I like to serve the contractor final payment affidavit with the construction lien.
The contractor final payment affidavit is not a meaningless form. It is a statutory form (set forth in Florida Statute s. 713.06) required to be filled out by a lienor in direct privity of contract with an owner and served on the owner at least 5 days prior to the lienor foreclosing its construction lien. The contractor final payment affidavit serves as a condition precedent to foreclosing a construction lien. Failure to timely serve a contractor final payment affidavit should result in a dismissal of the lien foreclosure lawsuit, presumably by the owner moving for a motion for summary judgment. This should not occur.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Strategy for Enforcement of Dispute Resolution Rights
May 30, 2018 —
Whitney Judson - Smith CurrieArbitration and litigation each offer their own benefits and drawbacks to litigants looking to resolve a construction dispute. A careful analysis of these benefits and drawbacks may be helpful in determining whether to avoid or pursue either dispute resolution process. Arbitration is oftentimes regarded as the more economically feasible dispute resolution option and is therefore attractive to many construction dispute litigants. Although arbitration may prove to be less expensive than litigation in the long run, some litigants may prefer to file a case in court because the upfront filing fees in litigation are less expensive than the filing fees of arbitration.
Litigants may also prefer the decision makers of one process for dispute resolution over another. Arbitrators in a construction dispute oftentimes have a background in the construction industry, whereas a judge or jury may not. Strategy may dictate whether the preferable decision maker should have experience within the construction industry or be free of any construction industry knowledge and possible biases. The finality of decisions may also be a reason to strategically choose one dispute resolution process over another. Arbitration decisions are overturned only under very narrow and specific circumstances. The losing party in litigation however, has a right to appeal decisions to a higher court and has more options for recourse when the findings of the court are not supported by the evidence or the law.
Read the court decisionRead the full story...Reprinted courtesy of
Whitney Judson, Smith CurrieMs. Judson may be contacted at
wtjudson@smithcurrie.com
Nondelegable Duties
June 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you heard the expression “nondelegable duty”? The issue of a nondelegable duty comes into play when a party hires an independent contractor and the independent contractor commits negligence, primarily in the personal injury context. In other words, a plaintiff wants to hold a defendant liable for the injuries caused by the defendant’s independent contractor.
A nondelegable duty is one that “may be imposed by statute, contract, or the common law. In determining whether a duty is nondelegable, the question is whether the responsibility at issue is so important to the community that an employer should not be allowed to transfer it to a third party.” Garcia v. Southern Cleaning Service, Inc., 360 So.3d 1209, 1211 (Fla. 3d DCA 2023) (internal citation omitted).
When it comes to CONTRACTUAL duties:
[S]pecifically the principle that one who undertakes by contract to do for another a given thing cannot excuse himself to the other for a faulty performance by showing that he hired someone else to perform the task and that other person was the one at fault. In other words, where the contracting party makes it her or his duty to perform a task, that party cannot escape liability for the damage caused to the other contracting party by the negligence of independent contractors hired to carry out the task.
Gordon v. Sanders, 692 So.2d 939, 941 (Fla. 3d DCA 1997).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
U.S. Homeownership Rate Falls to Lowest Since Early 1995
October 29, 2014 —
Prashant Gopal – BloombergThe homeownership rate in the U.S. fell to the lowest in more than 19 years as the market shifted toward renting and tight credit blocked some potential buyers.
The share of Americans who own their homes was 64.4 percent in the third quarter, down from 64.7 percent in the previous three months, the Census Bureau said in a report today. The rate was at the lowest level since the first quarter of 1995.
Entry-level buyers have been held back by stringent mortgage standards and slow wage growth. The share of first-time buyers was 29 percent in September for the third straight month, compared with about 40 percent historically, according to the National Association of Realtors said.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Can a Receiver Prime and Strip Liens Against Real Property?
September 20, 2021 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogCourts overseeing receivers generally enjoy broad discretion in directing and approving a receiver’s proposed actions. But does that authority extend to a receiver not only granting a super-priority lien ahead of existing liens, but also selling the real property free and clear of all liens? In County of Sonoma v. Quail, 56 Cal.App.5th 657 (Ct. App. 2020), the California Court of Appeals answered that question in the affirmative.
Quail involved a 47,480 square-foot lot with two houses, a few garages, several outbuildings, and numerous trailers surrounded by a veritable junk yard. Despite many of these structures being uninhabitable, unsanitary, and dangerous, multiple families resided on the lot. Although Sonoma County (the “County”) ordered the owner to remediate the property several times, he failed and refused to do so. After several years of these violations going unabated, the County ultimately sought and obtained the appointment of a receiver over the real property.
To obtain funds necessary to repair the property, the receiver asked the court for permission to borrow money through the issuance of a receivership certificate to be secured by a super-priority lien—i.e., a lien ahead of all other liens—against the real property. Although the trial court initially declined to prime existing liens, when the receiver could find no one to lend money (since the land lacked equity), the trial court relented and approved a super-priority lien despite the senior secured lender’s objection (the “lender”).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
New York Appellate Court Addresses “Trigger of Coverage” for Asbestos Claims and Other Coverage Issues
November 30, 2020 —
Paul A. Briganti - Complex Insurance Coverage ReporterOn October 9, 2020, the New York Supreme Court, Appellate Division, Fourth Department, decided an appeal from a trial court’s 2018 summary judgment ruling on a number of coverage issues arising out of asbestos-related bodily injury claims against plaintiffs Carrier Corporation (Carrier) and Elliott Company (Elliott). See Carrier Corp. v. Allstate Ins. Co., No. 396 CA 18-02292, Mem. & Order (N.Y. Sup. Ct. App. Div. 4th Dep’t Oct. 9, 2020).
The Fourth Department reversed the trial court’s ruling that, under New York’s “injury in fact trigger of coverage,” injury occurs from the first date of exposure to asbestos through death or the filing of suit as a matter of law. The parties agreed that, because the policy language at issue required personal injury to take place “during the policy period,” “the applicable test in determining what event constitutes personal injury sufficient to trigger coverage is injury-in-fact, ‘which rests on when the injury, sickness, disease or disability actually began.’” Id. at 3 (quoting Cont’l Cas. Co. v. Rapid-American Corp., 609 N.E.2d 506, 511 (N.Y. 1993)). The Fourth Department concluded that, in resolving the issue, the trial court erred by relying on inapposite decisions in other cases where: (1) the parties had stipulated or otherwise not disputed that first exposure triggered coverage[1]; or (2) the issue had not been resolved on summary judgment, but rather at trial based on expert medical evidence[2]. The Fourth Department further explained that, even if plaintiffs here had met their initial burden on summary judgment by submitting admissible evidence that asbestos-related injury actually begins upon first exposure, the defendant-insurer’s opposition – which included affidavits of medical experts contradicting that evidence and averring instead that “harm occurs only when a threshold level of asbestos fiber or particle burden is reached that overtakes the body’s defense mechanisms” – raised a triable issue of fact. Id. at 4. The Fourth Department also rejected plaintiffs’ argument that the defendant-insurer was collaterally estopped on the “trigger” issue by a California appellate court’s decision in Armstrong World Industries, Inc. v. Aetna Casualty & Surety Co., 52 Cal. Rptr. 2d 690 (Cal. Ct. App. 1996). The Fourth Department reasoned that the issues litigated in the two cases were not identical because, among other things, California and New York “apply different substantive law in determining when asbestos-related injury occurs.” Carrier, Mem. & Order at 4.