Courthouse Reporter Series: Nebraska Court of Appeals Vacates Arbitration Award for Misconduct
November 18, 2024 —
Brendan J. Witry - The Dispute ResolverVacating an arbitration award is often seen as an uphill battle. Indeed, the U.S. Supreme Court has stated that “courts may only vacate an arbitrator’s decision ‘only in very unusual circumstances.’” Oxford Health Plans, LLC v. Sutter, 569 U.S. 564, 568 (2013). The Federal Arbitration Act provides limited grounds to seek the vacatur of an arbitration award. In Lund-Ross Constructors v. Duke of Omaga, LLC, ___ N.W.3d ___, 33 Neb.App.73, the Nebraska Court of Appeals found that an arbitrator’s conduct warranted the partial vacatur of the award, which granted relief to a subcontractor who filed a counterclaim after the arbitration hearing had closed.
Lund-Ross contracted with Duke of Omaha to build an apartment complex in Omaha. Lund-Ross, in turn, sub-contracted with A Raymond Plumbing. Following completion of the building, Owner withheld payment from Lund-Ross, who in turn, withheld payment from Raymond. Both Lund-Ross and Raymond filed mechanics liens and initiated suits; Raymond’s suit ultimately was dismissed for want of prosecution. Lund-Ross proceeded to arbitration with Owner, naming Raymond as a respondent. Raymond did not participate in the arbitration as a claimant at the time of the hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Impact of Lis Pendens on Unrecorded Interests / Liens
September 15, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a previous article, I discussed the importance of recording a lis pendens in a construction lien foreclosure action.
There is another noteworthy point relating to the impact of lis pendens that can provide quite a bit of consternation.
Florida Statute 48.23(1)(d) provides:
Except for the interest of persons in possession or easements of use, the recording of such notice of lis pendens, provided that during the pendency of the proceeding it has not expired pursuant to subsection (2) or been withdrawn or discharged, constitutes a bar to the enforcement against the property described in the notice of all interests and liens, including, but not limited to, federal tax liens and levies, unrecorded at the time of recording the notice unless the holder of any such unrecorded interest or lien intervenes in such proceedings within 30 days after the recording of the notice. If the holder of any such unrecorded interest or lien does not intervene in the proceedings and if such proceedings are prosecuted to a judicial sale of the property described in the notice, the property shall be forever discharged from all such unrecorded interests and liens. If the notice of lis pendens expires or is withdrawn or discharged, the expiration, withdrawal, or discharge of the notice does not affect the validity of any unrecorded interest or lien.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Legal Risks of Green Building
March 22, 2021 —
Mark D. Shifton - Construction ExecutiveAll construction projects involve elements of legal risk. Insurance and indemnity claims, delay claims and professional negligence claims are simply accepted risks when involved in construction. Green building projects are no exception to this rule, and often involve unique issues that are not present in typical construction projects.
Green building projects commonly employ new or untested construction materials, require construction methods that lack significant track records, and ultimate building performance often fails to meet design expectations. As such, green building projects may give rise to entirely new types of legal risk that should be considered and allocated early in the process.
In the past 15 years, the number of buildings for which green certifications have been sought has grown exponentially, and the growth rate of green building and sustainable construction has far outpaced the growth rate of the construction industry as a whole. As green building projects become increasingly common (and often increasingly required by the federal, as well as state and local governments), the unique legal risks presented by green building projects take on an increase importance.
Reprinted courtesy of
Mark D. Shifton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Shifton may be contacted at
mshifton@gllawgroup.com
Is There a Conflict of Interest When a CD Defense Attorney Becomes Coverage Counsel Post-Litigation?
September 01, 2011 —
Chad Johnson of Higgins, Hopkins, McLain & Roswell, LLCIn Weitz Co., LLC v. Ohio Cas. Ins. Co., the U.S. District Court for the District of Colorado was asked to rule on a motion to disqualify counsel in an insurance coverage action. 11-CV-00694-REB-BNB, 2011 WL 2535040 (D. Colo. June 27, 2011). Motions to disqualify counsel are viewed with suspicion, as courts “must guard against the possibility that disqualification is sought to ‘secure a tactical advantage in the proceedings.’” Id. at *2 (citing Religious Technology Center v. F.A.C.T. Net, Inc., 945 F. Supp. 1470, 1473 (D. Colo. 1996).
Weitz Company, LLC (“Weitz”) is a general contractor and defendant in an underlying construction defect suit which had concluded before the action bringing rise to this order. In the underlying action, Weitz made third-party claims against subcontractors, including NPW Contracting (“NPW”). Weitz was listed as an additional insured under NPW’s policies with both Ohio Casualty Insurance Company and Mountain States Mutual Casualty Company (collectively “the Carriers”). The Carriers accepted Weitz’s tender of defense under a reservation of rights. However, neither insurance carrier actually contributed to Weitz’s defense costs in the underlying action. At the conclusion of the construction defect action, the parties unsuccessfully attempted to apportion the attorney’s fees and costs. Eventually, Weitz brought suit against the recalcitrant carriers. The Lottner firm, which had previously represented Weitz in the underlying construction defect action, continued to represent Weitz in this coverage action.
Read the full story…
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
No Prejudicial Error in Refusing to Give Jury Instruction on Predominant Cause
November 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's judgment after the jury determined there was no coverage for a leaking pipe. Mendoza v. Pacific Spec. Ins. Co., 2024 Cal. App. Unpub. EXIS 5477 (Cal. Ct. App. Aug. 20, 2024).
The Mendoza's third amended complaint alleged their home was damaged "by overflow of water from the dwelling's plumbing system resulting from a broken pipe, which overflow undermined the structural integrity of the dwelling."
The Mendozas insured their home under a policy issued by Pacific. The policy insured the property against "sudden and accidental direct physical loss" except where expressly excluded. The Mendozas submitted a claim Pacific paid approximately $1800 for the loss and closed the claim. The amount paid did not include payment for any structural damage to the home. The Mendozas alleged that Pacific's failure to conduct a full and fair investigation into the structural damage and its inadequate payment of benefits was a breach of the implied covenant of good faith and fair dealing.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
US Civil Rights Tools Are Failing the Most Polluted Black Communities
February 05, 2024 —
Manann Donoghoe & Andre Perry - BloombergIn 2022, the United Nations declared that access to a safe and healthy environment, free of pollutants and toxic waste, is a universal
human right. The resolution provides a legal foundation for international challenges to environmental injustice; it should also provide an impetus for nations like the US to enforce their own environmental protections.
Without more clearly defined rights, some of the greatest environmental injustices may continue to be mired in politics.
Take the case of “Cancer Alley,” an 85-mile stretch along the Mississippi River in Louisiana where Black residents have long faced higher rates of death and morbidity due to polluted and toxic environments. For people of color living in the region,
fresh air is certainly not a right; it is a privilege for others to experience.
Reprinted courtesy of
Manann Donoghoe, Bloomberg and
Andre Perry, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Mechanics’ Lien “Waivers” and “Releases”: What’s the Difference?
March 19, 2015 —
Thomas C. Rogers – White and Williams LLPIn the world of Pennsylvania mechanics’ liens there is much confusion about the interchangeable use of the words mechanics lien “waiver” and mechanics’ lien “release.” Many who work in the world of real estate in Pennsylvania, be they contractors, subcontractors, developers, lenders, or attorneys, use these terms interchangeably without understanding that there is a meaningful difference. Failure to understand the difference creates confusion when discussing issues and drafting documents regarding mechanics’ liens.
In Pennsylvania a mechanics’ lien “waiver” is the pre-construction waiver of liens that was historically executed by a general contractor and an owner and filed with the Prothonotary in the county in which construction is located. These pre-construction lien “waivers,” assuming they were properly prepared, signed by the contractor and owner and filed in accordance with applicable law, negated the ability of that contractor and its subcontractors to file a mechanics’ lien on the subject property. These pre-construction lien “waivers” were part of every construction loan closing up through the amendments to the Pennsylvania Mechanics’ Lien Act that went into effect in 2007. Since 2007, the Mechanics’ Lien Act has been amended twice to further address those circumstances in which pre-construction lien waivers still have vitality. Except with respect to those narrow situations specifically provided for in the statute, pre-construction lien “waivers” are against public policy in Pennsylvania.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas C. Rogers, White and Williams LLPMr. Rogers may be contacted at
rogerst@whiteandwilliams.com
Happy Thanksgiving from CDJ
November 27, 2013 —
CDJ STAFFAs Thanksgiving kicks off this holiday season, all of us at CDJ would like to gratefully acknowledge all of our valued readers and contributors in the construction defect and claims community. This November marks CDJ’s third anniversary. With your continued support we are looking forward to expanded coverage and features in our 4th year. Best wishes to you and yours this holiday season!
Read the court decisionRead the full story...Reprinted courtesy of