Ohio Supreme Court Holds No Occurence Arises from Subcontractor's Faulty Workmanship
January 09, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Ohio Supreme Court bucked the modern trend by finding that there was no coverage under CGL policy's the subcontractor's exception for faulty workmanship claimed against the insured. Ohio N. Univ. v. Charles Constr. Servs. 2018 Ohio LEXIS 2375 (Ohio Oct. 9, 2018).
The University contracted with Charles Construction Services, Inc. to build a new luxury hotel and conference center on campus. After work was completed, the University discovered extensive water damage from hidden leaks that it believed were caused by the defective work of Charles Construction and its subcontractors. Repairs were made at the cost of $6 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
What to Expect From the New Self-Retracting Devices Standard
November 29, 2021 —
Andre Pelland - Construction ExecutiveOne of the latest and most anticipated changes to occur this year relevant to fall protection is the publishing of the ANSI/ASSP Z359.14 2021 revision. Although the effective date isn’t until August 2022, this change is prompting the need for end user to prepare for using and understanding the new terminology performance requirements that will ultimately alter equipment selection criteria.
The reason for its relevance is mostly due to its industry dependence and the increasing popularity of these types of devices. This voluntary consensus standard accounts for a vast portion of the fall protection market equipment and has been adopted as the industry standard, even though it is not the legal requirement. To assure a smooth transition, the immediate priority should be to understand the changes and what it means from a usability standpoint. A clear understanding of what changes devices need to comply will allow users to proceed with a comprehensive transition plan.
What Are the Most Relevant Changes for the User?
Classes
The most significant changes are for Class A and B devices used to designate arrest distances and forces and the introduction of the Class 1 and 2 devices. These classes were known as designators for arresting falls at 24 inches and under with higher forces (Class A), and 54 inches and under with lower forces (Class B). Class 1 devices allow anchoring on overhead anchorages only and limitg freefall to no more than two feet.
Reprinted courtesy of
Andre Pelland, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Pelland may be contacted at
andre.pelland@puresafetygroup.com
Consider Manner In Which Loan Agreement (Promissory Note) Is Drafted
March 02, 2020 —
David Adelstein - Florida Construction Legal UpdatesConsider who you loan money too and, perhaps more importantly, the manner in which your loan agreements (promissory notes) are drafted. By way of example, in what appears to be a failed construction project in Conrad FLB Management, LLC v. Diamond Blue International, Inc., 44 Fla. L. Weekly D2897a (Fla. 3d DCA 2019), a group of lenders lent money to a limited liability company (“Company”) in connection with the development of a project. Promissory notes were executed by Company and executed by its managing member as a representative of Company, and not in a personal capacity. Company, however, did not own the project. Rather, an affiliated entity owned the project (“Affiliated Entity”). Affiliated Entity had the same managing member as Company. Once the Company received the loan proceeds, it transferred the money to Affiliated Entity, presumably for purposes of the project.
The loans were not repaid and the lenders sued Company, Affiliated Entity, and its managing member, in a personal capacity. The lenders claimed they were all jointly liable under the promissory notes. Although the trial court granted summary judgment in favor of the lenders, this was reversed on appeal as to the Affiliated Entity and the managing member because there was a factual issue as to whether they should be bound by the note executed on behalf of Company.
First, Florida Statute s. 673.4011(1) provides that “a person is not liable on a promissory note unless either (a) the person signed the note, or (b) the person is represented by an agent who signed the note.” Conrad FLB Management, LLC, supra. Affiliated Entity is a separate entity and did not execute the note.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the court decisionRead the full story...Reprinted courtesy of
Robinson + Cole
Failure to Meet Code Case Remanded to Lower Court for Attorney Fees
May 24, 2011 —
CDJ STAFFJudge Patricia J. Cottrell, ruling on the case Roger Wilkes, et al. v. Shaw Enterprises, LLC, in the Tennessee Court of Appeals, upheld the trial court’s conclusion that “the builder constructed the house in accordance with good building practices even though it was not in strict conformance with the building code.” However, Judge Cottrell directed the lower court to “award to Appellants reasonable attorneys' fees and costs incurred in their first appeal, as determined by the trial court.”
Judge Cottrell cited in her opinion the contract which specified that the house would be constructed “in accordance with good building practices.” However, after the Wilkes discovered water leakage, the inspections revealed that “that Shaw had not installed through-wall flashing and weep holes when the house was built.” The trial court concluded that:
“Separate and apart from the flashing and weep holes, the trial court concluded the Wilkeses were entitled to recover damages for the other defects they proved based on the cost of repair estimates introduced during the first and second trials, which the court adjusted for credibility reasons. Thus, the trial court recalculated the amount the Wilkeses were entitled to recover and concluded they were entitled to $17,721 for the value of repairs for defects in violation of good business practices, and an additional 15%, or $2,658.15, for management, overhead, and profit of a licensed contractor. This resulted in a judgment in the amount of $20,370.15. The trial court awarded the Wilkeses attorneys” fees through the Page 9 first trial in the amount of $5,094.78 and discretionary costs in the amount of $1,500. The total judgment following the second trial totaled $26,973.93.”
In this second appeal, Judge Cottrell concluded, that “the trial court thus did not have the authority to decide the Wilkeses were not entitled to their attorneys” fees and costs incurred in the first appeal.”
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Understand Agreements in Hold Harmless and Indemnity Provisions
June 06, 2022 —
Jeffrey Cavignac - Construction ExecutiveOne of the most important provisions in a construction contract is the indemnity provision. An indemnity provision, which usually includes a requirement to hold harmless and defend another party, is included in nearly all construction contracts. Generally speaking, the upstream party (a general contractor or owner, for example) is attempting to shift risk to a downstream party (the general contractor or a subcontractor). In simple terms, subject to certain parameters, the downstream party is agreeing to be responsible for the upstream parties’ mistakes.
DEFINING INDEMNIFICATION
Insurance brokers focused on development and construction businesses get asked frequently: “If we sign this, are we insured?” It would be great if this could be answered “yes” or “no,” but life is rarely that straightforward. To understand whether a specific indemnification is insurable, we have to drill down on the actual provision. Let’s look at a typical indemnification below:
“To the fullest extent permitted by law the Contractor shall indemnify, defend and hold harmless the owner, architect, architect’s consultants and agents and employees of any of them from and against any claims, damages, losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the work whether caused in whole or in part by the contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable.”
Reprinted courtesy of
Jeffrey Cavignac, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Disruption: When Did It Start and Where Will It End?
June 25, 2019 —
Brian Gallagher - Construction ExecutiveIf change is the only constant—as was famously observed by a Greek philosopher circa 500 B.C.—then why single out some changes as “disruption”?
Disruption is about more than just technology; it’s about more, even, than the rapid rollout and development of technology in the past couple of decades. The word disruption refers to processes or products that are fundamentally different from what is currently in use and that render unforeseen, large-scale changes. Early discussions of disruption (the term was coined by Harvard Business School professor Clayton M. Christensen in a 1995 Harvard Business Review article) compared incremental change in existing systems, which are usually supported by established corporations, to innovations that start out as something completely fresh, limited in their appeal and flawed in initial iterations.
The construction industry was—and still is—late to adopt most technologies and late in experiencing overall disruption. It also lags behind other industries when it comes to efficiency and productivity. McKinsey reported that construction is one of the “least digitized industries in the world,” despite employing approximately 7% of the world’s working-age population and representing one of the world economy’s largest sectors. Disruption is likely to be fast approaching now, even for the construction industry. But its delay may confer the benefit of allowing construction companies to learn from other industries’ mistakes.
Reprinted courtesy of
Brian Gallagher, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized as 2022 Illinois Super Lawyers® and Rising Stars
February 21, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that two Partners from the Chicago, IL office have been selected to the 2022 Illinois Super Lawyers list. In addition, three Partners have been named to the 2022 Super Lawyers Rising Stars list.
2022 Illinois Super Lawyers
2022 Super Lawyers Rising Stars
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman