Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New Hampshire Asbestos Abatement Firm Pleads Guilty in Federal Fraud Case
February 02, 2017 —
Justin Rice - Engineering News-RecordFor the second time in three months, a New England-based asbestos removal company pleaded guilty in federal court to wage and benefit violations.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com
Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season
October 11, 2021 —
Tracy Alan Saxe, Kelly A. Johnson, Samantha M. Oliveira & R. G. Nelson - Saxe Doernberger & VitaSDV's Natural Disaster Recovery Group presents the Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season. This handbook intends to be a practical guide on policyholder issues, both homeowners and business owners alike, when preparing for hurricane season and handling claims after a loss due to a hurricane. The handbook is a living document that will evolve over time, as our Natural Disaster Recovery Group members continue to contribute new and expansive content on the complex issues arising in this area. Remember to check back for additional information and updated content regarding the Hurricane Season Policyholder’s Handbook.
I. Are You Adequately Insured for a Hurricane?
Understanding the various types of coverage policyholders can purchase is vital to weathering the financial storm following a natural disaster.
Reprinted courtesy of
Tracy Alan Saxe, Saxe Doernberger & Vita,
Kelly A. Johnson, Saxe Doernberger & Vita,
Samantha M. Oliveira, Saxe Doernberger & Vita and
R. G. Nelson, Saxe Doernberger & Vita
Mr. Saxe may be contacted at TSaxe@sdvlaw.com
Ms. Johnson may be contacted at KJohnson@sdvlaw.com
Ms. Oliveira may be contacted at SOliveira@sdvlaw.com
Ms. Nelson may be contacted at RNelson@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Awarding Insurer Summary Judgment Before Discovery Completed Reversed
August 29, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed the trial court's awarding of summary judgment to the insurer because discovery was not completed. Sacramento v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 4292 (Fla. Ct. App. June 22, 2022).
The insured filed a claim under the all-risk policy for water damage caused by Hurricane Irma. Citizens denied the claim based upon a policy exclusion. The insured filed suit on March 8, 2019.
On April 24, 2020, Citizens moved for summary judgment. A hearing was set for August 10, 2020. Citizens filed a notice for a deposition of a Mitigation Company representative scheduled to occur on December 1, 2020. On August 14, 2020, the insured filed an opposition to the summary judgment motion arguing that it would be premature to grant the motion because there were still pending depositions. The insured specifically requested that the trial court not enter summary judgment until the mitigation company's representative was deposed because he was a key witness who would be testifying regarding the cause of loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Condos Down in Denver Due to Construction Defect Litigation
November 06, 2013 —
CDJ STAFFA new report suggests that fears of construction defect litigation may be the cause of the slump in condo building in the Denver area. The Denver Business Journal reports that the Denver Regional Council of Governments commissioned the study by Economic & Planning Systems. The conclusion of the report was that the only type of condominium likely to be built is high-cost units with high profit margins. This is not good news for the DRCOG, which is seeking to create more affordable housing.
The report found that builders assess the likeliness of being sued “is nearly 100 percent,” that costs of addressing construction defects are 12% higher than at apartment complexes, and that preparing for litigation adds about $15,000 to the cost of a condo unit.
One possible remedy is to reform Colorado’s construction defect laws. Bob Muphy, the mayor of Lakewook and an advocate of construction defect litigation reform, said that he sees “this as a verification of what I’ve been talking about.”
Read the court decisionRead the full story...Reprinted courtesy of
AB 1701 – General Contractor Liability for Subcontractors’ Unpaid Wages
December 01, 2017 —
Alex Baghdassarian, Eric M. Gruzen, & Kerri Sakaue – Peckar & Abramson, P.C.Contractors will soon find themselves on the frontline of wage disputes on projects if laborers working on behalf of their subcontractors or vendors are unpaid. On October 14, 2017, Governor Jerry Brown signed into law AB 1701, which will allow laborers to seek direct compensation from the general contractors on private projects, if their wages remain unpaid.
The legislative mandate requires direct contractors—defined as contractors who have a direct contractual relationship with an owner—to assume liability for any debt incurred by a subcontractor, at any tier, for a wage claimant’s performance of labor included in the subject of the original contract between the general contractor and the owner. The California bill will apply to all private construction contracts entered into on or after January 1, 2018. Previously, all laborers could maintain a mechanic’s lien claim against private property, without needing to serve a 20-day preliminary notice, but there was no statutory obligation on the “direct contractors” to reimburse the laborers their unpaid wages.
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Alex Baghdassarian,
Eric M. Gruzen and
Kerri Sakaue
Mr. Baghdassarian may be contacted at abaghdassarian@pecklaw.com
Mr. Gruzen may be contacted at egruzen@pecklaw.com
Ms. Sakaue may be contacted at ksakaue@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
NY Estimating Consultant Settles $3.1M Government Project Fraud Case
November 23, 2020 —
Eva Fedderly - Engineering News-RecordVJ Associates, a Hicksville, N.Y., estimating consultant, has agreed to pay $3.13 million in civil and criminal penalties to settle charges that the firm overbilled and falsified hours on multiple federal and state government-funded transportation and other contracts in New York and Massachusetts, the U.S. Attorney's office in Boston announced on Oct. 29.
Reprinted courtesy of
Eva Fedderly, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of