Liability Insurer’s Duty To Defend Insured Is Broader Than Its Duty To Indemnify
June 03, 2019 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to liability insurance, an insurer’s duty to defend its insured from a third-party claim is much broader than its duty to indemnify. This broad duty to defend an insured is very important and, as an insured, you need to know this. “A liability insurer’s obligation, with respect to its duty to defend, is not determined by the insured’s actual liability but rather by whether the alleged basis of the action against the insurer falls within the policy’s coverage.” Advanced Systems, Inc. v. Gotham Ins. Co., 44 Fla. L. Weekly D996b (Fla. 3d DCA 2019) (internal quotation omitted). This means:
Even where the complaint alleges facts partially within and partially outside the coverage of a policy, the insurer is nonetheless obligated to defend the entire suit, even if the facts later demonstrate that no coverage actually exists. And, the insurer must defend even if the allegations in the complaint are factually incorrect or meritless. As such, an insurer is obligated to defend a claim even if it is uncertain whether coverage exists under the policy. Furthermore, once a court finds that there is a duty to defend, the duty will continue even though it is ultimately determined that the alleged cause of action is groundless and no liability is found within the policy provisions defining coverage.
Advanced Systems, supra(internal citations and quotations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Another Setback for the New Staten Island Courthouse
January 13, 2014 —
Melissa Zaya-CDJ STAFFThe new Staten Island Courthouse received another setback when James McDonough filed suit stating unsafe work conditions, according to Frank Donnelly writing for Silive. The completion date for the new multistory, $230 million complex has been rescheduled four times so far.
Fifty-eight year old James McDonough, resident of Ridgewood Queens, became injured after a fall down a shaft, and he subsequently “sued the city, state Dormitory Authority, the state Office of Court Administration and various contractors,” Donnelly reported. A total of ten defendants have been named in the suit.
According to Silive, the Office of Court Administration, Dormitory Authority and the Law Department would not comment on the pending litigation further except to say that papers have been filed and the case is under review.
Read the court decisionRead the full story...Reprinted courtesy of
Brief Overview of Rights of Unlicensed Contractors in California
September 10, 2014 —
William M. Kaufman – Construction Lawyers BlogUnder California Contractor’s State License Law enumerated in Business and Professions Code Sections 7000 to 7191, a contractor may not “bring or maintain” any action for compensation for performing any act or contract for which a license is required unless the contractor was duly licensed “at all times” during performance. Bus & Prof Code Section 7031(a).
What does this mean and who does it include?
This is a question that often has to be answered on a case by case basis. Basically, California does not want unlicensed contractors to be able to get paid for work that should be performed by a licensed contractor. The law has set forth some general parameters. General contractors, subcontractors, and master developers must be licensed. However, suppliers, manufacturers, laborers and equipment lessors are exempt and do not need a contractor’s license. Essentially, those parties that merely furnish material or supplies without fabricating them into, or consuming them in the performance of work, do not need to be licensed. Bus & Prof Code Section 7052.
There are sever fines and penalties for those who improperly perform construction work without a license. A contract between any contractor and an unlicensed subcontractor is a misdemeanor. Lack of a license bars all actions in law or in equity for collection of compensation for the performance of work requiring a license. There are very few exceptions to this rule. A “savvy” unlicensed contractor cannot simply avoid these requirements by “subbing” out all the work to licensed contractors. Any person who uses the services of an unlicensed contractor may file a court action or cross-complaint to recover all payments made to the unlicensed contractor. In addition, a person who uses the services of an unlicensed contractor is a victim of a crime and eligible for restitution of economic losses regardless of whether that person had knowledge that the contractor was unlicensed. Bus. & Prof Code Sections 7028, 7028.16. It goes without saying that performing work without a license on projects is a bad idea.
Reprinted courtesy of
William M. Kaufman, Lockhart Park LP
Mr. Kaufman may be contacted at wkaufman@lockhartpark.com, and you may visit the firm's website at www.lockhartpark.com
Read the court decisionRead the full story...Reprinted courtesy of
Ensuing Loss Provision Salvages Coverage for Water Damage Claim
September 16, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the D.C. Circuit reversed the district court's finding of no coverage and found that the ensuing loss provision provided coverage for water damage. 3524 East Cap Venture, LLC, et al. v. Weschester Fire Ins. Co., et al., 104 F. 4th 193 (D.C. Cir. 2024).
Plaintiff 3534 East Cap Venture, LLC, a real-estate developer, hired plaintiff McCullough Construction, LLC, to build a residential and retail complex. Defendants Westchester Fire Insurance Company and Endurance American Insurance Company issued identical builders' risk policies, which covered the building while it was under construction. Each insurer was responsible for half of any qualifying losses.
The policies covered loss caused by or resulting from water damage. The policies, however, excluded loss caused by "dampness of atmosphere" or by "[e]xtremes or changes in temperature." But the exclusions contained an exception if "loss by an insured peril ensues."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
General Contractor Supporting a Subcontractor’s Change Order Only for Owner to Reject the Change
December 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe opinion in Westchester Fire Ins. Co, LLC v. Kesoki Painting, LLC, 260 So.3d 546 (Fla. 3d DCA 2018) leads to a worthy discussion because it involves a common scope of work occurrence on construction projects involving a general contractor and subcontractor. The contractor submits a subcontractor’s change order request to the owner and the owner rejects the change order. What happens next is a scope of work payment dispute between the general contractor and subcontractor. Yep, a common occurrence.
In this case, a general contractor hired a subcontractor to perform waterproofing and painting. A scope of work issue arose because the specifications did not address how the window gaskets should be cut and then sealed. The owner wanted the window gaskets cut at a 45-degree angle and the subcontractor claimed this resulted in increased extra work. The general contractor agreed and submitted a change order to the owner to cover these costs. The owner rejected the change order claiming it was part of the general contractor’s scope of work even though the cutting of window gaskets at a 45-degree angle was not detailed in the specifications.
After the subcontractor filed a suit against the general contractor’s payment bond surety, the project architect further rejected the change order because gasket cutting was part of the specification requirements. (Duh! What else was the architect going to say? It was not going to concede there was an omission that resulted in a change order to the owner, right?)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Endorsement Excludes Replacement of Undamaged Property with Matching Materials
August 20, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court approved the insurer's endorsement which stated the insured would not pay for undamaged property in order to match damaged property. Noonan v. Am. Family Mut. Ins. Co., 2019 U.S. App. LEXIS 15545 (May 24, 2019).
After hail and wind damaged part of the roof in the insureds' home, American Family inspected the roof and determined that it had suffered $12,000 in damage. The insureds disputed this amount and demanded an appraisal to provide a binding estimate of the amount of loss. American Family asked the appraisers to divide their estimate into two categories - one for replacing damaged shingles and another for replacing undamaged shingles that would not match those needed to replace the damaged ones. The appraisers did not do so. They instead found that replacing the entire roof would cost $141,000 and noted there was a matching issue because alternative products did not match the current shingles on the roof.
Of the $141,000 needed to replace the entire roof, American Family estimated that $87,232.98 was due to the costs of matching. The insureds sued. The district court remanded the case to the appraisers to clarify the award by differentiating the costs attributable to the actual roof damage from those attributable to shingle matching. The appraisers clarified the award and reported that actual damages were $66,619, meaning that $74,381 was attributable to matching. American Family then paid the actual damages, less the deductible, but refused to pay the rest.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Points on Negotiating Construction Claims
December 30, 2013 —
CDJ STAFFEugene Heady of Smith Currie and Hancock offers some pointers on the effective negotiation of construction claims. He notes that “claims and disputes in the construction industry are commonplace,” but that “settlement usually comes after much pain, suffering, and expense.” He offers nine points to consider when negotiating construction claims.
His first two points are to develop a claim position and then document that claim. He says that “the facts underlying the claim should be nonnegotiable.” The documentation “suggests to your opponent that you have done your homework and are serious about the pursuit of your claim.” He also notes that you need to understand the strengths and weaknesses of your position.
On the other side, you need to “understand your opponent’s positions,” and also “your opponent’s strengths.” He points out that “an appreciation for what is truly important to your opponent is the starting point for the development of creative solutions to the dispute.
Further, bargaining should be done in good faith, negotiation should be done on the merits, and you are well advised to “choose a seasoned and skilful negotiator. “A prolonged and expensive legal battle is not likely to change the outcome,” he warns.
Read the court decisionRead the full story...Reprinted courtesy of
Fundamental Fairness Trumps Contract Language
September 24, 2014 —
Craig Martin – Construction Contractor AdvisorThe Texas Supreme Court recently ruled that a “no-damages-for-delay” clause would not be enforced where the delay was caused by the owner. The court’s ruling flies squarely in the face of the contract language that attempted to insulate the owner from any delay claims, even those it caused.
In the case of Zachary Construction v. Port of Houston underlying contract, proposed by the Port of Houston, was heavy handed, to say the least. The contract provided:
“[Contractor] shall receive no financial compensation for delay or hindrance to the Work. In no event shall the Port Authority be liable to [Contractor] … for any damages arising out of or associated with any delay or hindrance to the Work, regardless of the source of the delay or hindrance, including events of Force Majeure, AND EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY. [Contractor’s] sole remedy in any such case shall be an extension of time.”
Wow, that’s some one-sided language. If the contract was enforced, the contractor could not get any damages for delay, even those damages caused by the active interference of the Port of Houston.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com