Recent Amendments and Caselaw Affecting the Construction Industry in Texas
April 19, 2022 —
Frederick H. Wen - Gordon Rees Scully Mansukhani, LLPHere are some recent Texas legislative amendments and Texas Supreme Court cases from the past year concerning the construction industry in Texas.
1) Recent Legislative Amendments Concerning the Construction Industry:
a) The Texas Legislature throws a “Spear” in the Lonergan Doctrine to reduce general/subcontractor liability for owner-provided plans and specs:
Forty-nine out of the fifty states follow the Spearin Doctrine under which owners warrant the accuracy and sufficiency of owner-provided plans and specs in construction contracts. On the other hand, for over a century, Texas has followed the Lonergan Doctrine under which, absent contractual language to the contrary, a general contractor/subcontractor, instead of the owner, bears the risk of deficiencies in owner-provided design documents, once they started construction. Texas Senate Bill 219, which went into effect on September 1, 2021, finally changed that and brought Texas in line with the rest of the country, with a few exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
Frederick H. Wen, Gordon Rees Scully Mansukhani, LLPMr. Wen may be contacted at
fhwen@grsm.com
Kansas City Airport Terminal Project Faces Delays, Rising Costs
February 06, 2019 —
Kansas City Star - Engineering News-RecordCosts have long since blown past initial estimates, prompting an independent review of the price tag. Its opening is eight months behind schedule and mounting delays drew heated questions from local officials last year.
Sounds like the continuing saga of Kansas City's planned airport terminal, overwhelmingly approved by voters in November 2017 . It's actually about the new international arrivals facility under construction at Seattle-Tacoma International Airport , or Sea-Tac.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Proposed Law Protecting Tenants Amended: AB 828 Updated
June 08, 2020 —
Rhonda Kreger – Newmeyer DillionOn May 18, 2020, AB 828 was amended and is currently on its second reading in the Senate Rules Committee. This legislation proposes a temporary moratorium on foreclosures and unlawful detainers while Governor Newsom's COVID-19 emergency order is in effect. In addition to the moratorium, AB 828 also required landlords to reduce rent by 25% under certain circumstances. AB 828 was amended to remove the provision that required landlords to reduce rent by 25% for 12 months. The new provision requires landlords to allow tenant to remain in possession, and requires tenants to start paying rent the month following the end of the emergency order. Tenants must timely pay monthly rent plus 10% of any rent due and owing when the emergency order ended.
Under AB 828, a tenant may stipulate to the entry of an order in response to a residential unlawful detainer action filed by the landlord. Upon a hearing, the court determines if the tenant's inability to pay rent is the result of increased expenses or a reduction in income due to COVID-19. The court must also make a determination that there is no material economic hardship for the landlord. Upon making such determinations, the court will issue an order that permits the tenant to remain in possession, and requires tenant to commence rental payments the month following the end of the COVID-19 emergency order. Tenant's payment would include the monthly rent plus 10% of an unpaid rent during the COVID-19 emergency order, but excludes any late charges or other fees or charges. The tenant would be required to make timely payments, and if tenant fails to do so, after a 48 hour notice from landlord, the landlord can file for an immediate writ of possession in favor of the landlord and money judgment for any unpaid balance, court costs and attorneys' fees.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Is the Issuance of a City Use Permit Referable? Not When It Is an Administrative Act
January 10, 2018 —
Adam E. Lang - Real Estate Litigation BlogArizona’s Constitution gives electors in cities, towns, and counties the ability to refer legislation that was enacted by their local elected officials to the ballot for popular vote. Ariz. Const. art. IV, Pt. 1 § 1(8). But only legislative acts are referable; administrative acts are not. In general, a legislative act makes new law and creates policy, is permanent in nature, and is generally applied. On the other hand, an administrative act is one that executes and implements a law already in place. Wennerstrom v. City of Mesa, 169 Ariz. 485, 489-90, 821 P.2d 146, 150-51 (1991).
For more than fifty years, Arizona courts have been clear: zoning and rezoning ordinances are legislative acts and therefore referable to popular vote. City of Phoenix v. Fehlner, 90 Ariz. 13, 17, 363 P.2d 607, 609 (1961) (holding that “what constitutes an appropriate zone is primarily for the legislature”); Fritz v. City of Kingman, 191 Ariz 432, 432, 957 P.2d 337, 337 (1998) (noting “we reaffirm our view that zoning decisions are legislative matters subject to referendum”); Pioneer Trust Co. of Arizona v. Pima Cty., 168 Ariz. 61, 64–65, 811 P.2d 22, 25–26 (1991) (holding “that, in Arizona, zoning decisions are legislative acts subject to referendum” and that even a “conditional approval of . . . rezoning was a legislative act”); Cottonwood Dev. v. Foothills Area Coal. of Tucson, Inc., 134 Ariz. 46, 653 P.2d 694 (1982) (analyzing whether zoning referendum complied with statutory requirements); Wait v. City of Scottsdale, 127 Ariz. 107, 108, 618 P.2d 601, 602 (1980) (noting “that the enactment and amendment of zoning ordinances constitute legislative action”); City of Phoenix v. Oglesby, 112 Ariz. 64, 65, 537 P.2d 934, 935 (1975) (“The matter of zoning is appropriately one for the legislative branch of government.”); Queen Creek Land & Cattle Corp. v. Yavapai Cty. Bd. of Sup’rs, 108 Ariz. 449, 452, 501 P.2d 391, 394 (1972) (denying an attempt to enjoin referendum on county’s zoning decision).
Read the court decisionRead the full story...Reprinted courtesy of
Adam E. Lang, Snell & WilmerMr. Lang may be contacted at
alang@swlaw.com
Challenging Enforceability of Liquidated Damages (In Federal Construction Context)
March 11, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent summary judgment opinion from the Armed Services Board of Contract Appeals (ASBCA), Appeals Of – BCI Construction USA, Inc.,ASBCA No. 6257, 2024 WL 773324 (2024), contains a worthy discussion regarding a contractor’s challenge to the government’s assessment of liquidated damages, specifically the enforceability of the liquidated damages rate. Although this challenge is in the federal context, this discussion would be more expansive and apply outside of the federal context.
When dealing with the enforceability of a liquidated damages, the ASBCA “examines whether the liquidated damages amount ‘is extravagant, or disproportionate to the amount of property loss, as to show that compensation was not the object aimed at or as to imply fraud, mistake, circumvention or oppression.” Appeals of – BCI Construction USA, Inc. (citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
NYC Shuts 9 Pre-Kindergartens for Health, Safety Issues
September 03, 2014 —
Henry Goldman – BloombergNew York City won’t permit nine of 1,700 planned pre-kindergarten centers to open because of health and safety shortcomings and will delay use of 36 others for incomplete construction, officials in Mayor Bill de Blasio’s administration said.
The announcement in an e-mail from the mayor’s press office came two days before the city was to embark on de Blasio’s signature policy initiative to offer free universal pre-school to the city’s 4-year-olds starting with more than 50,000 this year and expanding to more than 70,000 next year.
The nine shuttered schools each raised health and safety concerns after they were examined by building inspectors, fire officials and the Health Department, said Wiley Norvell, a spokesman for the mayor. Of the 236 students enrolled for those locations, officials had found alternatives for 83. The city is working with parents to find other schools for the rest, Norvell said.
Read the court decisionRead the full story...Reprinted courtesy of
Henry Goldman, BloombergMr. Goldman may be contacted at
hgoldman@bloomberg.net
If I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
December 29, 2020 —
William L. Porter - Porter Law GroupIf I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
In general, the answer to the above questions is “Yes”, but only if you meet the following requirements:
- You must only release the mechanics lien itself, but not the “right” to a mechanics lien: There is an important distinction to be made between releasing a mechanics lien and releasing the right to a mechanics lien. Whether you do one or the other will depend on the specific language used in your release. In the case of Santa Clara Land Title Co. v. Nowack and Associates, Inc. (1991) 226 Cal. App.3d, 1558 a “release of mechanics lien” document was recorded TO THE County Recorder’s office which included a statement that the mechanics lien was “fully satisfied, released and discharged”. Based on this language, the court concluded that the mechanics lien claimant had waived its “right” to a further mechanics lien on the same property for the work in question. The court concluded that since the release stated that the claim was “fully satisfied” the right to mechanics lien on the project had forever been waived. The Nowak case can be distinguished from the case of Koudmani v. Ogle Enterprises, Inc., (1996) 47 Cal.App.4th 1650, where the release of mechanics lien only stated that the mechanics lien was “otherwise released and discharged” and not that it was “satisfied”. Based on the distinction drawn from the two cases, a simple mechanics lien release that only releases the mechanics lien itself, but not the “right” to a mechanics lien should be used. At the following link you will find a proper form to achieve this purpose: https://www.porterlaw.com/wp-content/uploads/2019/06/03PRI-Mechanics-Lien-Release.pdf
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Insurer Must Pay Portions of Arbitration Award Related to Faulty Workmanship
October 21, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that portions of an arbitration award against the insured contractor based upon faulty workmanship were covered by the policy. Wallace v. Nautilus Ins. Co., 2019 U.S. Dist. LEXIS 122219 (D. N. H. July 23, 2010).
Plaintiffs, owners of adjoining homes, hired McPhail Roofing, LLC to replace the roofs of their houses. After installation, the plaintiffs found several problems with their roofs and withheld roughly a third of the agreed-upon contract price from final payments due to McPhail. A roofing consultant found evidence of water leaking through both roofs during rainstorms. Improper installation of the shakes on the roofs allowed rain to seep through to the roof decks (the plywood underneath the roofs) and eventually into the houses. The only way to cure the installation defects was to remove and replace the roofs entirely.
Plaintiffs and McPhail went to arbitration. Plaintiffs sought compensation for the damage caused by the leaking and for the replacement costs of the roofs. McPhail sought the remaining payment under the contracts. Nautilus defended McPhail under this CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com