Rhode Island Examines a Property Owner’s Intended Beneficiary Status and the Economic Loss Doctrine in the Context of a Construction Contract
March 18, 2019 —
Shannon M. Warren - The Subrogation StrategistIn Hexagon Holdings Inc. v. Carlisle Syntec, Inc. No. 2017-175-Appeal, 2019 R.I. Lexis 14 (January 17, 2019), the Supreme Court of Rhode Island, discussing claims associated with allegedly defective construction, addressed issues involving intended beneficiaries to contracts and the application of the economic loss doctrine. The court held that, based on the evidence presented, the building owner, Hexagon Holdings, Inc. (Hexagon) was not an intended third-party beneficiary of the subcontract between the general contractor (A/Z Corporation) and the subcontractor, defendant McKenna Roofing and Construction, Inc. (McKenna). In addition, the court held that, in the context of this commercial construction contract, the economic loss doctrine applied and barred Hexagon’s negligence claims against McKenna.
Approximately nine years after Hexagon entered into a contract with A/Z Corporation for the construction of a building, Hexagon filed suit against A/Z Corporation’s roofing installation subcontractor, McKenna, and the manufacturer of the roofing system. Hexagon alleged that the roof began to leak shortly after McKenna installed it. Notably, Hexagon did not sue A/Z Corporation.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and WilliamsMs. Warren may be contacted at
warrens@whiteandwilliams.com
Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)
August 11, 2011 —
Melissa Brumback, Construction Law in North CarolinaFor today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction. Dave writes:
I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.
The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS Announces Updated Construction Rules
June 21, 2021 —
JAMSIrvine, Calif. – JAMS, the largest private provider of
alternative dispute resolution (ADR) services worldwide, is pleased to announce it has revised and updated its
Construction Arbitration Rules & Procedures and
Expedited Construction Arbitration Rules & Procedures, effective June 1. These Rules were updated to reflect the latest developments and trends in
construction arbitration.
In response to the transition to virtual and hybrid proceedings, Rule 22 makes explicit the arbitrator’s full authority to conduct the hearing in person, virtually or in a combined form, as well as with participants in more than one geographic location. To support access to case documents throughout the proceedings, Rule 8 aligns electronic filing and service with the functionality of JAMS Access, a centralized, secure online case management platform.
Additional rules were created or revised to clarify and strengthen the authority of the arbitrator. Key changes include allowing an arbitrator to withhold approval of any intended change in party representation that could compromise the proceedings or the final award, to set a hearing without consulting a party that he or she reasonably believes will not participate and to permit a party to file a motion for summary disposition of a claim if the arbitrator believes that party has demonstrated the motion is likely to succeed.
About JAMS – Local Solutions. Global Reach.
Founded in 1979, JAMS is the largest private provider of alternative dispute resolution services worldwide. JAMS successfully resolves and manages business and legal disputes by providing efficient, cost-effective and impartial ways to overcome barriers at any stage of conflict. JAMS offers customized in-person, virtual and hybrid resolution services locally and globally through a combination of industry-specific experience, first-class client service, the latest technology and highly trained mediators and arbitrators.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida extends the Distressed Condominium Relief Act
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Distressed Condominium Relief Act had been poised to expire on July 1st, but has now been extended by two additional years by the Florida legislature, the National Review reported. The act was Part VII of the Condominium Act in 2010, and has been previously extended twice. According to the National Review, “This Legislation attempted to allay the fears of potential investors about incurring developer liability in connection with the purchase of bulk units. The Act created a shield in favor of bulk purchasers from such potential liability, especially construction defects liability.”
Read the court decisionRead the full story...Reprinted courtesy of
Coronavirus and Contract Obligations
March 30, 2020 —
David R. Cook - AHC Construction and Procurement BlogThe Coronavirus (COVID-19) pandemic has caused a global disruption to businesses, causing many to temporarily close and lay off employees. As businesses assess the short– and long–term economic impact of COVID-19, they should also evaluate what contractual obligations and remedies are available under various agreements (e.g., leases, vendor agreements, and supply agreements). When performance may be delayed or may not occur altogether, businesses should consider their force majeure clauses, if any, and the doctrines of impossibility, impracticability, and frustration of purpose.
Force Majeure
Generally, unless a contract provides that performance will be suspended or relieved when certain events occur (e.g., “acts of God,” government regulation, acts of war or terror, strikes), each party is obligated to perform. However, when there is an express force majeure provision, certain events or acts may excuse non-performance or delayed performance. But depending on the jurisdiction, courts may construe force majeure provisions narrowly and excuse performance only for those events expressly listed in the clause. Nonetheless, if the force majeure provision includes pandemic, epidemic, quarantine, government act, disease, or similar terms, then the COVID-19 pandemic may excuse performance or allow delayed performance.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
First Circuit: No Coverage, No Duty to Investigate Alleged Loss Prior to Policy Period
May 18, 2020 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsOn April 1, 2020, the First Circuit, applying Massachusetts law, issued a potentially useful decision addressing the Montrose “known loss” language in ISO Form CGL policies. In Clarendon National Insurance Company v. Philadelphia Indemnity Insurance Company,[1] the court applied this language to allow denial of defense for claims of recurring water infiltration that began before the insurer’s policy period, and it found an insurer had no duty to investigate whether the course of property damage might have been interrupted, or whether other property damage might have occurred during the policy period, so as to trigger coverage during a later policy.
In the underlying dispute, a condominium owner (Doherty) asserted negligence claims against her association’s property management company (Lundgren) stemming from alleged water infiltration into her condominium. The complaint said leaks developed in 2004 in the roof above Doherty’s unit, and repairs were not made in a timely or appropriate manner. The following year, the complaint said, a Lundgren employee notified Doherty that the threshold leading to her condominium's deck was rotting. In February 2006, Doherty discovered a mushroom and water infiltration on the threshold and notified Lundgren. At that time, Lundgren asked its maintenance and repair contractor (CBD) to replace the rotting threshold. According to the complaint, CBD did not do this repair in a timely manner and left debris exposed in Doherty’s bedroom.
In March 2006, the complaint said, a mold testing company hired by Lundgren found hazardous mold in Doherty's unit, caused by water intrusions and chronic dampness. Lundgren’s attempts at remediation were ineffectual. In September 2008, Doherty's doctor ordered her to leave the condominium and not to return until the leaks were repaired and mold was eliminated.
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
LEEDigation: A Different Take
June 22, 2020 —
Christopher G. Hill - Construction Law MusingsThis weeks Guest Post Friday at Musings is a real treat. Sara Sweeney is a registered architect, LEED AP and GreenFaith Fellow in religious environmental leadership. Her 18-year architectural career reflects her passion and commitment to sustainable building design and stewardship of our natural environment. She is the founder of EcoVision LLC, a solutions-based research and consulting firm, grounded in sustainable design practices, environmental stewardship, and building science.
Dude
Every so often I come across a word that drives me nuts. A few years ago it was ‘Dude.’ Lately, it is ‘LEEDigation.’ It’s a new term to “describe green building litigation” coined by Chris Cheatham, a fine person and very knowledgeable attorney in construction law and a LEED AP as well. Per his definition, LEEDigation “could involve disputes arising from green building certification, could arise if a project fails to obtain government incentives or satisfy mandates for green building construction, or could simply result from improperly designed or constructed green building strategies. It all makes sense. So why does it drive me nuts?
Round Peg. Square Hole.
Although I fully understand why the term was coined, such a term keeps us in flat world, that is, the world of conventional design and construction. Designing and building to LEED standards, or rather, just designing and building sustainably in general, whether to meet a third party standard or not, is a different way than what we have been used to. Period. Whereas our conventional way is focused on first costs, and sees the building more as a commodity than the human imprint and legacy on Earth, sustainable design and building is a process which, at its best, considers the economic impacts of NOT building responsibly. It is a more holistic way of building and balances long-term costs and implications with short term costs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com