MGM Begins Dismantling of the Las Vegas Harmon Tower
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFMGM has begun to dismantle the $8.5 billion, incomplete Harmon Hotel in Las Vegas, Nevada, according to the Las Vegas Review-Journal. The demolition process is expected to take up to a year.
The Las Vegas Review-Journal reported that construction of the tower was halted in 2008 after construction defects were allegedly discovered. Later, “the building was deemed structurally unsound.”
“Instead of blowing the building up in grand fashion, contractors hired by MGM Resorts are now removing scrap metal and other materials from the building, along with taking off the blue-tinged glass that has covered the structure for the last five years,” Howard Stutz wrote in the Las Vegas-Review Journal. “The process also includes installing pedestrian protection systems outside the structure above adjacent sidewalks and walkways.”
Read the court decisionRead the full story...Reprinted courtesy of
Arbitration Clause Found Ambiguous in Construction Defect Case
October 28, 2011 —
CDJ STAFFThe California Court of Appeals ruled on September 28 in the case of Burch v. Premier Homes. Ms. Burch bought a home after negotiating various addendums to the contract. The contract was a standard California Association of Realtors contract to which both the buyer and seller made additions. At issue in this case was paragraph 17 of the contract which included that “Buyer and Seller agree that any dispute or claim in Law or equity arising between them out of this Agreement or resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.”
The seller/defendant’s Addendum 2 “included provisions relating to the arbitration of disputes that may arise.” Ms. Burch’s realtor, Lisa Morrin, told Burch that “she had never seen a proposed contractual provision that would require a home buyer to agree to arbitrate with a builder over construction defects.” Ms. Burch told Morrin that she did not want to buy the property if she would have to give up her rights under California law.
As part of Addendum 2, the buyer had to buy a warranty from the Home Buyers Warranty Corporation. The sale was held up for a while, as Ms. Burch waited for a copy of the warranty. When she received it, she took further exception to Addendum 2. Scott Warren of Premier Homes said he could not sell the property without Addendum 2. Ms. Burch told her realtor that despite the claims made by Mr. Warren that this was for her benefit, she felt it was more to the benefit of Premier Homes. Don Aberbrook of HBW agreed to the clause, contained in the final sentence of Addendum 2, being struck.
Subsequent to buying the home, Burch submitted a claim concerning construction defects. HBW denied the claim and Burch began an action against the defendants. Premier filed a motion to compel arbitration which Burch opposed.
The trial court ruled that the striking out of the arbitration clause at the end of Addendum 2 “created a conflict with respect to the parties’ intent as to the scope of arbitration.” The trial court found that “the parties’ intention was to preserve Burch’s right to make state law claims including her right to a jury trial for any non-warranty claims against the builder.”
The appeals court in their ruling looked at the standard of review and concluded that the purchase agreement was ambiguous and that extrinsic evidence was required to resolve that ambiguity. As the contract contained contradictory provisions as to whether or not arbitration was required, it was necessary for the trial court to examine these claims. The appeals court found that the evidence supported the conclusions of the trial court.
Finally, the appeals court found that “there was no valid agreement to arbitrate disputes.” The court noted that arbitration can only happen by mutual consent and “it is clear that Burch did not enter into an agreement to arbitrate any construction defect disputes she might have.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Home Prices in 20 U.S. Cities Increase at Slower Pace
February 25, 2014 —
Victoria Stilwell – BloombergHome prices in the U.S. climbed at a slower pace in the year through December, pointing to a moderation in the market that will help keep more properties within reach for prospective buyers.
The S&P/Case-Shiller index of property values in 20 cities rose 13.4 percent from December 2012 after increasing 13.7 percent in the year ended in November, the group said today in New York. It was the first deceleration since June. The gain matched the median estimate of 33 economists surveyed by Bloomberg.
Price appreciation is slowing as rising mortgage rates combined with harsh winter weather to cool home purchases over the past few months. Smaller increases mean more homes will remain affordable as the labor market improves, helping maintain the rebound in residential real estate that has boosted growth.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Defense Victory in Breach of Fiduciary Action
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFEarlier this month, Scott Calkins and Anthony Gaeta of Collinsworth, Specht, Calkins & Giampaoli, LLP obtained a defense verdict in a breach of fiduciary duty action involving a high-rise condominium in downtown San Diego, California. The Association asked for excess of over $3 million, however, the jury returned with a 10-2 defense verdict in favor of K. Hovnanian.
Cortez Blu Community Association, Inc. v. K. Hovnanian at Cortez Hill, LLC, et al. initially involved construction defect claims against the developer, K. Hovnanian, and the general contractor, Turner Construction, as well as a claim of breach of fiduciary duty. However, the construction defect claims settled prior to trial leaving only the breach of fiduciary claim.
“While it is now becoming ever more common for attorneys representing homeowners associations to allege a breach of fiduciary duty by the developer, there has been little actual litigation of the issues surrounding those claims which test the viability of the allegations or the defenses to them,” defense attorney Anthony Gaeta stated. “A breach of a fiduciary duty by a developer, which is demonstrated to damage the viability of an HOA either to perform regularly scheduled maintenance, or replace building components from its reserves, has the potential in economic terms to surpass the damages from purported construction defects.
The Plaintiff argued that K. Hovnanian breached its fiduciary duty to the Association by failing to set adequate reserves within the initial Department of Real Estate budget (“DRE”) for painting, caulking, and power washing the exterior of the building, referencing Raven’s Cove Townhomes, Inc. v. Knuppe Development Co., Inc. (1981) 114 Cal. App. 3d 783. In response, K. Hovnanian stated that in part, the initial reserves as set forth in the DRE budget were adequate, good faith estimates and, therefore, there was no liability for breach of fiduciary duty.
“Our case was exclusively concerned with the duties of the developer when forming the initial HOA, preliminary budgets, and reserves,” Gaeta said. “We litigated the duties and responsibilities of the initial board and whether a developer may rely on reports prepared by third-parties during the formation of a common interest development. The jury found our client’s actions and reliance on third-parties was reasonable and, thus, no breach of fiduciary duty occurred.”
Collinsworth, Specht, Calkins & Giampaoli is a general civil litigation firm representing clients throughout California and Arizona. You may learn more about the firm at www.cslawoffices.com
Read the court decisionRead the full story...Reprinted courtesy of
The New “White Collar” Exemption Regulations
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorThis summer the Department of Labor’s Wage and Hour Division issued proposed changes to the white-collar overtime regulations under the Fair Labor Standards Act (FLSA). The white collar exemptions include the executive, administrative, professional, outside sales and computer employee exemptions. The focus of the proposed regulations is to increase the salary level required to qualify for the exemption from $23,660 per year to $50,440 per year. The DOL predicts this will cause employers to change the exempt status of nearly 5 million workers who are currently exempt from overtime requirements to non-exempt status – requiring the payment of overtime.
Current Regulations
Under today’s regulations, the white collar exemption applies to employees who are paid at least $455 per week ($23,660 per year) and who customarily and regularly perform any one or more of the exempt duties or responsibilities of an executive, administrative or professional employee.
Proposed Changes
The most significant change is the sizeable increase in the minimum salary requirements for the exemptions. The proposed regulations more than double the current minimum salary of $455 per week to $921. This corresponds to the 40th percentile of weekly earnings projected for the first quarter of 2016, based on the Bureau of Labor Statistics. The DOL also proposes annual adjustments to the minimum salary requirements.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Hawaii Supreme Court Finds Climate Change Lawsuit Barred by “Pollution Exclusion”
November 05, 2024 —
Jason Taylor - Traub Lieberman Insurance Law BlogOn October 7, 2024, the Hawaii Supreme Court answered the question of whether an “accident” includes an insured’s reckless conduct in emitting harmful greenhouse gases (“GHGs”) and whether such emissions are “pollutants” as defined in a general liability policy’s pollution exclusion. In Aloha Petro., Ltd. v. National Union Fire Insurance Co. of Pitt., PA, No., 2024 Haw. LEXIS 179 (Oct. 7, 2024), the Hawaii Supreme Court answered in the affirmative as to both certified questions from the United States District Court for the District of Hawaii, holding that an insured’s reckless conduct can be an “accident” and that GHGs are “pollutants” under the policies’ pollution exclusions.
In the underlying case, the County of Honolulu and the County of Maui (the “Counties”) sued Aloha Petroleum, Ltd. (“Aloha”) and several other fossil fuel companies for climate change-related harms. Namely, the Counties alleged that the fossil fuel industry knew that its products would cause catastrophic climate change, and rather than mitigating their emissions, defendants concealed such knowledge, promoted climate science denial, and increased their production of fossil fuels. Aloha was allegedly on notice that its products caused harmful climate change through its former parent company, Phillips 66, and its current parent company, Sunoco. Given this knowledge, the District Court determined that the Counties allegations constituted reckless conduct by Aloha.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Contractor Covered for Voluntary Remediation Efforts in Completed Homes
October 10, 2013 —
Tred Eyerly — Insurance Law HawaiiThe Texas Supreme Court held that a home builder was covered for the voluntary removal and replacement of a defective insulation product it had installed in hundreds of homes. Lennar Corp. v. Market Am. Ins. Co., 2013 Tex. LEXIS 597 (Tex. Sup. Ct. Aug. 23, 2013).
Lennar built homes using an exterior insulation and finish system (EIFS). It was subsequently determined that EIFS trapped water inside homes with wood-frame walls, causing rot and structural damage, mildew and mold, and termite infestation. Lennar decided to contact all its homeowners and offer to remove the EIFS and replace it with conventional stucco.
Lennar notified its insurers that it would seek indemnification for the costs. The insurers refused to participate in Lennar's proactive efforts, preferring to wait and respond to homeowners' claims one by one.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com