Jeffrey S. Wertman - Construction ExecutivePart I of this series discussed the benefits of construction participants using alternative project delivery methods and properly addressing change order issues, rising costs and payment structure issues to manage construction during these uncertain times. Part II below explores the possibility that higher prices and steady consumer demand could lead to an increase in unscrupulous contractor practices—and how owners can mitigate that risk, managing the challenges posed by the unforeseen labor shortage and turnover in the industry and evolving your construction team for short-term and long-term success.
Higher Prices and Steady Demand
With the demand for construction projects relatively stable, contractors remaining in high demand and a surge in prices for construction materials and components, owners are under great pressure to accept less favorable construction terms. This has presented unscrupulous contractors with perceived leverage over owners and new opportunities to engage in questionable business practices and fraud. Although some contractors may seek to stretch the boundaries of a construction contract, other contractors are more deliberate. Falsifying payment applications and invoices to inflate labor or materials costs, billing for work not yet performed or materials not yet delivered to the project site and manipulating change orders are examples of illicit and fraudulent practices by contractors.
Reprinted courtesy of
Jeffrey S. Wertman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
No Additional Insured Coverage Under Umbrella Policy
March 12, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured was not covered under a property policy for an injury occurring after work was completed. Lewark v. Davis Door Servs., 2014 Wash. App. LEXIS 341 (Wash. Ct. App. Feb. 10, 2014).
Public Storage, Inc. hired Davis Door Service Inc. to perform work at its facilities. The master agreement required Davis Door to maintain a CGL policy that insured Public Storage "during the entire progress of the work." Davis Door secured a CGL policy with American Economy. It also took out an umbrella liability policy with American States.
After Davis Door completed work on a door, Terrie Lewark injury her back opening the door. She sued Public Storage and Davis Door. Lewar and Public Storage settled. Public Storage assigned to Lewark its rights under the umbrella policy with American States. Lewark then sued Davis Door and American States. The trial court found that Public Storage was not an additional insured under the American States umbrella policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Labor Intensive
May 10, 2022 —
Neil Flynn - Construction ExecutiveIn 2020, the United States saw a significant decrease in non-fatal workplace injuries, which dropped to 2.1 million from 2.8 million the year before. While the precise extent to which this reduction in workplace injuries is attributable to COVID-19 is unknown, the pandemic was undoubtedly a significant factor. It is also unclear to what extent the pandemic affected the number and rate of workplace incidents in 2021 or might continue to do so in 2022 and beyond.
However, it is reasonable to expect that, as pandemic-related restrictions are removed and life returns to normal, the construction industry will revert to pre-pandemic employment levels and beyond. It is also reasonable to conclude that, once that level of recovery is attained, the number and rate of both fatal and non-fatal workplace incidents will increase substantially.
Even with the significant reduction in the overall number of workplace injuries in 2020, the United States still saw nearly 8,000 construction workers miss at least one day of work due to an injury sustained on the job, according to the U.S. Bureau of Labor Statistics (BLS). And, despite construction accounting for just 6% of jobs, BLS reports that construction-related incidents account for 20% of workplace deaths, or three every day. This one-fifth share of workplace fatalities makes construction the third-deadliest industry in the United States.
Reprinted courtesy of
Neil Flynn, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Flynn may be contacted at
nf@plattalaw.com
Idaho District Court Affirms Its Role as the Gatekeeper of Expert Testimony
March 15, 2021 —
Melissa Kenney - The Subrogation SpecialistMany subrogation claims involving fire losses rely heavily on expert testimony. Expert testimony is admissible under Federal Rule of Evidence 702 if it is both relevant and reliable. In Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579 (1993), whose standard has been incorporated into Federal Rule of Evidence 702, the Supreme Court instructed federal trial courts to act as a “gatekeeper” of expert testimony, giving them the power to exclude expert testimony that is not supported by sufficient evidence. In Maria Fernanda Elosu and Robert Luis Brace v. Middlefork Ranch Incorporated, Civil Case No. 1:19-cv-00267-DCN, 2021 U.S. Dist. LEXIS 14449 (D. Idaho Jan. 22, 2021) (Brace), the United States District Court for the District of Idaho exercised its gatekeeper role when it granted in part and denied in part the defendant’s motion to exclude expert testimony pursuant to Daubert and Federal Rule of Evidence 702.
Brace, involved a fire at a vacation cabin in McCall, Idaho. The cabin, owned by Maria Elosu (Elosu) and Robert Brace (Brace and collectively with Elosu, Plaintiffs) was part of a homeowner’s association called Middlefork Ranch, Incorporated (MFR). The cabin had a “wrap around” deck with a propane-fired refrigerator on the north side. On the day before the fire, Brace stained the deck using an oil-based stain. That night, Elosu smoked cigarettes on the deck. The next morning, Plaintiffs used rags to clean up excess oil from the deck and an MFR employee changed the propane on the refrigerator and relit the pilot light. At 4:00 p.m., a fire started in or around the cabin while no one was home. The fire was discovered by a group of contractors who testified that the fire was isolated to the east side of the cabin when they first arrived. Importantly, one witness testified that there was no fire and no flames around the propane-fired refrigerator. The fire destroyed the cabin and the contents within.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Kenney, White and Williams LLPMs. Kenney may be contacted at
kenneyme@whiteandwilliams.com
Construction Defects Lead to Demolition of Seattle’s 25-story McGuire Apartments Building
March 16, 2011 —
CDJ STAFFAccording to a story published last Thursday in Seattle PI: " The 25-story McGuire Apartments, at Second Avenue and Wall Street, would cost more to fix than the building is worth, according to its owners. Its most serious defect involves steel cables that are corroding inside of concrete slabs because the ends weren’t properly treated with a rust-proof coating and a pocket in the edge of the concrete that wasn’t properly sealed"
The report by Aubrey Cohen outlines the demolition plans which are expected to take between 12 and 18 months, and will utilize robotic Brokk Machines. The demolition plan calls for one story at a time to be demolished, with the debris to be trucked offsite. Demolition plans aim to minimize disruption to residents and businesses in the area by Limiting work 7 a.m. to 6 p.m. on weekdays and 9 a.m. to 6 p.m. Saturdays with "impact and percussive activities" limited to 8 a.m to 5 p.m weekdays.
Read More...
Read the court decisionRead the full story...Reprinted courtesy of
Relying Upon Improper Exclusion to Deny Coverage Allows Bad Faith Claim to Survive Summary Judgment
December 04, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer was successful on summary judgment in establishing it correctly denied coverage for collapse, but its motion was denied regarding the insureds' bad faith claim. Jones v. State Farm Fire & Cas. Co., 2018 U.S. Dist. LEXIS 153102 (W.D. Wash. Sept. 7, 2018).
The insureds' retaining wall collapsed. They tendered to State Farm under their homeowners policy. An engineer retained by State Farm determined that the wall buckled due to "excessive lateral earth pressure from retained soils behind the wall." The parties agreed that the soil, saturated by water from frequent rain, grew too heavy for the retaining wall to bear, causing the collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York State Legislature Passes Legislation Expanding Wrongful Death Litigation
July 18, 2022 —
Lisa M. Rolle & Justyn Verzillo - Traub LiebermanIn early June, New York State Legislature passed legislation, often referred to as “The Grieving Families Act” (A.6770/S.74-A), which expands New York’s Wrongful Death Statute. This legislation is pending approval from Governor Kathy Hochul and has the ability to drastically impact wrongful death litigation by expanding how parties can bring an action, as well as expanding on recoverable compensation.
Pursuant to the existing statute (EPTL §5-4.1), the statute of limitations requires commencement of an action within two years after the decedent’s death. The proposed Grieving Families Act expands the statute of limitations for a wrongful death action to three years and six months after the decedent’s death.
Further, under the existing statute (EPTL §11-3.3), recovery in a wrongful death action is restricted to distributees (the intended beneficiaries under the will). The proposed legislation expands the parties permitted to bring a wrongful death action, replacing the term distributees with surviving close family members. These may include, but are not limited to, spouse or domestic partner, issue, parents, grandparents, step-parents, and siblings, leaving it to the finder of fact to determine which persons are close family members of the decedent based upon the specific circumstances relating to the person’s relationship with decedent. It remains to be seen what the burden of proof will be for the surviving close family members, as well as what process will be instituted with respect to the finder of fact. Presumably, the finder of fact will be a Judge.
Reprinted courtesy of
Lisa M. Rolle, Traub Lieberman and
Justyn Verzillo, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Verzillo may be contacted at jverzillo@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Bidder Be Thoughtful: The Impacts of Disclaimers in Pre-Bid Reports
August 04, 2021 —
Joshua A. Morehouse - ConsensusDocsWhen bidding a project, subsurface or latent site conditions that are not immediately apparent can massively impact the costs of performance to general contractors. Were contractors required to bid on projects without any information on pre-existing conditions, they would need either to be assured that any additional costs would be reimbursed by the owner, or to include significant contingencies for subsurface conditions in their bids. For owners, these options result in either increased risk or increased cost—neither of which is particularly palatable. Owners therefore implement several contractual tools to minimize these risks and costs.
One of these tools is providing bidders with a report on latent conditions, often called a “geotechnical data report” or “GDR”, but otherwise shifting as much of the subsurface-related risk as possible to the contractor. In theory, these reports permit contractors to appropriately adjust their contingencies for latent conditions, thus saving owners money. However, several independent and thorny issues arise where site reports provided by the owner are either inconsistent with or silent on the actual conditions of a project site. Hence owners often include disclaimers with these reports, such as noting that the report is for “informational purposes only” or that the report is “not part of the contract documents."
Read the court decisionRead the full story...Reprinted courtesy of
Joshua A. Morehouse, Peckar & Abramson, P.C.Mr. Morehouse may be contacted at
jmorehouse@pecklaw.com