Employee Exclusion Bars Coverage for Wrongful Death of Subcontractor's Employee
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Fifth Circuit determined the deceased was a statutory employee of the general contractor under Florida law, thereby barring coverage for the general contractor. Stephens v. Mid-Continent Casualty Co., 2014 WL 1623737 (11th Cir. April 24, 2014).
The decedent fell from a ladder while working to install a modular home. Critically injured, he died on the way to the hospital. The decedent was an employee of Team Fritz, a subcontractor hired to set the modular home on its foundation.
The general contractor, Anchorage Homes LLC, had a liability policy with Mid-Continent. Damages relating to injuries to any of Anchorage's employees were excluded under the policy. Mid-Continent denied coverage contending that under Florida law, Team Fritz's employees were "statutory employees" of Anchorage. The law provided that the employees of a subcontractor were deemed to be employees of the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
“But I didn’t know what I was signing….”
May 30, 2018 —
Bobby Kethcart - Snell & Wilmer Real Estate Litigation BlogIn real estate cases—which frequently involve long purchase agreements, loan documents, personal guarantees, deeds of trust, etc.—we’ve likely all had a client or opposing party who trots out the line that they didn’t know what they were signing, or they didn’t read or understand what they were signing, so the document shouldn’t be enforced according to its terms.
Most of us instinctively believe the claim is a loser: You signed the document, you’re bound by it.
But is this actually right?
Well, we did some digging. Here is the Arizona law on the subject:
Nationwide Resources Corp. v. Massabni, 134 Ariz. 557, 658 P.2d 210 (App. 1982):
“A mistake of only one of the parties to a contract in the expression of his agreement or as to the subject matter does not affect its binding force and ordinarily affords no ground for its avoidance, or for relief, even in equity.”
“A manifestation of acceptance to the offeror or his agent forms a contract regardless of the intent of the acceptor.”
Read the court decisionRead the full story...Reprinted courtesy of
Bobby Kethcart, Snell & WilmerMr. Kethcart may be contacted at
rkethcart@swlaw.com
2017 Legislative Changes Affecting the Construction Industry
November 21, 2017 —
Melinda S. Gentile – Peckar & Abramson, P.C.Originally published by CDJ on July 13, 2017
The 2017 Florida Legislative Session recently concluded, and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session, most notably SB 204/HB 377. These Bills may impact General Contractors and Construction Managers in a number of ways, not the least of which is the period of time that a cause of action may be initiated for the design, planning or construction of an improvement.
The following construction-related Bills passed in both the House and Senate and will become law if approved by the Governor.
Senate Bill (SB) 204/House Bill (HB) 377: Relating to the Statute of Repose for causes of action based on design, planning or construction of an improvement to real property. This bill passed both the House and the Senate and was approved by the Governor on June 14, 2017. This bill becomes effective on July 1, 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
Real Estate & Construction News Roundup (10/18/23) – Zillow’s New Pilot Program, Production Begins at Solar Panel Plant in Georgia, and More Diversity on Contracts for Buffalo Bills Stadium
November 27, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, Netflix announces plans to open brick-and-mortar locations, NYU develops a way to examine buildings using drones, robots and AI, distressed U.S. commercial real estate hits a 10-year high, and more!
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Colorado Springs may be Next Colorado City to Add Construction Defects Ordinance
October 28, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Gazette reported that Colorado Springs city councilwoman Jill Gaebler stated that “she would bring a proposal to the council next month that would address the construction defects issue.”
Gaebler told The Gazette: “We have gone back and forth with how best to address this issue. It is a statewide concern, so how do we bring forward something that is meaningful to our community without stepping on the toes of our legislators?”
The state of Colorado has tried and failed to pass construction defects legislation three years in a row, according to The Gazette. If Colorado Springs adopts an ordinance, it will become the ninth city to pass construction defects laws.
Read the court decisionRead the full story...Reprinted courtesy of
Triple Points to the English Court of Appeal for Clarifying the Law on LDs
July 01, 2019 —
Vincent C. Zabielski & Julia Kalinina Belcher - Gravel2GavelCan an employer recover liquidated damages (LDs) from a contractor if the contract terminates before the contractor completes the work?
Surprisingly, heretofore, English law provided no clear answer to this seemingly straightforward question, and inconsistent case law over the past century has left a trail of confusion. Given the widespread use of English law in international construction contracts, this uncertainty had gone on far too long.
The good news is that drafters of construction contracts throughout the world can now have a well-deserved good night’s sleep courtesy of the English Court of Appeal’s March 2019 decision in Triple Point Technology, Inc. v PTT Public Company Ltd [2019] EWCA Civ 230.
The Triple Point case concerned the delayed supply by Triple Point (the “Contractor”) of a new software system to employer PTT. The contract provided for payments upon achievement of milestones, however order forms incorporated into the contract set out the calendar dates on which fixed amounts were payable by PTT, resulting in an apparently contradictory requirements on when payment was due. Triple Point achieved completion (149 days late) of a portion of the work milestones, and were paid for that work. Triple Point then sought payment for the work which was not yet completed, relying on the calendar dates in the order forms rather than achievement of milestone payments. Things got progressively worse as PTT refused payment, Triple Point suspended the work for PTT’s failure to pay, PTT terminated the contract and then appointed a new contractor to complete the work.
Reprinted courtesy of
Vincent C. Zabielski, Pillsbury and
Julia Kalinina Belcher, Pillsbury
Mr. Zabielski may be contacted at vincent.zabielski@pillsburylaw.com
Ms. Belcher may be contacted at julia.belcher@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Mechanics’ Lien “Waivers” and “Releases”: What’s the Difference?
March 19, 2015 —
Thomas C. Rogers – White and Williams LLPIn the world of Pennsylvania mechanics’ liens there is much confusion about the interchangeable use of the words mechanics lien “waiver” and mechanics’ lien “release.” Many who work in the world of real estate in Pennsylvania, be they contractors, subcontractors, developers, lenders, or attorneys, use these terms interchangeably without understanding that there is a meaningful difference. Failure to understand the difference creates confusion when discussing issues and drafting documents regarding mechanics’ liens.
In Pennsylvania a mechanics’ lien “waiver” is the pre-construction waiver of liens that was historically executed by a general contractor and an owner and filed with the Prothonotary in the county in which construction is located. These pre-construction lien “waivers,” assuming they were properly prepared, signed by the contractor and owner and filed in accordance with applicable law, negated the ability of that contractor and its subcontractors to file a mechanics’ lien on the subject property. These pre-construction lien “waivers” were part of every construction loan closing up through the amendments to the Pennsylvania Mechanics’ Lien Act that went into effect in 2007. Since 2007, the Mechanics’ Lien Act has been amended twice to further address those circumstances in which pre-construction lien waivers still have vitality. Except with respect to those narrow situations specifically provided for in the statute, pre-construction lien “waivers” are against public policy in Pennsylvania.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas C. Rogers, White and Williams LLPMr. Rogers may be contacted at
rogerst@whiteandwilliams.com
House Bill Clarifies Start Point for Florida’s Statute of Repose
September 14, 2017 —
Lian Skaf - White and Williams LLPThe Florida legislature recently enacted a law clarifying when the ten-year statute of repose begins to run for cases involving “improvements to real property,” as that phrase is used in Florida Statute Section 95.11. House Bill 377 was signed into law on June 14, 2017 and took effect in all cases accruing on or after July 1, 2017. This amendment is significant to subrogation professionals evaluating when cases involving contractors and design professionals are time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com