Nevada Supreme Court Reverses Decision against Grader in Drainage Case
June 30, 2011 —
CDJ STAFFThe Nevada Supreme Court has issued an opinion in the case of Rayburn Lawn & Landscape Designers v. Plaster Development Corporation, reversing the decision of the lower court and remanding the case for a new trial.
The case originated in a construction defect suit in which Plaster Development Corporation was sued by homeowners. Plaster filed a third-party complaint against its subcontractor, Reyburn. The testimony of Reyburn’s owner was considered to be admission of liability and so the court limited the scope of Reyburn’s closing argument and did not allow the jury to determine the extent of Reyburn’s liability. Reyburn appealed.
Plaster, in their case, cited California’s Crawford v. Weather Sheild MFG, Inc. The court held the application of these standards, but noted that the “an indemnitor’s duty to defend an indemnitee is limited to those claims directly attributed to the indemnitor’s scope of work and does not include defending against claims arising from the negligence of other subcontractors and the indemnittee’s own negligence.”
On the matter of law against Reyburn, the court concluded, “Given the conflicting evidence at trial as to whether Reyburn’s work was implicated in the defective retaining walls and sidewalls, and viewing the evidence and inferences in Reyburn’s favor, we conclude that a reasonable jury could have granted relief in favor of Reyburn.” The Nevada Supreme Court conduced that the district court should not have granted Plaster’s motion for judgement.
Further, the Nevada Supreme Court found that the district court should have apportioned the fees and costs to those claims directly attributed to Reyburn’s scope of work, “if any,” and should not have assigned all attorney costs and court fees to Reyburn.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Home Sellers Return for Spring as Buyers Get Relief
February 10, 2014 —
Prashant Gopal – BloombergSuzanne Baker and her siblings bought a foreclosed home in Atlanta two years ago, added a fourth bathroom, then waited for values to rebound before considering a sale. Now, she says, they’re ready to cash in.
The family last month listed the four-bedroom house in the affluent Buckhead neighborhood for $710,000. It was purchased as an investment for about $375,000 in late 2011, before bulk buyers snapped up many of the area’s distressed homes, helping to drive up prices in Atlanta by more than 25 percent.
“The market is back up,” Baker said. “We think we can make a good amount of profit so we’re going to try.”
For two years, a shortage of sellers like the Bakers has propped up prices across the U.S. as shoppers jostled for a dwindling supply of houses. Now, as the market’s busiest season approaches, escalating values are spurring more listings as homeowners regain equity lost in the worst crash since the 1930s. While new-home construction at a third of its 2006 peak will keep inventory tight, the supply increase is poised to damp price gains while higher mortgage rates cut into demand.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
The Construction Industry Lost Jobs (No Surprise) but it Gained Some Too (Surprise)
October 12, 2020 —
Garret Murai - California Construction Law BlogThe announcement this week by major airlines and then by Disney that they will be laying off tens of thousands of workers is just the latest in what we already know: The coronavirus pandemic has adversely impacted workers around the world. And the construction industry is no exception, although its impacts have been uneven, and in some cases surprisingly good.
According to a report by the Associated General Contractors of America, 39 states lost construction jobs between August 2019 and August 2020 while 31 states and the District of Columbia added construction jobs between July and August 2020.
California saw the largest decline in construction jobs between August 2019 and August 2020, down 52,000 jobs or 5.8%, followed by by New York (-46,000 jobs/-11.3%), Texas (-39,300 jobs/-5.0%), Massachusetts (-20,200 jobs/-12.4%) and Illinois (-17,200/-7.5%).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Overtime! – When the Statute of Limitations Isn’t Game Over For Your Claim
August 07, 2022 —
Bradley E. Sands, Jones Walker LLP - ConsensusDocsStatutes of limitations establish the period of time within which a claimant must bring an action after it accrues. An action can be filing a lawsuit and, in some instances, filing a demand for arbitration. But a multi-year construction project could be longer than the applicable statute of limitations. For example, under Delaware or North Carolina law, the statute of limitations for a breach of contract is only three years.1 So a claim for breach of a construction contract that occurred (i.e. accrued) at the beginning of a four-year project under Delaware or North Carolina law may expire before the project is completed.
Generally, a claim accrues at the time of the breach (however, it is important to note that this is not always the case and claim accrual could be the subject of an entirely different article). During the course of a multi-year construction project, proposed change orders or claims for additional compensation can sit, unanswered or unpursued, for months. Or, the parties may informally agree as part of regular project communications to put off dealing with a claim head-on until the end of the project. On certain projects, slow-walking a claim is understandable, as a contractor may be hesitant to sue an owner in the middle of a multi-year project and risk upsetting an otherwise good working relationship. But a delay in formally asserting a put-off claim after it accrues could result in the claim falling subject to a statute of limitations defense.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP (ConsensusDocs)Mr. Sands may be contacted at
bsands@joneswalker.com
Condo Board May Be Negligent for not Filing Construction Defect Suit in a Timely Fashion
December 09, 2011 —
CDJ STAFFThe Maryland Court of Special Appeals has ruled that condominium association boards have a duty to “properly pursue any claims,” overturning the decision of a lower court that said that it had no legal duty to file suit. Tom Schild, writing at Marylandcondominiumlaw.net, writes about Greenstein v. Avalon Courts Six Condominium, Inc.
In this case, the condominium board waited six years after residents complained about water intrusion problems before suing the developer. The court ruled that the suit could not be filed, as the statute of limitations was only three years. After residents were assessed for the repairs, homeowners sued the board, arguing that their delay lead to the need for the special assessment.
After overturning the decision, the Court of Special Appeals has asked the trial court to review the negligence claim.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Instant Hotel Tower, But Is It Safe?
March 28, 2012 —
CDJ STAFFBroad Sustainable Building has leapfrogged in China’s construction boom by building a thirty-story hotel in just fifteen days in the city of Changsha. According to an article in the Los Angeles Times, most of the building was prefabricated, but most prefabricated buildings require a longer time for assembly. Broad claimed that it cut no corners on safety. However, Zhang Li, a Beijing architect, told the Times that “incredible speed also means incredible risk.”
At the completion date, the interior was still partially finished. Some rooms were furnished, while others weren’t quite so ready. The hotel will be used to house clients who are visiting Broad and some of its employees.
Broad called their process “the most profound innovation in human history” and predicted that soon a third of new buildings worldwide would be constructed this way. The company anticipates using the same process to build taller buildings, with hopes of eventually constructing a 150-story building.
China is currently undergoing a building boom which Zhang attributed to a desire to catch up to the developed world. As a result of this boom, he noted that building inspections are often skipped in China to speed up building.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
NYPD Investigating Two White Flags on Brooklyn Bridge
July 23, 2014 —
Chris Dolmetsch – BloombergThe New York City Police Department is trying to figure out who replaced the American flags that fly atop the Brooklyn Bridge with white banners.
The replacement flags were discovered this morning on the towers at opposite ends of the bridge, where the Stars and Stripes are normally displayed, and were removed, police said.
The NYPD’s Counterterrorism Bureau and Emergency Service Unit are probing the incident and reviewing surveillance video to determine who replaced the flags and when the act took place, police said.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Dolmetsch, BloombergMr. Dolmetsch may be contacted at
cdolmetsch@bloomberg.net
Measure of Damages in Negligent Procurement of Surety Bonds / Insurance
September 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesMy broker procured the wrong insurance and I am exposed to a loss. My broker failed to procure proper insurance and I am exposed to a loss. “Where the parties enter into an agreement to procure insurance and there is a negligent failure to do so, an insurance broker may be liable for damages.” The Lexington Club Community Association, Inc. v. Love Madison, Inc., 43 Fla.L.Weekly D1860a (Fla. 4th DCA 2018). The proper measure of damages in a negligent procurement of insurance claim is “what would have been covered had the insurance been properly obtained.” Id. quoting Gelsomino v. ACE Am. Ins. Co., 207 So.3d 288, 292 (Fla. 4th DCA 2016). This measure of damages in a negligent procurement of insurance claim is important because it is the measure of damages that dictates recoverable damages under this claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com