You Are on Notice: Failure to Comply With Contractual Notice Provisions Can Be Fatal to Your Claim
September 26, 2022 —
Jenifer B. Minsky - ConsensusDocsImagine your firm is the construction manager on a multi-million-dollar project. At the end of the project you are five million dollars out-of-pocket. You have a stack of claims for additional and extended work which led to the overrun, payment for which will easily cover the shortfall. However, the owner refuses to compensate you until you can satisfactorily answer their inquiry: “Where are the notices that are expressly required under the terms of the contract?” You had a good relationship with the owner’s field representative who was aware you were performing the work and understood that your company was compiling claims. The once cooperative owner, now suffering financial restraints of their own, is resolute in their refusal leaving you no choice but to expend substantial sums of money to litigate the claims, the success of which is far from assured.
What Contract Language Can Be A Trap For An Unwary Contractor?
While courts are generally hesitant to order a forfeiture and some courts disfavor condition precedents, a judge’s hands may be tied by particular contract language requiring the strict enforcement of notice requirements. Such provisions may include: (1) an explicit clause that there be precise compliance with notice requirements; (2) express consequences for noncompliance (e.g., if the required notice is not provided the claim will be waived, forfeited or abandoned); (3) a statement that the notice requirements are a condition precedent to recovery; (4) language such as “if,” “provided that,” “or else” or “on condition that” (e.g., the owner shall review the claim, “provided such claim” was received within the applicable notice period) or (5) prohibition of any waiver of the notice requirement. To the extent the notice provision includes such language, a contractor can be without recourse even when the owner has actual knowledge of the claims or cannot show prejudice by the lack of notice.
Read the court decisionRead the full story...Reprinted courtesy of
Jenifer B. Minsky, Peckar & Abramson, P.C.Ms. Minsky may be contacted at
jminsky@pecklaw.com
Duty to Defend Broadly Applies to Entire Action; Insured Need Not Apportion Defense Costs, Says Maryland Appeals Court
January 27, 2020 —
Michael S. Levine & Kevin V. Small - Hunton Insurance Recovery BlogIn a recent decision, the Maryland Court of Special Appeals reiterated that the duty to defend broadly requires a liability insurer to defend an entire lawsuit against its insured, even where only some of the allegations are potentially covered. The court further held that the insured has no obligation to apportion defense costs among multiple implicated policies. The decision, Selective Way Insurance Company v. Nationwide Property and Casualty Insurance Company, et al., can be found here.
The coverage litigation arose out of a construction defect case against a general contractor. The general contractor tendered the action to its insurer, Nationwide, which, in turn, filed a declaratory judgment action against the various insurers of construction project subcontractors that had named the general contractor as an additional insured. Ultimately, the court granted a summary judgment motion declaring that all of the subcontractors’ insurers had a duty to defend the general contractor “because the allegations in the underlying lawsuit raised claims that potentially arose from the [s]ubcontractors’ work at the [construction site].” All of the subcontractors’ insurers settled with Nationwide except for one, Selective Way; and the parties proceeded to a jury trial on various issues. The jury found for Nationwide on all issues. Selective Way appealed.
Selective Way argued on appeal that even if some of the allegations were covered under its policy, it had no obligation to defend the general contractor because its insureds, the subcontractors, could not have been responsible for all of the losses given the nature of their work. Further, Selective Way contended that if it was responsible for defending the general contractor, it was not responsible for the entire defense, and the general contractor was responsible for apportioning the costs among the various subcontractors. The panel disagreed on both points.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Kevin V. Small, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Architect Norman Foster Tells COP26: Change 'Traditional' City Design to Combat Climate Change
November 19, 2021 —
James Leggate - Engineering News-RecordRegaining control over the climate crisis will require a change in the way cities are designed and built, noted British architect Sir Norman Foster told global attendees at the
COP26 summit in Glasgow, Scotland, in a presentation with John Kerry, President Joe Biden's special climate envoy.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
If a Defect Occurs During Construction, Is It an "Occurrence?"
February 12, 2024 —
Brendan J. Witry - The Dispute ResolverEstablishing insurance coverage for construction defects is almost as important as establishing liability in the underlying construction defect litigation itself.
The risk to the defendant contractor of defending a construction claim can place significant burdens on a contractor’s operations and an uninsured judgment might even put the contractor out of business.
For owners, suing a contractor for construction defects can become academic if there is no prospect of insurance coverage; obtaining a $1 million judgment against a contractor with limited assets would be a pyrrhic victory.
Commercial General Liability (CGL) carriers are obligated to defend claims that potentially fall within the coverage granted by the policy.[1] When presented with a claim, CGL insurers typically have three options: (1) assume the defense without reservation; (2) assume the defense asserting defenses to coverage, and depending on the state, reserving the right to recover defense costs if it later determines there is no duty to defend; or (3) deny the claim outright and seek a declaratory judgment holding that the insurer has no duty to defend or indemnify. An insurer may deny the claim outright and not seek a declaratory judgment, but does so at its peril because it can expose the insurer to significant liability if the insured later shows the insurer in fact had a duty to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Delaware River Interstate Bridge Shut to Assess Truss Fracture
January 26, 2017 —
Justin Rice - Engineering News-RecordThe Delaware River Bridge, which runs between Pennsylvania and New Jersey, was shut down indefinitely over the Jan. 22-23 weekend, after a large fracture was discovered in the bridge that connects the turnpikes of the two states. The fracture on a steel truss below the bridge deck on the Pennsylvania side was discovered during a routine check as part of a painting operation. Steel plates were installed to temporarily reconnect the fracture and stabilize the 1.5-mile bridge, which is located in Bucks County on I-276 and accommodates 42,000 vehicles a day. As engineers assess how the damage will impact the entire bridge, a sample from the fractured truss was sent to a forensic lab to determine the cause of the crack. A high-definition video survey is being used to monitor the bridge.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com
Biden Administration Focus on Environmental Justice Raises Questions for Industry
March 22, 2021 —
Karen C. Bennett, Jane C. Luxton, Rose Quam-Wickham & William J. Walsh - Lewis BrisboisThe Biden Administration has left no doubt that it intends to prioritize environmental justice (EJ) in implementing energy and environmental policy. While EJ is not new – in fact, President Clinton signed the first EJ Executive Order (EO 12898) in 1994 – the new Administration’s plan to expand the concept to include “climate justice” and “health equity” is both novel and undefined. Similar to actions taken on climate change (see our previous alert from January 28), President Biden has announced plans for elevating EJ by designating new Cabinet level offices, intensifying enforcement, and advocating for Congressional action. Given the likelihood of serious impacts from these sweeping changes, industry will need to step up engagement as these concepts are integrated into regulatory decisions and U.S. positions globally.
Authority for addressing injustice caused by environmental pollution that disproportionately affects certain communities is found in Title VI of the Civil Rights Act of 1964. The Act imposed a responsibility on the Environmental Protection Agency (EPA or Agency) to ensure that its funds are not being used to subsidize discrimination, based on race, color, or national origin, making EPA’s Office of Civil Rights responsible for the investigation and enforcement of Title VI within the Agency. President Clinton relied on this authority in signing EO 12898, which directed federal agencies to identify and address disproportionately high adverse human health and environmental effects of their programs, policies, and activities on minority and, going beyond the protections covered by Title VI, low-income populations.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois,
Jane C. Luxton, Lewis Brisbois,
Rose Quam-Wickham, Lewis Brisbois and
William J. Walsh, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Quam-Wickham may be contacted at Rose.QuamWickham@lewisbrisbois.com
Mr. Walsh may be contacted at William.Walsh@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Unpaid Hurricane Maria Insurance Claims, New Laws in Puerto Rico, and the Lesson for all Policyholders
January 09, 2019 —
Walter J. Andrews & Cary D. Steklof - Hunton Andrews KurthPuerto Rico’s dire insurance situation more than a year after Hurricane Maria remains a constant reminder of why policyholders must diligently pursue their property and business interruption claims in the immediate aftermath of a storm. The numbers are staggering. On an island the approximate size of Connecticut, Hurricane Maria caused an estimated $100 billion in damage. According to the Office of the Insurance Commissioner of Puerto Rico, the hurricane resulted in more than 287,000 insurance claims. Roughly 11,000 of those claims, representing an estimated $2 billion in losses, remain unresolved.
Reprinted courtesy of
Walter J. Andrews , Hunton Andrews Kurth and
Cary D. Steklof , Hunton Andrews Kurth
Mr. Andrews may be contacted at wandrews@HuntonAK.com
Mr. Steklof may be contacted at csteklof@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Development in CBF Green Building Case in Maryland
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsRemember that case I discussed a while back relating to the Chesapeake Bay Foundation (CBF) building in Annapolis, Maryland? Remember how it was a lawsuit over parallams and failure of those parallams? Do you even remember what a parallam is?
Well, that case was initially dismissed upon the Defendant’s Motion for Summary Judgment because the trial court determined that CBF did not file its lawsuit within the proper time frame after notice of the potential failure of the building materials. Of course, CBF appealed to the Fourth Circuit Court of Appeals under the caption The Chesapeake Bay Foundation, Inc., et. al. v. Weyerhaeuser Company (4th Circuit).
After a great review of the facts of the case, the engineering inspections and reports at issue and the trial court’s ruling, the Fourth Circuit vacated the dismissal and remanded the case for further proceedings. The Court of Appeals reasoned that the district court jumped the gun in dismissing the lawsuit so early in the process because:
a genuine dispute exists as to whether knowledge of the water infiltration problem would have put a reasonable person on notice that the Parallams were susceptible to premature deterioration and that their PolyClear 2000 treatment would not preserve them.
In short, the court ruled that the engineering reports relating to moisture issues would have put CBF on notice of the particular issue of deterioration that was at issue in the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at