The United States Court of Appeals, Fourth Circuit, Finds Wrap-Up Exclusion Does Not Bar Coverage of Additional Insureds
February 18, 2020 —
Callie E. Waers - Florida Construction Law NewsThe United States Court of Appeals, Fourth Circuit, recently took a close look at the application of a “controlled insurance program exclusion” (wrap-up exclusion) to additional insureds on a commercial general liability policy. In Cont’l Cas. Co. v. Amerisure Ins. Co., 886 F.3d 366 (4th Cir. 2018), the Fourth Circuit examined the interplay of an enrolled party’s additional insured status on an unenrolled party’s commercial general liability (“CGL”) policy with a wrap-up exclusion. The court applied North Carolina law and found that pursuant to the policy’s own language, the exclusion only applied to the original named insured, not the additional insureds.
The case arose out of an injury incurred by an employee of a second-tier subcontractor during the construction of a hospital. On this particular project, the owner maintained a “rolling owner controlled insurance program” (wrap-up insurance program) in which all tiers of contractors were required to enroll, but enrollment was not automatic. The general contractor was enrolled in the owner’s wrap-up policy, but neither the steel manufacturer subcontractor nor its sub-subcontractor, the steel installation company, were enrolled. The underlying plaintiff was injured while he was an employee of the steel installation company, but he did not name his employer in his personal injury lawsuit.
The Cont’l Cas. Co. case was instituted by Continental Casualty Company (“Continental”) after it defended and settled the underlying plaintiff’s claims against its insured and additional insured, the steel manufacturer and general contractor, respectively. Continental sought to be reimbursed for the $1.7 million settlement and attorneys’ fees and costs incurred for the defense and indemnity of the underlying lawsuit.
Continental alleged that Amerisure Insurance Company (“Amerisure”) breached its duty to defend and Amerisure’s policy provided the primary coverage for both the general contractor and steel manufacturer, who were additional insureds on the Amerisure policy. Amerisure denied a duty to defend the additional insureds based on the presence of the wrap-up exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
Ryan.Charlson@csklegal.com
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
Housing Inflation Begins to Rise
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Kathleen Madigan writing for The Wall Street Journal, “inflation remains muted at the start of 2014” except in one category: housing. Madigan stated that housing costs were “worth watching.”
The “owners’ equivalent rent index had been rising at a steady pace through most of 2012 and 2013, with 12-month percent changes hovering around 2%” however, “the pace picked up” at the end of last year.
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Assume Your Insurance Covers A Newly Acquired Company
February 19, 2019 —
Patrick M. McDermott & Michael S. Levine - Hunton Insurance Recovery BlogThe Supreme Court of Virginia’s decision yesterday finding no coverage for fire damage to a building is a cautionary tale for companies acquiring other companies. Erie Ins. Exch. v. EPC MD 15, LLC, 2019 WL 238168 (Va. Jan. 17, 2019). In that case, Erie Insurance issued a property insurance policy to EPC. The policy covered EPC only and did not cover any subsidiaries of EPC. EPC then acquired the sole member interest in Cyrus Square, LLC. Following the acquisition, fire damaged a building that Cyrus Square owned.
EPC sought coverage under its property insurance policy. Because the policy did not cover Cyrus Square, EPC argued that a provision extending coverage to “newly acquired buildings” applied, contending that EPC had newly acquired Cyrus Square’s building by virtue of becoming the sole member interest in the LLC. Based on the law relative to LLCs and its interpretation of the policy, the Supreme Court of Virginia ruled against EPC. It found that although EPC had acquired Cyrus Square, it had not “newly acquired” the building and so the “newly acquired buildings” coverage extension did not apply.
Reprinted courtesy of
Patrick M. McDermott, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Continuous Injury Trigger Applied to Property Loss
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Seventh Circuit Court of Appeals predicted that the Wisconsin appellate courts would apply the continuous injury trigger to find coverage after the policy expired for damage caused by water infiltration. Strauss v. Chubb Indem. Ins. Co., 2014 U.S. App LEXIS 21794 (7th Cir. Nov. 18, 2014).
The insureds built their home in 1994. They purchased coverage for their home from Chubb. Coverage was in place from October 1994 through October 2005. The policy stated that coverage was limited "only to occurrences that take place while this policy is in effect." "Occurrence" was defined as "a loss or accident to which this insurance applies occurring within the policy period. Continuous or repeated exposure to substantially the same general conditions unless excluded is considered to be one occurrence."
In October 2010, the insureds discovered that water infiltration had been causing damage within the building envelope of the home. The infiltration was ongoing, beginning around the time of original construction and continuously occurring with each subsequent rainfall. Chubb denied coverage because the damage was not discovered during any of their policy periods.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Summary Judgment in Favor of General Contractor Under Privette Doctrine Overturned: Lessons Learned
March 27, 2023 —
Garret Murai - California Construction Law BlogIt seems like we’ve been seeing a lot of Privette doctrine cases recently. Here’s another,
Brown v. Beach House Design & Development, 85 Cal.App.5th 516 (2002), which provides a cautionary tale for general contractors to watch what they include in their scope of work and how they manage projects.
The Beach House Case
Kyle Brown was a carpenter employed by subcontractor O’Rourke Construction, Inc. who contracted with general contractor Beach House Design and Development to provide finish carpentry on a construction project. A&D Plastering Co., another subcontractor on the project, had erected scaffolding on the project.
On June 16, 2017, while using A&D’s scaffolding, Brown fell onto a concrete walkway where he suffered severe injuries. Following the accident, Beach House and A&D inspected the scaffolding and found that some of the scaffolding was not properly secured to the building and that planks, crossbars, ties and guardrails had been cut or were missing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Visual Construction Diaries – Interview with Jeff Sassinsky of Fovea Aero
November 30, 2017 —
Aarni Heiskanen - AEC BusinessJeff Sassinsky, President of Fovea Aero, gave me a live demonstration on Fovea Aero Vision – an app that allows you to a get a fully immersive visual construction diary of your project.
The idea for the development of Fovea Aero Vision came from discussions with general contractors, owners, and other construction industry professionals. They were talking about the use of smartphones, particularly phone cameras, in construction. The photos, for example, of a fitting that does not look right end up in a folder on a server or goes back and forth in email messages. “The lack of any structure behind both the collection and the storage and sharing of the photos is hampering their usage,” Jeff said. “We wanted to solve the problem by creating a full record of everything that takes place on a construction site, on a regular basis, sharing it among the stakeholders, and making it super easy to use.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi